12th Change Order 08/17/2022 CONTRACT CHANGE ORDER
PROJECT TITLE: Marathon International Airport CHANGE ORDER : 1
Terminal Re-Roof Project
INITIATION :August 16,2022
TO CONTRACTOR: CONTRACT DATE: arch 17, 2021
The Contract is changed as follows:
The original (Contract Sum)(Guaranteed Maximum Price)................. ........................ 1,888,375.00
Net change by previously authorized Change Orders........................ .......................... $ 0.00
The(Contract Sum) (Guaranteed Maximum Price)prior to this Change order was.............$1.888,375.00
The(Contract Sum)(Guaranteed Maximum Price)will be(increas )(decreased)
(unchanged)by this Change Order.......$
The new(Contract Sum)_(Guarante Maximum Price) including this Change Order is....... $ 1,888,375.00
The Contract Time will be iincreased}(decreased)(unchanpl by............................... 30 days
The date of Substantial Completion as of the date of this Change Order is....................... September 15,2022
Detailed description of change order and justification:
This change order Is for Final Completion Time Extension 94 requestedin order to compile final
closeout documents and attain all final inspections.
This Change Order is 0. 1°1 of the original contract price.
Not valid until sinned by Owner,ArchiLqgt(if nllca l ),and Contractor
ARCHITECT: F F�K]
Date
CONTRACTOR: Marino Construction Group,Inc. - tlt - -
POS-
DIRECTOR OF AIRPORTS "" °' °°"""" E.15.22
Date
MONROE COUNTY: .... 08/17/2022
Ast,ICoun : Adtirr " '�
. ty
rnistrator Date
NROE IQ)r!E is FORMRI�EY
PIED O J._MERCA
AS`SISTA LINTY ATTORNEY
Date 116/22
Change Order Attachment per Monroe County Code Section 2-58(b)
- Change Order was not included in the original contract specifications. Yes( X) No
If Yes, explanation:
This change order Is for Final Completion Time Extension 04 requested In order to comp lie final
closeout documents and aftain all final Inspections.
� Change Order was included in the original specifications. Yes No ( X
If Yes, explanation of increase in price:
- Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes No )Q
If Yes, explanation as to why it is not subject for a calling for bids:
- Project architect approves the change order. Yes(X ) No
If no,explanation of why:
- Change Order is correcting an error or omission in design document. Yes No X
Should a claim under the applicable professional liability policy be made? Yes No( X
Explain:
Change Order Attachment per Monroe County Code Section 2-51)(b)
Change Order was not included in the original contract specifications. Yes ( X) No
If Yes, explanation-,
This change order Is for Final Completion Time Extension #4 requested in order to compile final
closeout documents and attain all final inspections,
Change Order was included in the original specifications. Yes y No ( X
If Yes, explanation of increase in price;
Change Order exceeds$50,000 or 5%of contract price(whichever isgreater).Yes No X)
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes(X ) No
If no,explanation of why-,
Change Order is correcting an error or ornission in design document. Yes No, X
Should a claim under the applicable professional liability policy be made'? Yes No ( X
Explain