3rd Change Order 01/05/2023 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: Hurricane Irma Boca Chica Road Roadway Repairs Project
CHANGE ORDER NO: 3
INITIATION DATER/20/23
TO CONTRACTOR: American Empire Builders, Inc. CONTRACT DATE: 5/18/22
The Contract is changed as follows:
The original Contract Sum ........................................................................................$1,100,007.95
Net change by previously authorized Change Orders......................................... .............-$311,220.51
The Contract Sum prior to this Change order was...........................................................$1,411,228.46
The Contract Sum is unchanged by this Change Order#3 ...........................................................$0.00
The Revised Contract Sum including this Change Order..................................................$1,411,228.46
The Contract Time will be increased by ..............................................................................175 days
The Date of Substantial Completion as of the date of this change order is .................................7/14/2023
The Contractor has requested a change order for 175-day time extension due to extra work encountered from
Hurricane Ian. The previous substantial completion date was January 20t", 2022. The new substantial completion date
is 7/14/2023.
Change Order is 0.00% of original contract price.
Antonio M Digitally signed by Antonio M
Gonzalez
Gonzalez Date:2023.01.0414:47:17
CONTRACTOR -05'00'
Date
ENGINEERING SERVICES DIRECTOR Judith Clarke,P.E. e:202 01.051102'24-05`00'
r Kevin G.Wilson,P.E. Date
ASSISTANT COUNTY ADMINISTRATOR � ,��...�'�����Ar 2023.01.05 16:58:02-05'00'
Date
Md(9ddROECOUNrY ATPlb6t'MY
CX H'P INE3 LIMBERT-BARROWS
ASSMANT COUNTY ATTORNEY
DA:1T^"
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
Change Order#2 is needed for hurricane damage to jobsite from resulting directly from Hurricane Ian.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project engineer/architect approves the change order. Yes ® No ❑
If no, explanation of why: N/A
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
An
Am
P AEEI
69 FIM,7MIN,1 American Empire Builders,Inc. 13775 SW 145 TH CT.,SUITE B., MIAMI, FL. 33186
OFFICE: 305-261-9276/FAX: 305-261-9210
January 4, 2023
County: MONROE COUNTY, FLORIDA
Project Name: Hurricane Irma Boca Chica Road Repairs Project
Subject: AEB Request for Additional Days Due to Hurricane lan, and Additional Work
Due to delays outside ofthe control of American Empire Builders, Inc. as well as the addition ofnew scope
ofwork,we are kindly requesting the addition of one hundred and seventy five days to the contract schedule.
Sincerely,
Antonio M.donzalez, silent
American Empire uilc s, Inc.