2nd Change Order 05/17/2023 BACKFILL RESTORATION WATER QUALITY IMPROVEMENT PROJECTS
CANAL #25 KEY LARGO, MONROE COUNTY, FL
MONROE COUNTY
CONTRACT CHANGE ORDER
PROJECT TITLE- Monroe County Canal Restoration CHANGE ORDER NO- 2
Water Quality Improvement
Project Canal#25 Key Largo INITIATION DATE: August 1, 2022
TO CONTRACTOR. CONTRACT DATE- June 15, 2022
Adventure Environmental, Inc
The Contract is changed as-follows:
The original (Contract Sum) (Guaranteed Maximum Price)............................................$1,280,509.00
Net change by previously authorized Change Orders........................................____$ 229,233.20
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order Was............a$ 1,509,742.20
The (Con-tract Sum) (Guaranteed Maximum Price) will be increased) (decreased)
(unchanged) by-this Change Order.......$314,085.99
The new (Con-tract Sum) (Guaranteed Maximum Price) including -this Change Order is..._.$ 1,823,828.19
The Contract Time will be (increased) (decreased) (unchanged) by..................................
The date of Substantial Completion as of-the date of-this Change Order is......................... 01/31/2023
Detailed description of change order andjusti-fication:
Additional -fill material needed to bring canal to proposed elevation to achieve proper flushing.
The amount of this change order is"not to exceed" to be verified by back up documentation provided
by'the Contractor and verified by the Engineer and County.
N1; A 'i''ot valid until signed r Owner Arch' 'if a fica l i and Contractor
Gregory W. Corning "I't'Ily signed by Gregory W.Corning
ENGlNEER: Date:2023.04.26 17:02:14-04'00'
Date
CONTRACTOR: 4/25/2023
Date
Digitally signed by Rhonda Haag
SUSTAINABILlTY PROGRAM MANAGER: Rhonda Haag Date 2023.04.27 10 59 02-04'00'
Date
Digitally signed by Roman Gastesi
COUNTY/DEPUTY ADMINISTRATOR Roman GastesiDate:2023.05.18 08:43:13-04'00'
Date
MONROE COUNTY ATTORNEY'S OFFICE
Approved for form and legal sufficiency
D glt�y by Cy,�L DN
1h I U
Cynthia Hall, Sr. Assistant County Attorney
APPLICATION FOR PAYMENT 01027-Flage 145 of 218
BACKFILL RESTORATION WATER QUALITY IMPROVEMENT PROJECTS
CANAL #25 KEY LARGO, MONROE COUNTY, FL
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes El No 1:9
If Yes, explanation:
• Change Order was included in the original specifications. Yes El No E
If Yes, explanation of increase in price-.
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes EX No El
If Yes, explanation as to why it is not subject for a calling for bids:
• Project engineer approves the change order. Yes ® No E]
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes E]No N
Should a claim under the applicable professional liability poky be made? Yes El No a
Explain:
APPLICATION FOR PAYMENT 01027-1::Iage 146 of 218