1st Change Order 05/19/2023 MONROE COUNTY/ DEPARTMENT O ' AIRPORTS
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 001
Key West International Airport
Noise Insulation Program
Construction of KWBTS Final Phase
INITIATION DATE: May 9, 2023
TO CONTRACTOR: DEC Contracting Group, Inc. CONTRACT DATE: 9/21/2022
The Contract is changed as follows:
The original (Contract Sum) ........................................... ... ........................$ 2,698,460.74
Net change by previously authorized Change Orders.................. .......,............$ 0.00
The (Contract Sum) prior to this Change order was............................ .............$ 2,698,460.74
The (Contract Sum)will be (decreased) by this Change Order.. ...............$ (187,741.26)
The new (Contract Sum) including this Change Order is....................................$ 2,510,719.48
The Contract Time will be (increased) (decreased) (unchanged) by..............................(0) Days
The date of Substantial Completion as of the date of this Change Order is...............May 2, 2023
Detailed description of change order and justification:
Delete Unit B601: 90 075.81 Deduct
Delete Unit B607: 99 749.26 Deduct
Chan e ERV to ceiling mounted ERV due to existin conditions: $2,083,81 Add
Total Deductive Change Order Amount: 187 741.26
This change Order is % of the original contract rice: 6.9% Deduct
Not valid until signed by Owner Architect if applicable), and Contractor
ARCHITECT: .519 73
Date
CONTRACTOR: Z
Date
AIRPORTS DIRECTOR : 5.17.2023
Date
COUNTY/ASSISTANT ADMINISTRATOR 05.19.2023
Date
APPROVED AS TO FORM&LEGAL SUFFICIENCY
Monr a ounty Attorney's Office
05 17 2023
N thalia Mellies Archer
Assistant County Attorney
Change Order Attachment per Ordinance No. 004-1999
o Change Order was not included in the original contract specifications. Yes ( X) No ( }
If Yes, explanation:
Two unit owners scheduled for renovation had elected to be dropped form the program.
0 Change Order was included in the original specifications. Yes ( ) No ( X)
If Yes, explanation of increase in price:
Change Order exceeds$25,000 or 5% of contract price (whichever is greater).
Yes (X ) No( )
If Yes, explanation as to why it is not subject for a calling for bids:
It is a 6.9% deduct to the contract.
* Project architect approves the change order. Yes (X ) No ( )
If no, explanation of why:
Change Order is correcting an error or omission in design document. Yes O No (X)
Should a claim under the applicable professional liability policy be made? Yes ( ) No (X )
Explain:
Unforeseen condition due to a beam above the ceiling which prevented implementation of
original ductwork design.