6th Change Order 01/05/2023 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Big Pine Sheriff's House Replacement CHANGE ORDER NO: 06
INITIATION DATE: 01/05/2023
CONTRACT DATE: 10/21/2020
TO CONTRACTOR:
SeaTech of the Florida Keys, Inc.
131 Palomino Horse Trail
Big Pine Key, FL 33043
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)........................................ $747,125.00
Net change by previously authorized Change Orders...................................................... $161,884.37
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was...,,.... $909,009.37
The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order..................... $0.00
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is... $909,009.37
The Contract Time will be (increased) (decreased) (unchanged) by............................. 35 days
The date of Substantial Completion as of the date of this Change Order is .................. 01/14/2023
Detailed description of change order and justification:
The contractor is requesting a change order for a 35-day time only due to unforeseen personnel changes.
The previous substantial completion date was 1211012022. The new substantial completion date is
0111412023.
Change order is 0.00% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
ARCHITECT: Not applicable
Date
CONTRACTOR: �d6 ��142CNP.cL 1/5/2023
SeaTech of a Florida 166ys Date
Cary Knight Digitally signed by Cary Knight
DEPARTMENT DIRECTOR: Date:2023.01.0515:39:15-05'00'
Cary Knight Date
P Kevin G.Wilson,P.E.
A
COUNTY/ASSISTANT ADMINISTRATOR: 2023.01.05 16:59:41 -05'00'
Roman Gastesi Date
Kevin Wilson
Change Order Attachment per Ordinance No. 024-2015
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Superintendent no longer works for SeaTech. Time was lost while SeaTech
retained an alternate Superintendent.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ❑ No
If no, explanation of why: No architect on file.
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
542:
i ini�c
December 9, 2022
Attn: Matt Howard
Monroe County Project Mgmt.
1100 Simonton St
Key West, FL 33040
Re: Big Pine Sheriff House Replacement
Subj ect: Time Extension
Dear Mr. Howard,
Sea Tech is requesting a Thirty-Five (35) day no cost time extension to our contract. We
have had delays due to staffing issues. We have obtained adequate staff to continue moving
forward and anticipate being substantially completed by January 13, 2023.
Sea Tech has every intention of accelerating the work progress to reduce the time
indicated on the project schedule. Please advise if you need additional information. I may be
reached at(305) 872-0888.
Sincerely,
/�yc ZaC
Ryon LaChapelle
Project Manager