12th Change Order 08/17/2022 CONTRACT CHANGE ORDER PROJECT TITLE: Marathon International Airport CHANGE ORDER : 1 Terminal Re-Roof Project INITIATION :August 16,2022 TO CONTRACTOR: CONTRACT DATE: arch 17, 2021 The Contract is changed as follows: The original (Contract Sum)(Guaranteed Maximum Price)................. ........................ 1,888,375.00 Net change by previously authorized Change Orders........................ .......................... $ 0.00 The(Contract Sum) (Guaranteed Maximum Price)prior to this Change order was.............$1.888,375.00 The(Contract Sum)(Guaranteed Maximum Price)will be(increas )(decreased) (unchanged)by this Change Order.......$ The new(Contract Sum)_(Guarante Maximum Price) including this Change Order is....... $ 1,888,375.00 The Contract Time will be iincreased}(decreased)(unchanpl by............................... 30 days The date of Substantial Completion as of the date of this Change Order is....................... September 15,2022 Detailed description of change order and justification: This change order Is for Final Completion Time Extension 94 requestedin order to compile final closeout documents and attain all final inspections. This Change Order is 0. 1°1 of the original contract price. Not valid until sinned by Owner,ArchiLqgt(if nllca l ),and Contractor ARCHITECT: F F�K] Date CONTRACTOR: Marino Construction Group,Inc. - tlt - - POS- DIRECTOR OF AIRPORTS "" °' °°"""" E.15.22 Date MONROE COUNTY: .... 08/17/2022 Ast,ICoun : Adtirr " '� . ty rnistrator Date NROE IQ)r!E is FORMRI�EY PIED O J._MERCA AS`SISTA LINTY ATTORNEY Date 116/22 Change Order Attachment per Monroe County Code Section 2-58(b) - Change Order was not included in the original contract specifications. Yes( X) No If Yes, explanation: This change order Is for Final Completion Time Extension 04 requested In order to comp lie final closeout documents and aftain all final Inspections. � Change Order was included in the original specifications. Yes No ( X If Yes, explanation of increase in price: - Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes No )Q If Yes, explanation as to why it is not subject for a calling for bids: - Project architect approves the change order. Yes(X ) No If no,explanation of why: - Change Order is correcting an error or omission in design document. Yes No X Should a claim under the applicable professional liability policy be made? Yes No( X Explain: Change Order Attachment per Monroe County Code Section 2-51)(b) Change Order was not included in the original contract specifications. Yes ( X) No If Yes, explanation-, This change order Is for Final Completion Time Extension #4 requested in order to compile final closeout documents and attain all final inspections, Change Order was included in the original specifications. Yes y No ( X If Yes, explanation of increase in price; Change Order exceeds$50,000 or 5%of contract price(whichever isgreater).Yes No X) If Yes, explanation as to why it is not subject for a calling for bids: Project architect approves the change order. Yes(X ) No If no,explanation of why-, Change Order is correcting an error or ornission in design document. Yes No, X Should a claim under the applicable professional liability policy be made'? Yes No ( X Explain