2022-14 Runway Pavement Evaluation MASTER AGREEMENT FOR PROFESSIONAL SERVICES TASK ORDER FORM Effective Date Upon Execution Task Order No. 2022 - 14 Client Project No. .404-63001-SC_00038 Engineer Project No. _EGXM7907 This Task Order is entered into on the effective date noted above pursuant to the "Master Agreement for Professional Services" between Monroe County, Florida ("Client") and JACOBS PROJECT MANAGEMENT CO. ("Consultant"), dated February 16, 2022 ("Agreement"). The Agreement is incorporated herein and forms an integral part of this Task Order. Services Authorized—EYW Runway Pavement Evaluation—Amendment 1 Client authorizes Consultant to perform the Services described in Exhibit A attached hereto and incorporated herein, which Exhibit A is marked with the above noted Task Order No. and consists of 1 page(s). Pricing N/A Time and Expense per Agreement and Appendix B to the Agreement. X Firm Fixed Price of$ 3,854.00 N/A Other(Describe): NPOE COUNTY ATTonN JY, IAPPI)IOV PT Schedule F OR M Services may commence on Execution WAM— Services will cease by 547 hi vs A88t T A ;r RN Date 9/15/22 Recommended by: Approved by: P _ l irectrar�o Airports Date: 9.15.22 - Asst./County Ad I'll Date 09.19.2022 CONSULTANT: JACOBS PROJECT MANAGEMENT CO Jeffrey D. ' y s 'by Jeffrey D. DAi° r�gYay D.A cton, =US, JoaActon enMlx„dr0fg Adon@Jecohe cam Jacqueline � �m n �w�m r-easml" Date MA-Se�Y� ���:amv�+Jnuxwa�Hmra����0��. _ 0-Jaw"knyp�rmermir*{g mrmmll 9maquut+m+a;,n��jkwwwohn ramp Witness Ross MW 2W210,130802Ti0,04 0' TitleS Region PM/CM Services Group Leader File: MSTR APS—Monroe County Page 1 of 1 Exhibit A-(2022-14) Scope of Services Monroe County Airports Key West International Airport(EYW) R nt Ev i n- me ~r 1 SCOPE OF WORK This scope of services is an amendment to PSO 2022-07.The original scope of services included three (3) pavement cores to investigate the existing pavement condition.After further investigation,it was determined that additional pavement cores are required to complete the pavement evaluation.This scope of services includes an additional twelve(12) pavement cores completed by Tierra South Florida. K� 141 l Xd.fM9— 4 � wr ry ��"' y� A RH M^4Yf,B 56.wi ,u M r ...................., ... .000.,a. .....m..... �....... ,.,. ..............,...---ram.,. Figure 1.EYW Runway Pavement Failures GENERAL SCOPE For this scope of services,Jacobs will provide the following services: 1. Coordination with subconsultants. ASSUMPTION51DESIGNA A E . 1. This proposal does not include submittal of design documents,cost estimates,or technical specifications. 2. This scope of work does not include bid support,construction administration,resident project representative nor quality assurance testing. This scope of work also does not include the development of a construction management plan. 3. This project does not include financial feasibility analyses,benefit-cost analyses,return on investment nor payback period estimations. 4. Jacobs will reasonably rely upon the accuracy,and completeness of the information/data provided by the Client or other third parties. 5. In providing opinions of cost,financial analyses,economic feasibility projections,for the project,Jacobs has no control over cost or price of labor and materials;unknown or latent Page 1 of 2 conditions of existing equipment or structures that may affect operation or maintenance costs;competitive bidding procedures and market conditions;time or quality of performance by operating personnel or third parties;and other economic and operational factors that may materially affect the ultimate project cost or schedule.Therefore,Jacobs makes no warranty that Client's actual project costs,financial aspects,economic feasibility,will not vary from Jacobs'opinions,analyses,projections,or estimates. 6. In soils,foundation,groundwater,and other subsurface investigations,the actual characteristics may vary significantly between successive test points and sample intervals and at locations other than where observations,exploration,and investigations have been made. Because of the inherent uncertainties in subsurface evaluations,changed or unanticipated underground conditions may occur that could affect total project cost and/or execution. These conditions and cost/execution effects are not the responsibility of Jacobs. 7. Jacobs shall at no time take title,risk of loss or ownership of the hazardous materials or wastes. Client recognizes that Jacobs assumes no risk and/or liability for hazardous materials encountered while performing any services associated with such hazardous waste. 8. Monroe County will provide access to all project areas. ARTICLE A-DATA COLLECTION AND REHABILITATION PLAN 1. Coordinate with subconsultants. 2. Perform additional pavement cores at the locations shown in Figure 1.These services will be completed by Tierra South Florida. Services for Article A will be provided under a lump sum basis. PROJECT30EP The tentative project schedule from the Notice to Proceed date will be as follows: Data Collection 15 days from NTP Page 2 of 2 lot JOB HOUR AND FEE ESTIMATE uplacobs Monroe County Airport: Key West International Airport Project: RUnway Paymnt Evaluation-A_m2ndment I FEE SUMMARY BASIC SERVICES Hours Fee DBE AMOUNT Article A:Data Collection 4 $ 510 Total 13mir,Ser-Oces Lump Sum Fee 4 510 SITC1/1 LSFIi VICES Hours Fee DBE AMOUNT Article A:Data Collection Tierra South Florida $ 3,344 $ 3,344 ITotal Smial Services Lump Sum Fee 0 $ 3,344 $ TOTAL L.UMPSUM PROJECT FEE 4 S 3,SS4 $ 3,344 DBE Percentage 8677%