Item N01 M E M O R A N D U M Office of the County Administrator TO: Board of County Commissioners FROM: Debbie Frederick Deputy County Administrator DATE: January 13, 2009 SUBJECT: County Divisions’ Monthly Activity Report for December, 2008 ______________________________________________________________________________ MONTHLY ACTIVITY REPORT – DECEMBER, 2008 KEY WEST AIRPORT We have reached the point of substantial completion on the KWIA new terminal building. The Airlines are finishing up their data and phone line installation and moving furniture into their offices in anticipation of the first day of operation on February 25, 2009. The bag makeup building is nearly complete as are the airline operation offices down on the ramp. The VCB is back on track and being framed up quickly. The amendment to our TSA mandated Airport Security Plan (ASP) has been filed within the deadline with two days to spare. Therefore, TSA issues should not be an impediment to opening the new facility. In December we were notified by the FAA that the complaint brought against us (for the second time) by Chesapeake Bay Helicopters has been dismissed. The FAA concluded that we did not violate our grant assurances and that our practices do not constitute economic discrimination. MARATHON AIRPORT Continental Connection operated by Cape Air commenced daily service with three round trips to Ft. Myers on December 19, 2008. Co-hosted public reception with Cape Air to introduce daily service between Florida Keys Marathon Airport and Southwest International Airport in Ft. Myers. New Directory Sign installation on U.S.-1 in front of passenger terminal. Updated version of Florida Keys Marathon Airport Profile for the Continuing Florida Aviation System Planning process (CFASPP) Web Site. Update of the Airport Layout Plan for Florida Keys Marathon Airport is on-going. Initial and recurrent training classes associated and/or related to FAR Part 139 operations and certification are on-going. Several construction and operations related projects continue to be in various stages of completion at the airport including: perimeter fence & gates installations; construction of generator building and electrical vault; terminal repair and renovation punch list items; HVAC system replacement; Enhanced Taxiway Markings; update of noise contours; Runway 7-25 Pavement Markings. 1 Updated Airport Web Page & FAQs. EMPLOYEE SERVICES I. WEBSITE UPDATES (other than normal position vacancy updates, etc.): Benefits: KPHA Provider Directory Updates Changed Wells Fargo website address on benefits webpage (from Acordia) Human Resources: Updated 3 job descriptions; Committees updated to reflect current members. II. TURNOVER NUMBERS TO DATE: Dec Turnover: .41% Turnover as of Dec 2008 20% Turnover as of Dec 2007: 16% Resignations: 1 Terminations: 1 Retired: 0 Deceased: 0 Employed: Both were employed less than 3 years. III. ACTIVITIES: Human Resources Two (2) United Way Presentations. One in Key West on December 10th, 2008 and one in Marathon on December 18th, 2008. 2009 Annual Evaluation report to all Supervisors. Annual SS report request to departments in accordance with FS 119.071(5) Collection and Release of SSN. Reviewed changes regarding new FMLA rules that go into effect January 16, 2009. Departments will be notified once effective. Bi-annual Division Safety Meeting held. Risk No major activities. Benefits (Group/Workers Comp) HIS Retiree Report completed and sent to FRS (due Dec 29th). Provided #’s for Annual Wakely Actuarial (F.S. 112.08). Completed Florida Association of Counties Health Insurance Survey. Administrator met with Corvel regarding their Wkrs Comp TPA Services. BUDGET & FINANCE Budget Analysts: Formatted and assembled the first copy of the FY2009 Budget Book After Finance reconciled and posted their entries for FY08 Capital Projects, FY09 Project Budgets were entered in the Finance System Processed 63 Budget Transfers, 23 resolutions, and reviewed 15 contracts. Compiled and finalized FY09 Budget Book due to GFOA. Trued-up Social Services grants revenue and expenditure. Purchasing Department: Total purchase orders processed: 357 Total orders placed for departments: 74 2 Total orders entered for departments: 67 Office Depot orders processed: 53 Staples Orders processed: 3 We opened 3 bids and processed another 3 which was below average from the previous months. Addendums entered 1, contracts reviewed 12, and bills paid 4, and voided 10 purchase orders. We also processed 918 pieces of mail which was a decrease from previous months. Grants Department: Completed 25 Project Worksheets for TS Fay. Completed 10 Project Worksheets for Hurricane Ike. Completed quarterly reports for outstanding PWs from Wilma, Rita, Katrina, Dennis. Florida Housing Finance Corporation grant: completed and submitted grant for $2 million. th JAG/Bryne grants: completed 4 quarter reports and close out reports. CJMHSA Planning Council grant activities (reporting, meeting, advertising, minutes). Processed40 Purchasing Orders for HSO contracts. Ongoing monitoring of HSO contracts and processing of invoices. COMMUNITY SUPPORT SERVICES SOCIAL SERVICES DEPARTMENT (SSD) In-Home and Nutrition Services (IHNS) OAA, Older Americans Act Programs: Nutrition (Information in this section is for the period 11/21/08 – 12/31/08) C-1 Congregate Meals increased to 1726 units this month, which is a reflection of the longer year end reporting period, as well as the return of the seasonal clients. The Nutrition Department spent 92% of the 2008 congregate meal grant money. C-2 Home-Delivered Meals increased to 3518 units, in part for the same reasons. We also took on six new clients as the result of the convalescent center closing. The Nutrition Department spent 96% of the 2008 home delivered meal grant money. 100% of the grant money would have been spent if the reimbursement rate from the Alliance for Aging accurately reflected the true cost of running the programs. In-Home Services (Information in this section is for the period 10/21/08 – 11/20/08) III-B Screening and Assessment: 20 units this period, 91% year-to-date achieved, .63% underachieved. 43 clients on the waiting list. III-B Homemaking: 95.75 units this period, 63.3% year-to-date achieved, 28.33% underachieved. 43 clients on the waiting list. III-B Personal Care: 149.5 units this period, 130.93 % year-to-date achieved, 39.3% overachieved, due to the amount of personal care required by the clients. 16 clients on the waiting list. We have spent 92% of III-B funds, which represents a 0.37 % underachievement. We are in the target range and will spend all of the III-B funds by the end of the grant year. 3 III-E Facility Respite: 485.5 units this period, 79% year-to-date achieved, 12.63% underachieved. Given the current rate of spending and the longer year-end reporting period, it is anticipated that all of the III-E funds will be spent. Non-OAA Programs: CCDA (Community Care for Disabled Adults) for November 2008: Case Management: 13.75 units for the month were produced; 74.25 units year-to- date. Homemaking: 86.75 units for the month were produced; 469.5 units year-to date. Home-Delivered Meals: Monthly units were 185 meals; 6870 meals year-to-date. Personal Care: Monthly units were 24; 99.5 units year-to-date. Overall Program Achievement was 71%, 12% underachieved. CCE (Community Care for the Elderly) for the period 10/21/08 – 11/20/08: Case Management: 67.5 units for the period and 363.5 units year-to-date. 24% achieved year to date. There are 57 clients on the waiting list. Intake: 1 unit achieved (new service). 3 % achieved year-to-date. Homemaking: 798.5 units for the period and 3502 units year-to-date. 81% achieved year to date. There are 52 clients on the waiting list. Personal Care: 421 units for the period and 1804.25 units year-to-date. 40.09% achieved year to date. There are 21 clients on the waiting list. Respite: 25 units for the period and 272.5 units year-to-date. 18.2% achieved year to date. There are 8 clients on the waiting list. CCE overall year-to-date is at 47% achievement which is a 5.35% overachievement. Some of the clients may be transferred to other programs in order to reduce spending in CCE. The wait list continues to grow; some of those clients wait listed are Rank 5 (in greatest need of services). ADI (Alzheimer’s Disease Initiative) for the period 10/21/08 – 11/20/08: 359.25 units were produced in the period and 1172.25 units year to date. 42.75% year-to-date achieved, 1.1% overachieved. Up until this point we have been underachieved; we will begin to watch this achievement level to avoid overspending. There are six clients on the wait list. HCE (Home Care for the Elderly Program) for the period 11/16/08 - 12/15/08: 15.5 billable units this period, 85.5 billable units year-to-date. Current spending level year to date is at 32.1%. Monroe County Transit (MCT) Department Activity for December 2008 One-way trips provided: 1,847 Unduplicated clients served: 231 Special Needs Clients registered: 314 Awarded the 5310 FDOT Grant for the funding of a new Paratransit bus and the 5316 FDOT Grant for funding the Mobile Data Terminals/software for the Trapeze Dispatching and Reservation System. The awards and agreements will be brought to the board in the fall BOCC meetings. Deposited Revenue: $$1,974.50 Expenditures: $50,777.31 4 Percentage Spent Fiscal YTD: 3.5 % Community Support Services In the month of December 2008 we had: 21 New Welfare cases 335 Office visits 29 Home and field visits 2,322 Incoming calls – Information/Referral We served 122 unduplicated Welfare client households Low Income Home Energy Assistance Grant Program cases totaling $ 750.00( 3 -cases) Low Income Crisis Assistance cases totaling $ 3,560.26 (11-case) Spent in DEC.$ 4,310.26 (3) cases peer reviewed by staff. Staff member attended the SHAL committee meeting on Homeless Issues-in KW. 2 staff members attended the Med-Waiver training given by the Alliance in Miami - 12/12/08. 2 staff members attended the services for the County Pauper burials- Vault 80-KW Cemetary 12-19-08. 2 staff members attended the Lower Keys Interagency monthly meeting-12-12-08. Bayshore Manor (BSM) Bayshore Manor’s current census is 16 residents. The current census is five private pay and 11 subsidized. BSM provided 510 hours of OA3E respite care and 6 hours of Medicaid Waiver respite care this month.Bayshore Manor has two OA3E clients and one Medicaid Waiver client at this time. There are 2 clients on the wait list. Revenue for December 2008 $34,840.54 Expenditures for the same period $68,713.73 Percentage of the budget spent year to date 23.89% LIBRARY Library usage continued its seasonal increase, although figures still reflect the reduction in hours and days of service: circulation totaled 28,554 items and the onsite visitor count was 30,975, both numbers reflecting decreases of 24% from November of the previous year 315 new Library cards were issued in November and 6498 public access computer sessions were provided There was a 25% increase in borrower transactions (logins, renewals, requests) on the Library’s Information Portal website for the month, underlining the importance of our off-site web presence for Library patrons The Edwin O. Swift, Jr., collection was recently added to the Library’s Flickr photo project—this site is now averaging 733 “views” per week Library use of the FY 2009 budget is proceeding on a pace with the year: with one-fourth of the year gone, approximately 26% of the Library budget has been 5 used; use of discretionary funds, such as those for supplies and materials, is being closely monitored by Managers and Administration EXTENSION SERVICES Number of services provided: 367 phone calls, 26 office visits, 34 visits to clients, 11 group teachings with 169 people in attendance, 8 media submissions, and 343 bulletins distributed. Total Budget for FY 08/09: $186,485.00; Year to Date Expenditures and Encumbrances: $122,403.54; Remaining Balance: $64,081.46; Percentage of budget spent and/or encumbered year to date: 65%. The Extension Director completed a three-day class on “Solar Water Heating Systems” at the Florida Solar Energy Center in Cocoa, FL. The Environmental Horticulture Agent held three Master Gardener preview sessions throughout the Florida Keys, attended by 32 people, with 28 signing up for a phone interview for 25 Master Gardener intern slots. The Family & Community Development Agent coordinated county participation for the Energy Saver and Drive $marter Challenge; Monroe County won the Drive $marter Challenge and will get national recognition for our sustainability efforts through the National Association of Counties (NACO). GROWTH MANAGEMENT GMD COMPARATIVE REVENUE SUMMARY RevenueTotalTotalRevenueRevenueRevenue BudgetRevenueRevenueEndingEndingEnding FY 2009 CollectedCollectedDecembeDecembeDecembe in FY in FY r 2008 r 2007 r 200820072006 Building$2,790,063$2,857,68$2,769,31$633,066$874,805$554,080 Permit 244* Licenses & Permits Planning$430,000$488,081$532,000$141,479$172,133$109,850 Department Fees Code$90,000$110,412$97,940$41,144$19,729$24,000 Enforcemen t Fines & Forfeits *Note: ’08 was a Contractor License renewal year, which generated an additional $129k. These are the primary, customer driven revenues and do not include the revenues obtained by taxes etc. EXPENSES 6 BudgetTotalTotal200920082007 FY’09ExpensesExpensesExpensesExpensesExpenses FY 2008 FY 2007 EndingEndingEnding DecemberDecember December Growth $916,52$648,098$1,637,473$84,982$156,789$293,763 Management 6 Admin. Building $2,434,7$2,311,238$2,299,758$471,746$677,625$623,823 46 Code $1,009,8$894,006$1,021,256$216,312$254,822$352,780 Enforcement 85 Planning $1,149,5$878,366$1,333,008$184,462$292,426$460,685 16 Environmenta $299,30$330,016$313,488$66,858$100,610$91,173 l Resources 2 Planning $100,54$88,345$86,226$18,722$28,743$24,988 Commission 1 Comprehensive $358,40$74,655$290,478$2,154$34,494$32,947 Plan 0 Geographic$314,13$181,935$310,576$48,483$47,606$52,422 Information 3 (GIS) Marine$55,051$84,753$235,623$12,966$28,926$56,555 Resources Pump Out $68,587$64,640$48,275$16,519$9,284$17,956 Boat Monroe County Marine Resources Office Handled approximately 25 customer inquiries Installed ten new navigational buoys in Boot Key Harbor Received bids for repowering the Marine Resources survey vessel Held Marine and Port Advisory Committee meeting Removed seven derelict vessels Coordinated new derelict vessel procedures with FWC Surveyed regulatory zones in the middle keys Performed 4 site visits in response to customer inquiries Worked with OMB to split out Boating Improvement Funds into two revenue sources and cost centers to provide for allowable expenditures under state statute Vessel Pumpout Program Functions: Pumped out 117 boats 7 Building Department Number of Permits 12/01/08 THRU 12/31/08 Apps Submitted 292 Permits Issued 306 Walk Thru 70 Cert of Occupancy 30 Inspection: Total 1884 Average Per Day (17 days) 90 Per Discipline: Building/Roofing 1096 Electrical 321 Plumbing 203 Mechanical(A/C) 130 GAS 13 Plans Reviews: Total 2592 Average Per Day 123 Per Discipline: ABO 377 Bio 156 Code Enf 2 3 Code Enf 3 6 Coord 303 Elect 151 Eng 3 Exam 286 File 5 Fire 69 Flood 89 Mar-Bldg 417 Mech 46 P.K.Building 242 Pending 56 Plan 116 Plumb 82 Ready 7 ROGO 9 Roof 14 S.I. Building 113 Track 39 8 Code Enforcement Number of New Cases Opened 340 Number of Inspections Completed 1799 Fines, After the Fact Fees and Contractors Citations $ 8,860 After the Fact Fees Collected $98,110 Number of Contractor Citations Issued 19 Number of Contractor Citations Heard No Hearing Contractor Citations Paid $4,047 Number of Cases Heard before Special Magistrate- No Hearing PLANNING & ENVIRONMENTAL RESOURCES PERFORMANCE REVIEW Dec. 01 through Dec. 31, 2008 Category: Special Approval Applications CURRENT PLANNING: Appeal to Planning Commission 1 Applied Appeal to Planning Commission Completed Appeal to BOCC Applied Appeal to BOCC Completed Appeal to DOAH Applied Appeal to DOAH Completed Administrative Relief8 /Beneficial Relief Applied Administrative Relief/Beneficial Use Completed Alcoholic Beverage Applied Alcoholic Beverage Completed Beneficial Use Applied Beneficial Use Completed Code Enforcement Referral 11 Conditional Use, Major Permit Applied Conditional Use, Major Permit Issued 9 Conditional Use, Minor Permit Applied Conditional Use, Minor Permit Issued ConditionalUseMinor Deviation Applied ConditionalUseMinor Deviation Completed Land Authority Referral Letter of Understanding 1 Application Long Dock Variance 1 Letter of Currant Site Conditions Permit Application Site Visit 128 Pre App Conference Wetland Delineation2 CURRENT PLANNING CATEGORY con’tConditional Use, Major Deviation Applied ConditionalUse,Major Deviation Completed ConditionalUse,Time Extension Applied ConditionalUse,Time Extension Issued ConditionalUse,NRFA Transfer Applied ConditionalUse,NRFA Transfer Issued Conditional Use, TRE Transfer Applied Conditional Use, TRE Transfer Issued 10 Conditional Use, TDR Applied Conditional Use, TDR Issued Development Agreement Applied Development Agreement Completed Home Occupational Permits 3 Applied Home Occupational Permits 1 Issued InclusionaryHousing Exemptions, Applied InclusionaryHousing Exemptions, Completed Public Assembly Permits Applied Public Assembly Permits Issued 1 Road Abandonment Applied 2 Road Abandonment Issued Setback Waiver Administrative, Applied Setback Waiver Administrative, Issued VarianceAdministrative, 3 Applied Variance Administrative, Issued Variance,Planning Commission, Applied Variance, Planning Commission Issued Permits Reviewed & Processed 95 Vacation Rental Applied Vacation Rental Issued Vacation Rental Mgr. License 1 Applied Vacation Rental Mgr. License 1 Issued COMPREHENSIVE PLANNING Y CATEGOR 11 PlatsApplied PlatsCompleted LUD Map Amendment, Applied LUD Map Amendment Completed Tier Map Amendment, Applied Tier Map Amendment Completed FLUM Amendment Applied FLUM Amendment Completed MCC Text Amendment, Applied MCC Text Amendment Completed Comp Plan Text Amendment, 2 Applied Comp Plan Text Amendment, Completed 380 Development Agreement Applied 380 Development Agreement, Completed ROGO Related Applications: Residential: Market Rate Allocations, Applied Market Rate Allocations, Issued Affordable Allocations, Applied Affordable Allocations, Issued ROGO Exemptions Applied 4 ROGO Exemptions Issued 8 Beneficial Use Applied 1 Beneficial Use Issued Non-Residential AllocationsApplied AllocationsIssued MIXED USE CATEGORY LDRD’s Applied LDRD’sIssued 12 DEVELOPMENT REVIEW COMMITTEE RegularMeetings:1 SpecialMeetings AgendaItems: 2 PLANNING COMMISSION RegularMeetings:2 SpecialMeetings AgendaItems: 11 PARKS & RECREATION ADVISORY BOARD. RegularMeetings SpecialMeetings *includes all County Parks each meeting *Agenda Items * CUSTOMER SERVICE* * estimated at 5 per day per planner (2) In-person inquiries 300* * estimated at 10 per planner (7) per day Telephone inquiries 2100* *estimated at 5 per planner (7) per day Email inquiries 300* Request for Research 2 Applications Pre-ApplicationConferences2 Letters of Understanding Historic Preservation Committee Application CATEGORY: 8 Site Visits Administrative Relief/Beneficial Use Apps Code Enforcement Referral 11 Conditional Use Application Land Authority Referral Letter of Current Site Conditions Applications Letter of Understanding 1 Long Dock Variance Application 1 Permit Application Site Visit 128 Wetland Delineation2 Pre App Conference OTHER: 13 DCA Request Misc. On Site Assessment Memo 13 WRITTEN CORRESPONDENCE/ BIOLOGICAL ASSESSMENTS Administrative Relief /Beneficial Use 1 BOCC/PC Agenda Item 1 Code Enforcement Assessment Memo 6 Conditional Use Staff Report GIS Map 25 GOCEA Recording 1 Interagency Coordination 11 Land Authority Assessment Letter of Current Site Condition Long Dock Variance Memo/Approval 2 Letter of Understanding 1 ROGO Land Dedication Letter 2 OTHER: Mitigation letter 1 Denial letter 1 Permit Application Review/Assessment 166 Adoption of LDR Recodification Capital Improvements to Comp Plan MEETINGS DRC2 PC BOCC Pre-Application2 Code Enforcement Hearing Special Projects/Training 3 OTHER: Invasive Exotic Tech Interview Tier Change Staff Meetings Planning Site Visits Historical Preservation Meetings 14 Vacation Rental Mgr. Renewal issued 1 Vacation Rentals Applied 1 Vacation Rentals Issued 1 Big Pine LCP Amendments Committee Mtg. 1 GIS Office Completed 21 address requests. Scheduled and advertised selection committee for Land Cover RFP. Met with selection committee to evaluate and rank 12 Land Cover Project Proposals. Negotiated contract with top ranked firm and recommended firm to BOCC during the December Board meeting. Met with planning staff to review and edit the GIS based Future Land Use data. This will be an on-going review process. Attended US Census Participant Statistical Area Program (PSAP) Completed over 20 data requests. Including but not limited to the following: 1.PDF Flum maps, location maps for Housing Authority 2.Land acquisition status map for Land Authority. 3.CBRS maps – wastewater, developed, and public land for DCA. 4. Shoreline data provided to Florida Natural Area Inventory (FNAI). 5.Sand Sub Key Deer Corridor Maps 6.Hurricane Evacuation Study for University of Maryland 7.Tier requests 8.Ortho image requests and topography 9.LiDAR data request EMERGENCY SERVICES Fire Rescue The IAFF bargaining agreement was ratified by the firefighter membership and rd approved by the Board of County Commissioners, December 3. The Board of County Commissioners conducted a public hearing and approved the Trauma Star ordinance. Fire Rescue delegation attended former Fire Chief Clark Martin’s Memorial Service in Fairfax County, Virginia. Training Fire Rescue personnel completed their biannual CPR practical skills evaluations. Probationary firefighters continue to complete Department orientation. 15 Two firefighter paramedics were cleared by the Medical Director to function as Charge Paramedics. These two firefighters were sponsored by Monroe County to attend and complete paramedic school, here in Monroe County Fire Marshal Reviewed numerous commercial plans for adherence to building and fire codes. Emergency Management Conducted Local Mitigation Strategy Working Group Meeting Participated in Florida State DEM Catastrophic Disaster Housing Roundtable Symposium Conducted Regional Citizen Corps Task Force As a member of the Monroe County Selection Committee scoring meeting of the Request for Qualifications for the Emergency Operations Center, reviewed project bids Worked on outstanding Hurricane Fay and Ike bills payments with Finance, Risk Management and FEMA Trauma Star Trauma Star Flight crews participated in planning the Air National Guard Air Bridge training exercise coordinated with Emergency Management Basic Life Support Instructor training initiated for MCSO and community members. Air Medical Chief attended Regional Disaster Behavioral Health training given by the Department of Health in Tallahassee Total patient transports = 15. (8 Scene transports, 7 hospital to hospital) Upper Keys Trauma District th Upper Keys Trauma District board meeting held December 12. PUBLIC WORKS Transported files to storage for the Supervisor of Elections and Social Services Installed antennae at Spottswood roof for Technical Services Replaced electric fixtures at the PK Court House, AARP, Spottswood and Tavernier Fire Station Minor plumbing repairs at the PK Court House, Key Largo Library and the Animal Shelter Replaced furniture at the Court Reporter’s office Minor a/c repairs at the PK Court House, Spottswood and Social Services Interior painting at the PK Court House and exterior painting at AARP and the Animal Shelter Replaced electric fixtures at Key Largo Park and Harry Harris Park Painted pavilions, tables and benches at Harry Harris Park Emergency plumbing repair at Friendship Park 16 Transport equipment to PK Garage for Card Sound Toll Authority Removed portion of the canopy at the Card Sound Toll Authority Striped roads in the Key Largo Park subdivision Re-worked the surface treatment of Valois Boulevard Pollution Control collected over 33 tons of illegally dumped debris from the county rights of way, and also collected 11.72 tons for other departments (2,840 lbs of debris from Marathon Public Works; 4,980 lbs from the Key West Garage; 10,160 lbs of debris from the Key West Jail; 2,940 lbs of tires from the Marathon Garage; and 2,520 lbs. of invasive exotics from a Land Authority clean-up in the Upper Keys) Because of a binding contract with local fuel providers, the County’s average cost for unleaded ethanol gasoline was approximately $1.52 per gallon countywide (as of 12/30/08) Because of a binding contract with local fuel providers, the County’s average cost for regular diesel, and bio diesel fuel, was $2.10 per gallon countywide (as of 12/23/08) Completed four-month fuel cost survey which shows on average that users pay less at County pumps than anywhere else countywide. B30 bio-fuel testing continues in Key West with no problems detected as of this date Two in-house mechanics were promoted filling badly needed Lead mechanic/supervisor positions in Key West and Marathon The three garages continue to struggled with back-log of work due to mechanic shortages in all three garages, with little, or no customer complaints, major mishaps, or safety issues Replaced a 20-ton condenser at Marathon EOC meeting room Remodeled offices at Sheriff’s Substation for new Captain and Lieutenant Deep cleaned carpets at Marathon Government Center and Annex Stripped, sanded, caulked, primed and repainted entrance of the Marathon Health Center Refurbished back walls of buildings at entrance to Freeman Justice Center Replaced the sand at Higgs Beach Volleyball Court with Lake Wales sand rated for fall impact safety Major clean-up at Hickory House and grounds Repaired Sheriff Administration building roof on Stock Island Repaired Stock Island Fire Station #8 roof ENGINEERING Engineering Services – Key Deer Boulevard Road Project – project completed; staff processed change order #2, resulting in a credit of $22,251; received final release of lien from the contractor; finance processing final pay application to close project. Prado Circle Stormwater Project – substantial completion on November 6, 2008; waiting for alarm and valve to arrive from manufacturer to be installed; final completion expected by early December. Rejected $40,000 change order for 17 additional work not properly authorized; will review $625 change order pending additional information from contractor. Breezeswept Beach Estates Culvert – contractor has installed 80% of piping, one of two concrete structures, and has completed the water line relocation; remaining work includes installing second concrete structure, final 20 feet of HDPE pipe, second headwall and asphalt restoration; anticipated completion is end of January 2009. South Florida Water Management District Grant 2009 – $500,000 grant agreement approved by BOCC at December meeting; agreement was sent to SFWMD for execution; staff working with SFWMD representative to provide ongoing status of funds expended in order to ensure use of funds during grant period. US 1 Stormwater Project – after staff evaluation, three stormwater projects on US 1 have been combined into existing DOT road restoration projects to provide more cost effective approach; awaiting amendment to Joint Participation Agreement from DOT to cancel agreement that previously provided funding for the work. Tropical Storm Fay / Hurricane Ike – staff assisting grant management with preparation and review of FEMA project worksheets for various projects; staff performed survey of Higgs Beach elevations and prepared drawing showing pre- and post-storm elevations. Engineering staff calculated the sand loss due to hurricanes and submitted information to FEMA. Palm Drive Bridge – received information on temporary bridge structure; staff working with designer to finalize construction drawings and project manual. Duck Key Bridges – staff requested revised proposal from Kisinger Campo for repair design for the Tom’s Harbor Channel bridge, connecting US1 to Duck Key; revised proposal received; staff reviewing. Duck Key Security Cameras – Hawks Cay wireless system not yet installed; awaiting completion before cameras on bridge can be installed and hooked to resort’s system; letter sent to Duck key homeowner’s group president to update status. Duck Key Pedestrian Bridges – coordinating with pre-fabricated bridge manufacturer and Duck Key Security District to identify options; options with pricing received from Contech; potential pedestrian bridge design was forwarded to Duck Key homeowner’s group for review and discussion. Sunset Point Park Boat Ramp – project manual was approved by County Attorney’s office; Fish and Wildlife grant agreement was approved by BOCC; the project manual and construction drawings were forwarded to Fish and Wildlife for review on December 15, 2008; upon approval by FWC, the project will be posted for bids. Boca Chica Road Study – second appeal was sent to State Department of Emergency Management on October 3, 2008; additional information has been provided to DEM staff to facilitate review and approval of appeal; staff anticipates receiving revised project worksheet for all requested amounts by end of January 2009. Pigeon Key Ferry Service – received approval extending contract term through June 2009; staff managing on-going contract, including processing monthly invoices from ferry contractor and preparing reimbursement requests to DOT for payment though Joint Participation Agreement for ferry service funding. Card Sound Road/C905 Department of Transportation Project – staff working with Planning Department, Florida Keys Overseas Heritage Trail staff and FDOT to confirm prior commitment of District 3 impact fees has been terminated; upon receipt 18 of confirmation, Planning/DOT staff will prepare impact fee use request for BOCC approval. Cudjoe Gardens Private Roads – staff inspected three roads in subdivision to determine whether they meet County standards to facilitate having County take them over, per residents’ request; letter outlining remaining work required to bring roads up to County standards was sent to resident; staff is working with County Attorney to determine process and mechanisms for County to take over private roads so that they are county maintained. Tavernier Right of Way Encroachments – notification letters have been sent to homeowners advising them to remove right-of-way encroachments; staff has communicated with several residents to explain situation and satisfy questions. Emergency Fire Signals – Upper Keys – request sent to DOT to evaluate signals that aren’t working to determine if equipment upgrade is warranted (outside of County/DOT maintenance agreement requirements); DOT is working with county staff to determine cost-effective method for upgrading emergency signals. Old Seven Mile Bridge Repair – ongoing coordination and discussions regarding draft Memorandum of Understanding for bridge and island with DOT and DEP staff; no action this month. County Street lights – staff reviewing Keys Energy Services and Florida Keys Electric Coop records of County funded and maintained street lights for accuracy; requires review of lists, site plans, site visits and meetings with utilities to compile information; staff received updated information from FKEC for Upper Keys and is reviewing; site visits with FKEC staff are planned for January. CDBG (Community Development Block Grant) - staff is continuing to monitor CDBG program to determine next grant cycle opening; coordinating with Florida Keys Wastewater Assistance Foundation; reviewing required CDBG specific purchasing policies for County compliance; staff drafted a letter for County Administrator’s signature to Secretary Pelham requesting changes to rules to facilitate using grant for sewer hook up. Long Key State Park/Outdoor Resorts – at the request of County Attorney’s Office, surveying staff researched the ownership of a parcel of land that Monroe County has leased to the Resort; staff provided a legal description, researched historical photographs to determine approximate dates of work performed on the property and other issues pertaining to the condition and ownership of the parcel as needed by County Attorney. Big Coppitt Sewer Project - staff overseeing FKAA construction on three contracts for collection system installation to insure compliance with County procedures, including site inspection, attending construction progress meetings on all contracts, responding to requests for information from contractors and FKAA and investigating resident complaints and questions. Key Largo Sewer Project – staff performing oversight on four Key Largo sewer construction projects, including overseeing KL contractors to confirm compliance with Monroe County requirements, attending construction progress meetings as needed. Three more phases of the project will commence in January/February 2009. Engineering Services Ongoing Work - 19 Staff provided review of 2 sets of DOT construction drawings, providing comments where necessary. Office staff reviewed 6 right of way applications and issued 5 right of way (ROW) permits. Staff worked with County Attorney’s office to determine eligibility of appeal of after- the-fact right-of-way permit denial. Staff researched ownership of right-of-way in North Key Largo to assist Overseas Heritage Trail design firm with pre-construction permitting activities. Resolved requests from residents and Sheriff’s Office regarding Big Pine key traffic signal; DOT is performing traffic survey to determine whether light reprogramming is necessary. Inspectors made 1 permit inspection prior to issuance of permits to determine permit requirements and made 3 right of way (ROW) permit inspections after construction. Staff coordinated investigation of 10 ROW boundary determinations /complaints /violations from residents and other County departments, including Code Enforcement, Public Works, and the Sheriff’s Office. Inspected FKAA pavement cuts and repairs in 2 locations in the Lower Keys for proper road repair. Staff handled various citizen inquiries regarding wastewater assessment payoff inquiries, drainage and flooding complaints, miscellaneous sewer and road inquiries, requests for street light installations, and traffic signals. County property sales – staff coordination regarding sale of excess right of way on Geiger Key; researching additional county properties for potential future sale; no action this month. Ongoing coordination with FDOT staff to review street light agreement and inventory. Ongoing coordination with Hospital employees/DOT/bus shelter manufacturer to fulfill request for bus shelter on US 1 in Tavernier; no action this month. Dedication Ceremonies – staff coordinating with County officials, civic groups and other entities regarding ceremonies for the Murray E. Nelson Government Center, scheduled for February 17, 2009. Reviewed 7 different plans and made 3 site inspections for commercial stormwater management. Processed invoices/purchase orders for payment for multiple projects. Facilities Development – Freeman Justice Center – close-out phase of project; Certificate of Occupancy issued December 12, 2008; landscaping mitigation accepted by the City of Key West; litigation research and coordination with County Attorney and outside counsel ongoing. Solid Waste Analysis Project – review and analysis of Monroe County’s current franchise agreements completed; comparison of services and rates against other Florida counties is almost complete; executed contracts and information from other Florida counties received. Historical trend analysis and comparison spreadsheets are 20 complete. Draft report and presentation at 100% complete, with presentation scheduled for January 5, 2009. ADA Compliance Assessment – field survey of additional facilities and sites approved at the November BOCC meeting has begun; field surveys of all building square footage is 95% complete; field surveys of all polling places at 100% complete; beaches and parks survey is at 85% complete, with the report at 50%; lease agreement review is complete; roads and sidewalk intersection field survey is at 60%. Draft interim reports for Upper Keys, Transfer Stations, and Leases were submitted December 17, 2008. Full assessments of beaches and parks, inspections of the Marathon and Key West Airport auxiliary buildings and the Public Works compound are scheduled for January 2009. Big Pine Key Fire Station – project is 60% complete; truck bay columns completed; generator pad installation scheduled for week of January 5, 2009; roof truss shop drawings approved; site drainage completed. Plantation Key Fueling Facility – in design and bid document phases - front end documents (Division 1) in progress; final construction plan set scheduled to be delivered by AE in early January; agency coordination for permitting applications has begun. Key Largo Fueling Facility – in design and bid document phases - front end documents are in progress; architect directed to complete and deliver final construction plan set and specifications by January. Emergency Operations Center – Marathon – Request for Qualifications was opened on December 3, 2008, with 20 respondents; selection committee met to rank respondents in public meeting held on December 18, 2008; agenda item requesting permission to negotiate with the top-ranked firms will be on the January 28, 2009 BOCC meeting. Big Pine Key Park – close-out phase of project - waiting for final releases of liens from General Contractor and subcontractors, and payment of final payment. Murray E. Nelson Government and Cultural Center – project is 95% complete. Final inspections are underway, electrical work almost complete; telephone and data switching installation almost complete; BOCC broadcast AV system wiring to be installed by mid-January; final punch lists to be generated by early January; occupancy to start mid-January; BOCC meeting scheduled for February. Medical Examiner’s Facility – close-out phase of project - County Attorney’s office has prepared a response to the letter for delay compensation in the amount of $1,038,691.03. Medical Examiner’s Facility Wetlands Mitigation – SFWMD and ACOE have approved modification of permit to rectify conflict; planting of mangroves and herbaceous species is complete; “time-zero” baseline monitoring report is to be submitted in early January 2009. Architect/Engineer Small Project – RFQ draft is in process. Public Works Rockland – review by Building Department officials are still in process. Marathon Courthouse Renovations – review of design in process; draft of front end documents Division 1 is in process. 21 US 1 Fire Department Emergency Flashers – working with Signal Service on a proposal for the flashers at MM 106 and MM 96. Conch Key Fire Station – in the design and bid document phases - final design plans and specifications to be submitted January 2009; front end documents in draft process. Stock Island Fire Station – search for potential project sites in is progress. Jefferson B. Browne Building – on hold. Wastewater – Included in the January 28, 2009 agenda item: “Report to update the status of Wastewater projects through December 2008.” TECHNICAL SERVICES As a team we completed 235 work requests in December, continued the rollout of Metro Ethernet, prepared for the Pentamation upgrade, upgraded LAVATS, applied critical Microsoft security patch to all computers, etc. Worked on County Attorney Wireless link. Worked on quotes to bring Medical Examiner office on our network. VETERANS AFFAIRS CLIENTS ASSISTED: 1950 NEW CLIENTS ASSISTED: 69 FIELD VISITS 19 BENEFITS DELIVERY AT DISCHARGE 3 VAN CLIENTS TRANSPORTED: 177 (to the VAMC, Miami as well as other Miami area hospitals, without incident) The Veterans Affairs Department: The financial data for the month of December $36,241.00 indicates the amount of new revenue brought into Monroe County derived from claims for the entire department, including Plantation Key and Marathon. The financial data captured monthly will vary due to the Veterans Administration variable time frame on adjudication of awards, as well as the amount awarded. 22