1st Change Order 11/15/2022 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Key West Lighthouse Oil Display &Tower Repairs CHANGE ORDER NO: 01 INITIATION DATE: 10/07/2022 CONTRACT DATE: 08/17/2022 TO CONTRACTOR: Marino Construction Group 7025 Shrimp Rd. suite 2E Key West, FL. 33040 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)..................................... $282,820.00 Net change by previously authorized Change Orders....... ...................... ............... ..... $0.00 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was....... $282,820.00 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order................... $0.00 The new(Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $282,820.00 The Contract Time will be (increased) (decreased) (unchanged) by.................. ........ 177 days The date of Substantial Completion as of the date of this Change Order is ................. 8/07/2023 Detailed description of change order and justification: At the request of the Key West Art&Historical Society(KINAHS), the anticipated construction commencement date of September 13, 2022 has been postponed until April 10, 2023. The original construction start date for the project occurred at the beginning of the busy season for the Key West Lighthouse attraction and would have had a detrimental impact on revenue expected during this timeframe. As such, while the Notice to Proceed will remain September 13, 2022, to accommodate preconstruction activities and submittals, the Contractor and KWAHS have mutually agreed to push the construction mobilization date back to April 10, 2023, without any increase to the construction budget. The Contractor was contractually granted 120 days to complete construction. Therefore, the substantial completion date will be moved from January 10, 2023, to August 7, 2023. This delayed mobilization allows time for project completion prior to the TDC grant expiration date of September 30, 2023. Change order is 0%of original contract price. Not valid until signed by Owner,Architect(if applicable). a Contra I/ - /, / . ,AD J.S44A k 4 V AR9714'; ARCHITECT: 1 /'1/22 o' David, Date CONTRACTOR: Marino Construction Date ligita Ily signed by Ca ry Knight DEPARTMENT DIRECTOR: Cary Knight Date:2022.11.15 15:32:40-05'00' Cary Knight Date Kevin G.Wilson,P.E. 2022.11.15 16:27:07-05'00' COUNTY/ASSISTANT ADMINISTRATOR: Roman Gastesi Date Kevin Wilson Change Order Attachment per Ordinance No. 024-2015 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Time extension to facilitate project completion outside of peak tourist season at the request of KWAHS. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: