Change Order No. 3
MONROE COUNTY
ENGINEERING/CONSlRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: Demolition of the Public Service Buildinq
CHANGE ORDER NO: 3
Total Previous Change Orders
Current Change Order
% of Original Contract Amount
% of Contract after Prior C/O's
Original Contract Amount
Revised Contract Amount
Change in Contract Time
$15.222.00
$6.417.00
0%
0%
$407.700.00
$429.339..00
14 days
Detailed description of change order and justification:
Due to environmental testinq for Dioxins inside of the incinerator at the PSB site. selective demolition is
required.
This will involve additional labor to hand demo around the incinerator.
The revised contract completion date is 12/04/03.
CONTRACTOR:
CONSTRUCTION MANAGER:
COUNTY ENGINEER:
COUNTY ADMINISTRATOR:
Dent Pierce
----/'~~
James L. Roberts
DIRECTOR OF PUBLIC WORKS:
/ () - J..~- 0..::)
Date
CMD007-1l/03/97
MEMORANDUM
TO:
Board of County Commissioners
From:
James L. Roberts
County Administrator
Date:
October 17, 2003
RE:
Change Orders
Attached is a proposed change order for D.L. Porter Constructors, Inc. for
Demolition of the Public Service Building for approval.
According to the ordinance adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are
placed on the BOCC agenda.
~...h' &..k:l
The Administrator intends to approve this change order on~, October-2r,'
2003.
-.---b ~k
_.~ (
James L. Roberts
County Administrator