RE: Notice to Proceed - Construction:
Key West International Airport Noise Insulation Program
Construction of Key West bythe Sea Final Phase
Project No. 404-630222
Dear Mr. Masch:.
Please consider this letter as Notice to Proceed with Construction for the above contract dated
September 21, 2022.
The Program Manager has approved the schedule and has confirmed that the Contractor has a
minimum of two (2) weeks of materials stored on site and has obtained all the necessary permits.
A Pre-Construction Meeting will be held on Monday,January 23, 2023,at 10:00 am, at the Jobsite Trailer.
Pursuant to Special Provision No. 2, the Construction and Post Construction Closeout Contract Time
of 140 Calendar Days will begin on Tuesday, January 24, 2023, the effective date of this Notice to
Proceed for Construction.
It is expected the Contractor will begin construction on January 24, 2023.
If you have any questions, please contact me.
Richard Strickland
Director of Airports
305.393.7742
XC: Deborah Lagos,ANPC, Deborah Murphy Lagos&Associates
Steve Vecchi, Project Manager,THC
Richard Sun, NIP Construction Manager,The Sun Group