2022-32 General Consulting MASTER AGREEMENT FOR PROFESSIONAL SERVICES
TASK ORDER FORM
Effective Date Upon Execution Task Order No. 2022 - 32
Client Project No.404-630203-SC_00038 G1 04) Engineer Project No. EGXM7905
This Task Order is entered into on the effective date noted above pursuant to the "Master
Agreement for Professional Services" between Monroe County, Florida ("Client") and JACOBS
PROJECT MANAGEMENT CO. ("Consultant"), dated February 24, 2022 ("Agreement"). The
Agreement is incorporated herein and forms an integral part of this Task Order.
Services Authorized—General Consulting Services—Key West International Airport
Client authorizes Consultant to perform the Services described in Exhibit A attached hereto and
incorporated herein, which Exhibit A is marked with the above noted Task Order No. and
consists of— I page(s).
Pricing
N/A Time and Expense per Agreement and Appendix B to the Agreement.
X Firm Fixed Price of 49 72.00
N/A Other(Describe):
rrRoE COUNTY ATTOnNEY
Schedule e.Tk ,
l ecution _. sc Ea a j�e r�oo-----_'-
Services may commence on _ unory�a
Services will cease by 730 days tip 2/21/2023
Recommended by: Approved by:
A �.........
0irecto ortsD: 2.21.2023 Asst./County instr � .2023
CONSULTANT: JACOBS PROJECT MANAGEMENT CO
Digitallynui medbyJecquellne By
Jacqueline Roes _ --..... ......
�+�+ DN.cn=„lec4u�wline Ross,c=US,o
ROSS da�b�[ &0 rm0,asXOM
Witness °° �"rv°° � ' '"gym Title Director
i7�aw 202"1 Q 08 M 7V-05'00'
File: MSTR APS—Monroe County
Page 1 of 1
Exhibit A-Scope of Work (2022 - 32)
Monroe County
General Consulting Services - Key West International Airport
Jacobs Project Management Company will provide the following services:
Overview
The Key West International Airport will need on occasion consulting outside of established
projects. The type of consulting services are outlined in the Master Agreement dated February
24, 2022 and will be requested by the Monroe County Airport Director on an as needed basis.
This scope of services identifies the elements and tasks Jacobs Project Management Company
will provide as support services for Monroe County Airport.
Tasks
1. Provide professional engineering and planning services for Key West International Airport
on an as needed basis that does not exceed the total value of this task order;
2. Deliverables from these services may include drawings, specifications or white papers;
3. Attend Project Update Meetings as requested;
4. Tasks will not be performed without prior approval from the Airport Director;
5. Jacobs Project Management Co.will invoice on a percent complete, including expenses,to
compensate the level of effort required for each assignment.
Page 1 of 1
JACOBS ENGINEERING GROUP JOB HOUR AND FEE ESTIMATE
Monroe County Airports
Airport:
Key West International Airport
Project:
General Consulting Services-Key West International Airport(2022-32)
FEE SUMMARY
BASIC ggRVIC Hours Fee DBE AMOUNT
Article A:General Consulting 353 $ 49,872
Total Basic Services Lump Sum Fee 353 $ 49,872
'PEgAL SffRJd(Z
Hours Fee
Total Special Services Lump Sum Fee $ $
ITOTAL LUMP SUM PROJECT FEE 353 $ 49,872 $ -
DBE Percentage 0.00%
.kW,p.ftk-M0NR0E COON TYTSO'.t-2.023 PSO'.\PSO 32-EYW-GEMPSO 932 G-1.1 C....Ibla F..A.