Loading...
7th Change Order 04/04/2023 MONROE COUNTY/DEPARTMENT OF AIRPORTS CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 7 FBO ACCESS ROAD, KWIA INITIATION DATE:_March 22, 2023 TO CONTRACTOR: CHARLEY TOPPINO & SONS, INC CONTRACT DATE: ,APRIL 21,2021 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price).......................................... $ 3,163,649.67 Net change by previously authorized Change Orders.................................................. $476,233.05 The(Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$ 3,636,882.72 The(Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order.......$ 24,672.00 The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is....... $ 3,664,554.72 The Contract Time will be(increased) (decreased) (unchanged) by............................... 202 days The date of Substantial Completion as of the date of this Change Order is....................... 8/21/2023 Detailed description of change order and justification: This change order includes (1)time extension from January 31, 2023 to August 21, 2023. Work to be completed includes installation of concrete foundations for pedestrian canopies and the final installation of a guard booth. Concrete foundations shall be complete by April 28, 2023 with final guard booth installation and acceptance no later than August 21, 2023. This change Order is 0.78% of the original contract price. Not valid until sinned by Owner Architect if applicable), and Contractor ARCHITECT: 3/30/2023 w Dat CONTRACTOR: ..._ .. 23 m ._ .. .. _ .. ate DIRECTOR OF AIRPORTS 3.31.2023 Date MONROECOUNTY; ^.:�.... „� 04.04.2023 Asst./Coun)y Administrator Date N IOE COUN TY ATTORNEY OYE FO PED3 O J, ASSISTA U CASTOORNEY late 3/31/23 Change Order Attachment per Monroe County Code Section 2-58(b) • Change Order was not included in the original contract specifications. Yes ( ) No(X) If Yes, explanation : Additional site work for concrete foundations for additional covered pedestrian bench. Change Order was included in the original specifications. Yes ( ) No (X ) If Yes, explanation of increase in price: Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X) If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes(X ) No ( ) If no,explanation of why: • Change Order is correcting an error or omission in design document. Yes ( ) No (X ) Should a claim under the applicable professional liability policy be made? Yes ( ) No (X) Explain: qm Price Quotation Attention: McFarland Johnson DATE: 03107123 2409 North Roosevelt Blvd Sulte 4 Key West,Florida 33040 ITEMIZED QUANTITIES Location: 3401 S Roosovm t FlNr�st FL,m33040 .. ^_�. ,,_ D n,&dtl vmX�C�urtd9W - S�apOs #uaslwvllCaawurmOO.Faumldtld _.�.....�... .� Itawn Descriotlon ......... C7u rry y U�0�... �M„ d%IM L--IItT C;i1mt `105'. ..I.........�.. ......... �.�.. ......... ............� m r '.Milmlll CmnA'raI.FouodalWonS'Ior69d�mwa0r tiaino 1.tA R.$ �& 24mm67200 6 dm..6'F7.20 ........ IrICJ vmTa rw+mm AFwre rt+a y.[V,7w .. .,. _ ., �Fdavn 01r d. m a ien..w'erm n.wate R1w112 1A-2'?2 ...._... ._. ... ....,^...... ;SA..walk bnd Curb � _............. --------. m . _.......�.. Subtotal S 24,672.00 �. ...... ...... _....�..._,. 2 - ... .....,... ': unrferrwnn+%c+dw"a m^wmi1 Eumnd'a, ;MM 00NRdwan,rwa�a. ................ p 0' �5�.... ..._... 0 ...h9ehe0ag!ImMDe�mmlr04.ala. ............. ...... 9Im ? ........ ....... .... io ......tS ......5 ...�..�............. ......� ... ... Total: $ 24.672.00 ... .. .. ...... ..... ... ..... _.. '._ ......... �.�.. __Noloa: W.,.tj+'}�immrrma. am"wraard'wPm JYA ef ,2.�.... .............................. .. ..._ _.. ... ...... .... ........._ Prepared by: PA& 'Sastimator CRsarle 7a--Ino&Sons,Ina - -..-_.. Sheea t srtt ........ Dat.: 03107/23 Signature: Date: