2nd Change Order 05/17/2023 BACKFILL RESTORATION WATER QUALITY IMPROVEMENT PROJECTS CANAL #25 KEY LARGO, MONROE COUNTY, FL MONROE COUNTY CONTRACT CHANGE ORDER PROJECT TITLE- Monroe County Canal Restoration CHANGE ORDER NO- 2 Water Quality Improvement Project Canal#25 Key Largo INITIATION DATE: August 1, 2022 TO CONTRACTOR. CONTRACT DATE- June 15, 2022 Adventure Environmental, Inc The Contract is changed as-follows: The original (Contract Sum) (Guaranteed Maximum Price)............................................$1,280,509.00 Net change by previously authorized Change Orders........................................____$ 229,233.20 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order Was............a$ 1,509,742.20 The (Con-tract Sum) (Guaranteed Maximum Price) will be increased) (decreased) (unchanged) by-this Change Order.......$314,085.99 The new (Con-tract Sum) (Guaranteed Maximum Price) including -this Change Order is..._.$ 1,823,828.19 The Contract Time will be (increased) (decreased) (unchanged) by.................................. The date of Substantial Completion as of-the date of-this Change Order is......................... 01/31/2023 Detailed description of change order andjusti-fication: Additional -fill material needed to bring canal to proposed elevation to achieve proper flushing. The amount of this change order is"not to exceed" to be verified by back up documentation provided by'the Contractor and verified by the Engineer and County. N1; A 'i''ot valid until signed r Owner Arch' 'if a fica l i and Contractor Gregory W. Corning "I't'Ily signed by Gregory W.Corning ENGlNEER: Date:2023.04.26 17:02:14-04'00' Date CONTRACTOR: 4/25/2023 Date Digitally signed by Rhonda Haag SUSTAINABILlTY PROGRAM MANAGER: Rhonda Haag Date 2023.04.27 10 59 02-04'00' Date Digitally signed by Roman Gastesi COUNTY/DEPUTY ADMINISTRATOR Roman GastesiDate:2023.05.18 08:43:13-04'00' Date MONROE COUNTY ATTORNEY'S OFFICE Approved for form and legal sufficiency D glt�y by Cy­,�L DN 1h I U Cynthia Hall, Sr. Assistant County Attorney APPLICATION FOR PAYMENT 01027-Flage 145 of 218 BACKFILL RESTORATION WATER QUALITY IMPROVEMENT PROJECTS CANAL #25 KEY LARGO, MONROE COUNTY, FL Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes El No 1:9 If Yes, explanation: • Change Order was included in the original specifications. Yes El No E If Yes, explanation of increase in price-. • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes EX No El If Yes, explanation as to why it is not subject for a calling for bids: • Project engineer approves the change order. Yes ® No E] If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes E]No N Should a claim under the applicable professional liability poky be made? Yes El No a Explain: APPLICATION FOR PAYMENT 01027-1::Iage 146 of 218