Loading...
14th Change Order 03/01/2023 MONROE COUNTYANGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Plantation Key Courthouse & Detention Center CHANGE ORDER NO: 014 INITIATION DATE: 01/31/2023 CONTRACT DATE: 12,/13/2017 TO CONTRACTOR: Biltmore Construction Company 1055 Ponce De Leon Blvd. Belleair, Florida 33756, The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum (Price)..................................... $32,818,441.14 Net change by previously authorized Amendments............................................... $2,231,070.34 Net change by previously authorized Change Orders............. ........................... ($3,182,136.07) The (Contract Sum)(Guaranteed Maximum Price) prior to this Change order was....... $31,867,375.41 The (Contract Sum) (Guaranteed Maximum Price)will be (increased), (decreased) (unchanged) by this Change Order........—.....— $0.00 The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is.. $31,867,375A1 The Contract Time will be (increased) (decreased) (unchanged) by..—-—................. 910 days The date of Substantial Completion as of the date of this Change Order is ................. 03/31/2023 Detailed description of change order and justification: The County is currentIV in the process of redes0ning the Detention Center AC sVstem at the request o the MCSO. A building permit for the nevi work was not received until Janua1y 2023 necessitating an extension of the substantial completion, The substantial completion date has been extended from December 31, 2022, to March 31, 2023, with an expected final completion 30 daVs after this substantial completion. Change order is 0.0% of or9qjnal contract price. Not valid until signed by Owner, Architect if applicable), and Contractor ARCHITECT: January 31,2023 Currie Sowards Aguila Architects, Inc. Date CONTRACTOR: /Oz�' Biltmore Construction Company Datid Digitally signed by Cary Knight Cary Knight Date:2023.02.27 10:49:53 DEPARTMENT DIRECTOR: -05'00' Cary Knight Date Kevin G.Wilson,P.E. COUNTY/ASSISTANT ADMIINISTRATOR: 2023.03.01 17:22:31 -05'00' Roman Gastesi Date Kevin Wilson Change Order Attachment per Ordinance No. 024-2015 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The substantial completion date needed to be extended due to changes in the scope of work. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ®No ❑ Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: While the initial design was not consistently cooling to the desired design temperatures, the County is taking this opportunity to upgrade the dormitory AC system to achieve the MCSO's desired functionality. Erickson-Breanne From: Leonard Anderson <LAnderson@BiltmoreFL.com> Sent: Friday,January 13, 2023 10:18 AM To: Howard-Matthew Cc: Erickson-Breanne;Travis Parker;Jeff Parker;Jennifer Lederhouse; Knight-Cary; Wilson-Kevin; 'Keith Beal';Jose Aguila; Paul Rankin Subject: RE: Revised Change Order#13 - PK Courthouse -time extension 12/31/22 to 3/31/2023 Attachments: PKJCHDF DORM COOLING-LIGHTING-CAMERA WORK SCHEDULE 1-13-2023.pdf CAUTION:This email originated from outside of the County. Whether you know the sender or not, do not click links or open attachments you were not expecting. Mathew, Please find the attached project work schedule to modify the dormitory cooling, lighting relocation, and isolation cell camera relocation work. Consider this our request for additional no cost time extension from 12/31/2022 to 3/31/2023 to perform the referenced work. Thank you, Biltmore Construction Pi,ojed V i,,�agei, e: Ai,,�(Ieia soi,,�@I'rIIhrrioi,e 1.corri I w:www,lolll Ilion ecoi,,�sti, rr,t oi,,i.corrii a. �.0,15 Poi,,lce(I e I.veoi,,1 ?,s vd, L',R, ea iI,, 33 7'15 I his Oko,II fn I I`la l Isinissio I Inay f,oIIII al I II1 orina o II hlh rich is co d'IdcIII a al"ld rn ll/I I hri dorirlaI of"1 IaI1;nnI (o, is II11(oldcd ton IY'['1nr Ihr,pc l";dn1 o r I II Y I h1h rich II i Odd I'(,93;Wd If You ar(1 I I o I':hr,II1I(,I 1 dcd r(o'llpic 11 aI1Y I1,A/I9;i�,J,l,I(,I r a II;4Irll;,;nrd l'1,dlmwl n I I 1 a I:I r n 11 nr o I hw r ww o[,o r ICY dII1g o[aI1Y acI oI1 II1 I(,I1al"Iu, uroII,':his IIdC'7Ir Ina k)I1 by pc r so I I S oI 1,I1:I'I cs o I hwI, 'IhaI1 Iht'f II'1I(oldcd Ir(o'llpicIII is pI,ohIhIICSf, If You r(o,t,I"wd I:his IICYIISlYlISSI+I1 II1 Gr7rro 1, 01CO;W co n1IacI'.':h sclldcr and dcIcI(,Ihr,Ina'',:(,I1aI [1,0111 0I1 Y Sys I(7 I n Iha I U)ll1011"1;,II,II1cIu,iI1g hu I I"IoI IIIrIII(of Io Ihr,d(f s I I I o I 1 ra'�[0010r,l a II do I ha"r physical r(q)rG du,I o Its o[Ihis I I`a l'ISl lISSIOl'1 Ih,f,r,pI by/\ JY II"1dividuYI 1nr 4r7I1 1 Y h;I101 0 A/Okwr o[yid l"IY c,al prlvnlc 1,I(y g al l oI incy dicill,u+1ul I<rn 1odud,G,c) IGal1hrrrrlrlr,I1,,I his Oko,l1orllCI011SInisslrnldocsnolcnslilul(10111,SlpIlalGarGr,rlr,I ally olhr,If1nIllra4'1, dcIllIf'icalloll1nGraulhrnvallloll BYt:11ISII011,,r1I1Is;nrollRllllrlol1,( nlsirudkar�l d ocs rlol II11(old l o wvld(olu, a hrlulling a r(,(orlrrrll,or to Iinply I hal t:hc aulhor has ally aulhrol II d to(mlkor II111;a a hrlulling a I(,(orlr 111 oil hdhalf 1of Bill lrllrol 1,f,rolurtrlrr,llcarl� 1