Loading...
Item F11 BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY Meeting Date: November 15. 2006 Division: Engineering Bulk Item: Yes -X No Department: Facilities Development Staff Contact Person: Jerry Barnett AGENDA ITEM WORDING: Receipt ofmontWy report on Change Orders reviewed by the County Administrator's Office. ITEM BACKGROUND: There were 8 change orders considered for approval by the County Administrator for the period beginning October 1, 2006, and ending October 31, 2006, totaling $143,096.28. All were approved. See attached for details. PREVIOUS RELEVANT BOCC ACTION: On September 9, 1998, ordinance no. 026-1998 was adopted in order to provide that the County Administrator may approve separate, non-cumulative change orders for construction projects and professional service contracts in amounts not to exceed $25,000.00 or 5% of the original contract price, whichever is greater. The BOCC requested a monthly report of all change orders considered by the County Administrator. CONTRACT/AGREEMENT CHANGES: N/A STAFF RECOMMENDATIONS: N/A TOTAL COST: N/A BUDGETED: Yes NI A No COST TO COUNTY: N/A SOURCE OF FUNDS: N/A REVENUE PRODUCING: Yes AMOUNTPERMONm_ Year No X APPROVED BY: County Atty _ OMBlPurchasing _ Risk Management _ DOCUMENTATION: Included X Not Required_ DISPosmON: AGENDA ITEM # Revised 8/06 MONROE COUNTY FACILITIES DEVELOPMENT MEMORANDUM TO: David Koppel County Engineer FROM: Ann Riger, Contracts Administ Facilities Development DATE: October 30, 2006 RE: Agenda Item - Change Order Report AGENDA ITEM WORDING: Receipt of the monthly report on Change Orders reviewed by the County Administrator's Office. ITEM BACKGROUND: There were 8 change orders considered and approved by the County Administrator. They are as follows: 1. Change Order No. 20 to The Tower Group, Inc. for the Freeman Justice Building in the amount of $57,500.00 is to install waterproofing behind the stone cladding and brick facing in two coats. 2. Change Order No. 19 to The Tower Group, Inc. for the Freeman Justice Building in the amount of $37,288.84 is for time and materials to complete the security upgrades that were not included in Change Order No. 12. They include patchwork, coring, cutting, and chipping. 3. Change Order No. 17 to The Tower Group, Inc. for the Freeman Justice Building in the amount of $67,183.46 is to furnish and install a domestic hot water system. This change order will be paid by the 16th Judicial Circuit. 4. Change Order No.1 to Charley Toppino and Sons for the Big Coppitt Key Park for no dollar amount is to extend the contract time for substantial completion by 90 days, due to delays in obtaining the building permit. 5. Change Order NO.1 to Atlantic Civil, Inc. for Duck Key Recreational Pathway in the amount of $7,308.26 is to furnish and install one additional light pole to include the base and electrical system connection. 6. Change Order No. 21 to The Tower Group, Inc. for the Freeman Justice Center in the amount of $26,085.72 is to modify site lighting for pedestrian and vehicle traffic, $2,710.65; credit for holding cell door hardware $4,507.64; 3-way control valves for the chilled water system in lieu of 2-way, $8,317.40; additional lighting for artwork in room #3047, $511.19; and modification to the 2nd and 3rd floor lobby lighting, $19,054.12. The 16th Circuit Court will fund the last two items totaling $19,565.91. 7. Change Order NO.2 to Atlantic Civil, Inc. for Duck Key Recreational Pathway in the amount of a credit for $63,150.00 is to correct an error in the calculation of sod. The Contractor inadvertently calculated the area in square yards, and it should be in square feet. 8. Change Order NO.3 to Atlantic Civil, Inc. for Duck Key Recreational Pathway in the amount of $10,880.00 is to add 6,400 square feet of sod due to changes made to the configuration of the pathway. PREVIOUS RELEVANT BOCC ACTION: On September 9, 1998, Ordinance No. 026-1998 was adopted in order to provide that the County Administrator may approve separate, non-cumulative change orders for construction projects and professional service contracts in amounts not to exceed $25,000.00 or 5% of the original contract price, whichever is greater. The BOCC requested a monthly report of all change orders considered by the County Administrator. CONTRACVAGREEMENTCBANGES: N/A STAFF RECOMMENDATIONS: N/A Thank you. If you have any questions, please contact me at ext. 4439. AR w U .... I&. I&. o (I) .. G:::U) eo ~~ tic) ...."'" (l)ZI a:....U) w~o cO....... ~c(g 0)........ wl-o CJz"'" z:)c COO :t:u~ uww :z:A. I-w :t: i;1- O~ w~ G::: w o .... (I) Z o u ~ a;.E di 1:) ~.!2 B-g.E g'.8 ~~.!2 >-:>""0 C :::s ~"O cc .!!!,fi ~ IU - ",= ~~-8...; >- ~ 0 IV.!! o ~ ["lij ~ ~c=5~~~tiEMN~~ i c- IV~U~ fa IV 1:1 IU BE .c Cc:::S .... ..... clB~ ~IU~ EClVi - ~- g :::s ~ VI~ ~~ig;~~ ..... 0> IV ~ U "lij IV fi 1V'l5 o>U 0> Ilo.e 1V1llal q:; 00 -g~ IV C c :!:!~ "'~ :Eli! C t!~""'1:: fi. "2. j 0.0 ij""- 0 ~ ..4J.w.e ::::J:"cu IUVI IU ~u .... 0 0>1:1 >-:!:! ~i ~B go IE! 3l ~ ~ B ~ g''g IU IV , U < -tj.8 =>C~U.!:~ .o:::S .2'", .=5~ I~ U "t:= ~i~1~~ U 1:1 IU :::s Co. .., "0': IV-IU """0 .... al~vi M~ U~ :1: .c .b....j~.2'Q.."OEm\O ~ fJ : 5....U:: >.c Uc i~ ~ce g'~IV~ mlB i a..... "lij1U "ij1V"'; ) [~:ffi-g ~ '" 01 0 - .c"O.... lB1:I1V ~"5 ~ . 0."5 :::su 1U:2 ~~~ B=~"".!2~1V >'6fi ;E~w CT'6 ~:g Vi ~ ~ ~ ~ aF i u ~ ~ ~ eu '$ IV "0 IV..... li}* ~ IU .2 &~ 8~ g.... F~ > 0 Q w D:: ~e \0 \0 \0 \0 \0 \0 \0 \0 0 0 0 0 0 0 g 0 QU) ~ ~ M- M- ;:0- M- - It) It) z 0 0 0 0 0 '" '" '" 0 0- - - - - 0- - - 0 0 0 0 0 0 u ..... ..... ..... ..... ..... ..... ..... ..... * * * * * * * * ~ E . B "t: i ('I") ..... c: "0 :::s B ., Eo e lrlN ~iB IU VI..... VI IV go .....* .... !E ~"'!E o .... B '6 elV IU . 1Ua;"8 0"E! 3:3 .c1V .c.....E aI iO 1:)~ g'~ .... ~"O . ~ "ci u ~ g ~ :5 go g IV a.~ J:U m'" e Ee um IU am ~=~...~ 'l5 ..... ~ o IU Xl~ "0 :pU 0 .e.c....o> li u.c ~ :g~ u~- IV ~ IVU E :::s ~QJ >- "lij .2! Z .cc 8'; IV :u; "O.c .0 E 0 .....- E ~""'IU.o IV .E~ Xl .... "0 \0 1:1 a-g u.... 0 IU E e IU..... ~ .,.e .E ::: :::s :c .!2:::s =IV _IU golB 0>8 .... g .8 IU - ~fi ~ -IV IV &! .5~ tl'" :g>eq:; > ~ .s~ eZ -1:1 0 0> ~g 8 g' ~ "5,M IV ~ e - q:;ci> "0"0 "0 IV . IVO="O .c .0 ~'5 e- IV :5&.a ..... ILl "OlB IU~ .c 1ii.g~:5 .... m ..... .cIVB .e e Q e..e C"O ~.8 "0 .2:- 8 o~ 0 fJ-tj lUe ~ .!2"01V .- 1:1 '" ~ :p ~~ e_ e:::se "8 >- '6 IV '6 ~~ .... U e 3:~ .reo ~~aIfi ~ I F=> _ u U ~ ~ .--.. 0 ~ \0 '" ~ 8 0 '" " = g ~ M ~ ex) vi 0 ~ 00 00 It) 0 It) '" ..... Z ~ 0 ..... % ,,' " " ,,' .0 t")' 0' It) t") \0 ..... '" ~ ..... C ..... ..... ..... ..... ..... - .. 0 0\ " ..... 8 '" ..... ..... ..... ..... '" '" t") 0> 0> 0> 0> e e e ~ m c m m ~ :!2 :!2 :!2 .... e :!2 e e IU 0 0 0 U "5 "5 "5 0.. 1:1 "5 1:1 :c ~ al al al li lll>- 00 lll>- ~~ IV IV IV IV ~ u u u ~ irl~ u irll ~ 1il 1il :I:l a:~ 1il ';."lij a:.c :::s :::s a. :::s li~ ~ .., .., .., 0. lio.. .., IV 0.. e e e 0 ~ c ~ ~ IU IU IU U IU E E E ~ E ~ ~ 01 u u u ~ II ~ in :::s ~ :::s :::s .t 0 0 0 ~ Co Co <( * ClO N ~ g ti pf * ~ MONROE COUNIY ENGINEERING DIVISION CONfRACT CHANGE ORDER PROJECT TITLE: Duck Key Recreational Pathway CHANGE ORDER NO: 3 Total Previous Change Orders Current Change Order % of Original Contract Amount % of Contract after Prior C/O's Original Contract Amount Revised Contract Amount Change in contract time Revised date of Substantial Completion ($55,841.74) 10.880.00 1.51 $720,146.79 $675,185.05 No Detailed description of change order and justification: November 8, 2006_ For an added 6400 SF of sod. This was due to chanqes made to the confiquration of the Recreational Pathway. CONTRACTOR: CONSTRUCTION ENGINEER: SR. Project Manager COUNTY ENGINEER: COUNTY ADMINISTRATOR: CMD007-1 Ji03/97 ~b' l" .0(, Date 0-'0 -C' Date IJ/ Z5JG Date Change Order Attachment per Ordinance No. 004-1999 · Change Order was not included in the original contract specifications. Yes [gl No 0 If Yes, explanation: There is an additional 6400 SF of sod. · Change Order was included in the original specifications. Yes 0 No [gl If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes No X If Yes, explanation as to why it is not subject for a calling for bids: · Project architect approves the change order. Yes 0 No [gl If no, explanation of why: N/A · Change Order is correcting an error or omission in design document. Yes [glNo Should a claim under the applicable professional liability policy be made? Yes [gl No Explain: MEMORANDUM TO: Board of County Commissioners From: Thomas J. Willi County Administrator Date: October 24, 2006 RE: Change Orders Attached is a proposed change order for Atlantic Civil Inc., for the Duck Key Recreational Pathway. (Ch~ Order #3 is for an additional 6400SF of sod due to the changes made to the configuration of the Recreational Pathway.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval. assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Administrator intends to approve this change order on Wednesday, October 25,2006. Tho~/J:/ County Administrator TJW:adc Campo-Abra From: Campo-Abra Sent: Tuesday, October 24,2006 8:52 AM To: County Commissioners and Aides Subject: Change Order Attachments: 00002833_283.tif Attached for your review is Change Order #3 for Atlantic Civil Inc. for the Duck Key Recreational Pathway. Abra Campo Sr. Administrative Assistant Office of County Administrator 1100 Simonton St. Suite 205 Key West FL 33040 (J05}292-4445 10/24/2006 ra!S~ I VI I MONROE COUNIY ENGINEERING DIVISION CONfRACT CHANGE ORDER PROJECT TITLE: Duck Key Recreational Pathway CHANGE ORDER NO: 2 Total Previous Change Orders Current Change Order % of Original Contract Amount % of Contract after Prior CIO's Original Contract Amount Revised Contract Amount Change in contract time Revised date of Substantial Completion $7.308.26 ($63.150.00) 8.76% $720,146.79 $664,305.05 No Detailed description of change order and justification: November 8, 2006_ For lump sum item # 6 on paqe 00110-4 Contractor inadvertently calculated the area of sod in square yards whereas it should be in square feet. Contractor later aqreed to lower his bid by $63.150.00. CONTRACTOR: CONSTRUCTION ENGINEER: SR. Project Manager COUNTY ENGINEER: COUNTY ADMINISTRATOR: CMD007-11!03/97 I 0 . , (;, . fX:::, Date '0- .06 Date Change Order Attachment per Ordinance No. 004-1999 · Change Order was not included in the original contract specifications. Yes 0 No 0 If Yes, explanation: Contractor made an error in calculating the area of sod in square yards (SY) whereas it should have been in square feet (SF) · Change Order was included in the original specifications. Yes 0 No 0 If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes X No If Yes, explanation as to why it is not subject for a calling for bids: Contractor agreed to lower his bid due to an error in measurements. · Project architect approves the change order. Yes 0 No 0 If no, explanation of why: N/A · Change Order is correcting an error or omission in design document. Yes 0No Should a claim under the applicable professional liability policy be made? Yes 0 No Explain: MEMORANDUM TO: Board of County Commissioners From: Thomas J. Willi County Administrator Date: October 24, 2006 RE: Change Orders Attached is a proposed change order for Atlantic Civil Inc., for the Duck Key Recreational Pathway. (Change Order #2 is for the contractor lowering his bid by $63,150.00 due to his calculating the area of sod in square yards when it should have been square feet.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits, Change orders not within the Administrator's authority are placed on the BOCC agenda. The Administrator intends to approve this change order on Wednesday, October 25,2006. --1Y- .o:omas .:vIWilli County Ad"ilhistrator TJW: ode rl1~C;; I VI I Campo..Abra From: Campo-Abra Sent: Tuesday, October 24, 2006 8:51 AM To: County Commissioners and Aides Subject: Change Order Attachments: 00002832_282.tit Please review the attached. This is Change Order#2 for Atlantic Civil Inc. for the Duck Key Recreational Pathway. Abra Campo Sr. Administrative Assistant Office of County Administrator 1100 Simonton St. Suite 205 Key West FL 33040 (305)292-4445 10/24/2006 ," MONROE COUNTY / ENGINEERING /FACILITIES DEVELOPMENr CONfRACf CHANGE ORDER PROJECT TITLE: Freeman Justice Center Jackson Square Key West, FL TO CONTRACTOR: The Tower Grou~, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 CHANGE ORDER NO: 21 INITIATION DATE: Various CONTRACT DATE: June 16,2004 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price) ........................................ $13,804,000.00 Net change by previously authorized Change Orders ......... ... ... ...... ...... ..................... $1,147,437.32 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ......... $14,951,437.32 The (Contract Sum) (Guaranteed Maximum Price) will be (Increased) (decreased) (unchanged) by this Change Order... ... ... ......... $ 26,085.72 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $14,977,523.04 The Contract Time will be (increased) (decreased) (unchaooed) by .................. ( ) N/A The date of Substantial Completion as of the date of this Change Order is ...... ... ... ... ...January 25,2007 Detailed description of change order and justification: Chanae Order No. 2115 In resoons8 to Chanae Order Reauests (CORJ #7-R1. 45-R1. 49. SO. and 61. summarized as follows: $2. 710.f6 (::~::J 11.19 19 064.12 '2f.086.72 This Chanae Order Is .19 %, the orlalnal contract amount. Not valid until siGned bv Owner. Construction Manaer and Contractor ARCHITECT: {{lJ~~ The Tower Group Date JO/J~/d Date CONTRACTOR: DIRECTOR, FACILITIES DEVELOPMENT: Jerry B /0 -/1 0 , COUNTY ENGINEER: Date COUNTY ADMINISTRATOR Date FREEMAN JUSTICE CENTER CHANGE ORDER NO. 21 ANALYSIS Change Order Reauest # DeSCJiDtion Amount 7-R1 Modify the lighting on site to facilitate pedestrian and vehicle traffic along Fleming Street and Thomas Street: · Credit for changing 18 pole mounted light fixtures to 8 pole Mount fixtures, 8 wall mounted light fixtures, and 4 up-lights $(3,434.00) · 4 additional wall mounted light fixtures 6,144.65 · 1 pole mount light fixture for parts N/A TOTAL $2,710.65 45-R1 Credit for Door Hardware at the Sheriff Holding Cells: · Original electric locksets for 23 doors $(4,740.81) · Dummy locksets for 19 doors 1,118.15 · Credit for 23 bronze closures replaced with 19 aluminum (325.00) · Credit for 23 bronze kick-plates replaced with 19 stainless steel (245.50) · Credit for sales tax (314.49) TOTAL $(4,507.64) 49 Fumish and install 3-way control valves and bypass branch for the Chilled water system at each of the six air handling units, in lieu of 2-way control valves: · Additional costs for the 3-way valves · Labor & Material for installation by Weathertrol . The Tower Group 5% TOTAL $770.80 7,161.82 384.78 $8,317.40 50 Fumish and install additional lighting for artwork in Room #3047: 51 . Material . Labor · Sales Tax · The Tower Group 10% TOTAL (Funded by the 1f11' Circuit Court) Modifications to the 2nd and 3rd floor lobby lighting: · Material including estimated freight charges $14,058.34 · Labor 2,487.58 · Sales Tax 941.88 · The Tower Group 10% 1,566.32 TOTAL (Funded by the 1f11' Circuit Court) $19,054.12 $315.56 131.90 23.67 40.06 $511.19 TOTAL CHANGE ORDER NO. 21 $26.085 72 Change Order Attachment per Ordinance No. 004-1999 · Change Order was not included in the original contract specifications. Yes ~ No 0 If Yes, explanation: Change Order Request #7-R1 to modify the lighting on site was proposed by the architect m facilitate pedestrian and vehicle traffic. The credit for Change Order Request tuS-R1 Is primarily due to the vendor not being able m sell /oclrsets to our Contractor. They must be purchased by the end user. Change Order Request tf49 Is correcting the design for the chilled water piping system that had been designed with 2-way control valves, and could be corrected to have 3- way control valves. Change Order Request #60 and #51 W8IV requested by Monroe County to Include additional lighting for attworlr In room #3047, and modifications to the Hghtlng In the ~ and 3'" floor lobby. These will be funded by the 16'" Circuit Court. · Change Order was included in the original specifications. Yes 0 No ~ If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes 0 No ~ If Yes, explanation as to why it is not subject for a calling for bids: · Project architect approves the change order. Yes 0 No ~ If no, explanation of why: The Architect is not required to approve Change Orders for the Freeman Justice Center. · Change Order is correcting an error or omission in design document. Yes ONo ~ Should a claim under the applicable professional liability policy be made? Yes 0 No ~ Explain: .1. ~-,~' ~ 11 ~1 :1 :):1 Monroe County FOCI/HIes Development AUG 22 2006 TIME: RECEivED BY:----.eIt. SIXTEENTH JUDICIAL CIRCUIT OF FLORIDA MONROE COUNTY COURTHOUSE ANNEX S02 WHITEHEAD STREET KEY WEST, FLORIDA 33040 TELEPHONE (30Sl 292-3423 SUNCOM: 494.3423 TELEFAX (30S) 292-343S August 17,2006 ! -I Mr. David Koppel Monroe County Engineer 1100 Simonton Street Key West, FL 33040 RE: Freeman Justice Center Dear Mr. K.oppel: Please see attached the following change order requests from the Tower Group: · Change Order Request 00050 in the amount of$515.87 · Change Order Request 00051 in the amount of $20,429.91 Both of these COR's are for lighting changes in the Freeman Justice Center. The Court, using the existing Court Facilities budget, would like to pay for both of these changes. By using the Court's existing budget, there would be no additional costs to the Capital Fund, therefore we are asking for your approval to these requests. Tharik you for your attention to this matter. If you have any questions, or need any additional information, please do not hesitate to contact me. Sincerely, l ctcD Holly H. omina Administrative Services Manager CC: Chief Judge Richard G. Payne John Chandler, The Tower Group 'OUTING 0 ~~<~---~ I; .JJ. I()j'~_~._ 0 _. yY)Q V;Ji._,~ id~~~~D _~~~~n~> ,-ka-~""~-.~>--"",," 0 ~~=_>M~~' - 0('0 -} .Jx>.J(.., U~/~~/~UUO ~O:U{ ~AA ~b4 370 5401 THE TOWER GROU~ General Contractors ConstructIon Management Construction Design-Build Planning Slle Development Infrastructure Consulting EstimatIng Scheduling Value Engineering Post Construction CGCA3B309 UNITED ENGINEERING CORP. I4J 001 \j7 ~ RJ- September 19,2006 0417 -02294 Attn: Clark Briggs, Senior Project Manager Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Fax: (305) 295-4321 Monroe County Facilities Development Re: Freeman Justice Center (FJC) Subject: COR #7-Rl - Site Lighting Revisions SEP 19 2005 TIME: RECEIVED BY: -et- Dear Mr. Briggs: Please find enclosed Change Order Request (COR) #7-Rl for the site lighting revisions proposed by Gonzalez Architects (GA) in their Request For Proposal (RFP) #1, dated March 29,2005, and the site lighting revisions proposed by Currie Sowards Aguila Architects (CSA) in Item #1 of their September 8,2006 RFP. The Tower Group proposes to implement these changes for an increase to the Contract Value of $2,733.26 plus one pole-mounted Type SA fixture complete with pole as spare parts, and no change to the Contract Time. This change is implemented at the request of the Architects to facilitate pedestrian and vehicle traffic along Fleming Street and Thomas Street, and to incorporate resolution of grade conflicts first identified by The Tower Group to Monroe County and GA via Request For Infonnation (RFI) #9, dated November 9, 2004. Please furnish your acceptance of this proposal and process a Change Order to the Contract for this Extra Work. If you have any questions, you may call me at (786) 367-0549. Sincerely, J;cfJ--. John Chandler Project Manager Enel. : "/ ~', ,~ _.~.~,,'l'" ," J.~ ~" C ' . C,-'('L)'" --~~~7Jiii} '! ~.~ ... _ . ('-.i\ 1/, -/1 i (.1,1.""' /, J .'/)1.. V2._' COR No, 00007-RI (13 pages) cc: ITOMO (COR-7), FF (COR-7) 405 S,W, 148th Avenue' Suite One - Davie, Florida 33325 - Tel: 954'476-3200 . ~ax: 954-474-3111 7601 S,W, Lost River Road - Stuart, Florida 34497 - Tel: 772- 287. 7525 . Fax: 772'287' 7524 9440 Philips Highway, Sulte#5 - Jacksonville. Fiorlda 32256 - Tei: 904 - 292 -1811 - Fax: 904' 292 '4865 .......,J ...........J ...VVU ..L......v, .'['1..4 uv"'t .JIV ..Jolf:VJ.. U1H l~U ~r;lilr;hhl<lr;li CUl<P. I4J 002 The Tower Group, Inc. 4{}S SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 CHANGE ORDER REQUEST No.00007-R1 - -=.=:----- TITLE: Site Lighting Revisions DATE: 9/19/2006 PROJECT: Freeman Justice Center (FJC) TO: Attn: Clark Briggs Momoe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 JOB: 0417 Monroe County Facilities Development CONTRACT NO: 1 SEP 1 9 2005 TIME: .__~__ RECEIVED BY:___ RE: RFP To: TTG From: CSA Number: lA DESCRIPTION OF PROPOSAL Change Order Request (COR) #7-R1 addresses the costs to implement site lighting modifications desribed in Request For Proposal (RFP) #1 from Gonzalez Architects (GA), dated March 29, 2005, and Item #1 on the RFP from Currie Sowards Aguila Architects (CSA), dated September 8, 2006 (henceforth referred to as RFP #IA). The original scope of site lighting included 18 pole-mounted Type SA light fixtures only (See attached, reduced copy of Contract Dwg. #E0.01). RFP #1 from GA (copy attached, 4 pages) changed this scope to 8 pole-mounted Type SA light fixtures, 8 wall-mounted Type SA light fixtures, and 4 Type SC up-lights. The Tower Group (ITG) submitted COR #7. dated June 16, 2006, proposing a credit in the amount of$3,434.00 for these changes based on the June 6,2005 proposal from Patrick Power (copy attached, 1 page). Monroe County accepted this proposal in their October 6,2005 letter (copy attached, 1 page) and Patrick Power proceeded to order the fixtures blllied on this scope. CSA subsequently modified the parking lot to resolve grade conflicts in the GA design, which changed the exterior ligbting scope to 7 pole-mounted Type SA light fixtures, 12 wall-mounted Type SA light fixtures and 4 Type SC up-lights as described in Item #1 of the September 8,2006 RFP (copy attached, 3 pages). COR #7-R1 supersedes COR #7 in its entirety. COR #7-Rl is based on the the June 6, 2005 Patrick Power credit proposal for GA's RFP #1 and The Tower Group cost analysis and Farrey Quotation, dated August 31,2006 (copy attached, 2 pages). Please note that Patrick Power had already purchased 8 poles and 8 Type SA pole.mounted fixtures. As The Tower Group cannot return the spare pole and fixture, we are turning them over to the County llli spare parts in lieu of a credit. Please process a Change Order in the amount of$2,733.26 plus one spare pole and Type SA fixture for this Extra Work. This Extra Work does not change the Contract Time. Item 00001 Description Stock# Change scope to 8 pole-mtd. Type SA fixtures, 8 wall-mid. Type SA fixtures, and 4 Type SC up-lights (RFP #1 from OA) Change scope to 7 pole-mtd, Type SA fixtures, 12 wall-mtd. Type SA fixtures, and 4 Type SC up-lights (RFP #lA from CSA) Quantity Units 1,000 LS Unit Price ($3,434.00) Tax Rate Tax Amount Net Amount 0.00% SO.OO ($3,434.00) 00002 1.000 $6,167.26 0.00% $0.00 ~ 6 I '-jLJ- &s:- Unit Cost: Unit Tax: Unit Total: ,733.26 $0.00 $2, 3.26 ,-/ d 7/0. ~::_ .~-- -", ..L....., _.............. ..L..... -LV .l"fiA i:J..J'"t "'IV .tJlfUJ.. UNIThV hNGINEERING CORP. 7 P 1- 141013 - < Monroe County Focllltfes Development (\EP j 9 200r' '.) .L. [; IIM1::..)__.,,__,_,______ R~WE~:,_._~~ ~ c:r- ~ ~ ~ ~ \i) -_ ~ ;J \ '\ \ \ Q::C\lCDOIt)It)OOgo oaq"":C!,,,:C!C!C! .C! 5~OOM"'OOOO ~ o ... ,,'\. "\ ~ ~ ~ ~'~ ~ """'UJC\I~~ ,.. .... ~ :s i"dg ~""4i""~ cl \ r- T' ~ ~W:&UU:SOOOO ~ 0 ~~ (J)O"j/!. ~a'" 1 :z: ." ~o I- g@l@ .... ~ l"')~Z "'OI.U ys~ cl:. ~ a2 ...,- i-- ~ ~ a:: o~gooooooe j~ .olt)oeooo M~d.lridd== ..... " \, I, \, mC\l06l"')ClO.",...c6a)!Il "'''''''''''''''Oc.oM~ iM-.ilriuSw;rJ.UJ tIt~""M"'~""M :J ,.. .,. .,. o~~ ... i2 (l 1:; ;l i~~ ~ iWO<JU:SUCJCJCJ ~ ClO009CDS"'C\lClO ~~~~""="':~~~~ ~~:s:~ns~....t;~~ a..u:; .... .. .. ... ,.. ~ ~ ,.. M ? ~... ... .... .... ... j'U) 0 <t ~ ~ t:: C)~~U) t'J ~ im(J)5!~~~~ LL. ><ZZ;:;O~Za:ll- ~wm~g~8~8~CJ(J) et:~..,'lt""_""CJ~!i ~ ~><><~!2'" w ~ ~~~: XW:E : o U. "lit...- Wa.~ <I.;: 4( M~. ~(q - W (J) (q"litCWi -9\' z M ~ ~wwwttwwww ~..,..,..,~~,.....,...,~ ~ ~ M ......~ ~~ g~ \ ~ ,0 0.... (0 Dc /) :::r--. CVJ \ {\ C1 ('J) ~ ~ ~ \J\' if( ,0 --- ! \ ~ ~ ~ 'S- -.. ~ (\ ~ ~ ~ -t- <1j ~ ;% M ~ u~/~~/~uuo ~O:l~ ~AA ~~4 37U ~4Ul FILE No.129 08/31 '06 12:08 ID: .".. 'r' I 7": , UNITED ENGINEERING CORP. FAX: 7 (!-)- I4J014 PAGE 1/ 1 I~I~I~I~'.'S QUOTATION llSO!N.1t 146 Street. Miami. 'Ic)rtda JJJ81 VSA CorP,orllto Offlce: (305) 947~S45t . FAX (3GS) 940-3450 ~;'arreysl&\ollt . E-Mail: tarr.YM@$arO.net /)8/31/06 083106EML Monroe County FR~BMANS JUSTICE CENTBR Faclltlles Development I U~ ~cU Prices quot,d: p.O.8. Mitlmi IIME:__.____._--- Prlc&1l1 valid tor: 90DA YS RECENED BY:__ l.caiJ dttle: 6~9 WE::t::1<.S (fJl~cd on IVlllhlbilily M of .!lOWl dale) Oil": QalUJc: Proj eel: PaefH SEP 19 2006 Quo~rloQ 'lIbmltud by: Man,,)' Mlcotn\S Dlreot Lino: (305) 919.0UI Collular: (30S) 812.131 J QUAIl'/TITY --or I. 4 'fcrm!i: PriCIl!l quoted arc l>~dd upon quantities JOSE CLAUSltL.L IISllld. Any QhlUllt:l~ willlnv.lIdll~ qllnh~. THB TOW~R OROUP Oru~ will be processed upon re~IIH pl' PHONE: 954-275.1121- PAX: 30S.296.2587f4)34.474.3111 (I) Sisnc:d l\pprov\ld quoladoni (2) P\lro/aSi Otdet contlrmilli quantllllu I1NIT PRICE 'tOTA'. PRla SI.II0,98 SM4U2 so. 00 SO.OO 10.00 $(l,00 $0.00 SO.OO 50.00 SO.OO SO.OO SO 00 50,00 $0.00 50.00 $0.00 SMO 50,00 $0.00 $0.00 $0,00 SO.OO SO.OO SO.OO Sfl.OO SO,OO SO.(\<) $000 SQ.OO 50.00 TV'~ SA.W CATALOG NUMBER AND DESCRIPTION SUNV XAB.WM-INVERTeDILCKMI.SlJNV CPA CI'ROSTBP>-I50-HPSMTQD277.SIINV pr.UK S^MP. ^S TYn .~A' aur WA.L.1. MOUNTllU. Pr'Hnted t~t SO.OO 10.00 lJQ~ prices arc based Oil bulk purchli!le. I "'011 ilddjf'orl"ll1~rures a new quote mUllt be provided. Cll1\iaDltfe Quore mud be \lStd. no pQrtiab. SURTOTAI. TAX TOTAl. $4,.01043.9) $31101 $4.7SH~ ~....,.....,_............ ................- ............... ....~... "..... 'O.i..........L- V~,..I.. .a.......,...., ......,.~,'-I.l-..,L...o......,..I.,,-L.l'U vv..."... .. 10: Monroe County Facilities Development From: John Chandler Attn: Ann Riger TellFax: (954) 476-3200 I (954) 474-3111 Fax: (305) 295-4321 Pages: 1 Phone; (305) 292-4439 Date: October 7, 2006 Re: Freeman Justice Center (FJC) cc: TTGJMO (MCCM), FF (MCCM) 0417 - 02346 b] TOWER GROUP lbe Tower Group, Inc. 40S SW 148th Avenue. Suite On. Davie, Florida 33325 Phone: 954-478-3200 Fax: 954-474-3111 ~.H 4- Fax Memo .. I . - .:~. -II ... ~ .. o Urgent Sublect: Labor Burden for ITG Fiel<lForces o For Review 0 Please Comment 0 Please Reply 0 Please Recycle . Comments: Dear Ann: In response to your request, please accept the following breakdown of our labor burden costs for field forces at the Freeman Justice Center Project: Vacation and Holiday Pay Social Security and Medicare Unemployment Compensation Workers Compensation Health and Dental Insurance Payroll Services Per Diem Total 6.15% 7.65% 2.70% 24.72% 8.16% 0.03% 10.00% 59.41% We round this value down to 55% because some employees choose not to participate in the health and/or dental insurance plans, and because unemployment tax decreases every six months of continuous employment. I hope this clarifies this issue, and I apologize for taking so long to get you this information. If you have any questions, please call me at (786) 367-0549. Sincerely, John Chandler, Project Manager ~ ~dl~vl~VVU ~U.VO r~A ~u~ J/U a~UL LJNIThV hNGINEEHING CORP. 7 f<,-:L- . @003 ~J XI JJ ~, ij m.~. 1IIIIIIilll 'II f d. J ~ 'r ...-4 ~ ~ J ~ J~ ~ ..~.t.:a ulll Co [JJ lu --hi I Monroe County FacilitIes Development Co SEP 1 9 20D6 T1ME:________~ RECEIVED BY:____ lit' -, __J .l.:lI3~.l.S flNIV;:a,.:: db db ~ ~M/////<l ~I I I fill _ . . ~ 111~1' ~..I fft I~ I I." ~i .1 ~, : d I e zr I- I ~ - ,il! . I ", I ~!~I Alii ~tH 19.;~ ~tI"''8Mp'\OO'~!:J'l,..''''~.~O\nrmwO\looaBJ.:l31"O)Jrl\:d .'na uftJ"'I' .... I V ...."i:'VL Ul~ 1 U~.U ~rH:dN~~<<lNli CU<<Y. ~ 7 {<-2 ~004 ~._ 604-'=''/ oM Gonzalez Architects Architecture · Planning · Interiors Monr~ county FOolI/tI&S Development Date: To: From: Project: Re: Cc: March 29, 2005 Greg Ga!m.in, The Tower Group Jose A. Gonzalez, NCARS AIA Freeman Justice Building Site Lighting Revisions - Request for Proposal (RFP) # 1 .Larry Chalmers, Director of Construction & Planning, Monroe County M E M 0 RAN DUM SEP 19 2006 flMf::___P .iJ.-- RECEIVED By;~---"--'-'t. 'C- '-.." Please see attached Site Plan, sheet EO.O I for the revisions to the site lighting fIXture type and location. The revisions are 'clouded' and include the following: (j) Front Entrance - Relocate pole fixture (SA) to accommodate revised parking. Add (4) lights (SC) to up-light columns. ..... "'" ._.....~ -, ~'l Thomas Street- Remove (4) pole light fixtures (SA) and add (4): wall-mounted fixtures. \.: .::.- _ ...____''-~'---...". .........1 : 'iiFlemin~ Street - Remove (6) pole light fIxtures (SA) and add (4) wail-mounted fixtures. ...... The site light fixtures are to match existing site lighting. See attached information provided by Monroe County for the existing site light fixtures. The wall-mounted fbcture to be used is Security Lighting Systems, Inc., fixture R WS 70MH DL VfH 277 - see attached specification. Please submit a proposal for these revisions. SA- - 9 S C-- J-/ S D-- B ~sjo~ 32 East Bay Street, Savannah, Georgia 31401 * (912)201-9888, FaI (912)201-0240 :1.20.-\ North Rooseyelr Blvd.. Key West, Florida 33040 it (305)'29~3i48, Fu (305)294-821 i 160~ _-Utoa Road, p~ 503, Miami Beach. Florida 33139 * (305)6i2-9044, f:u (305)866-8324 TrG (0(2.d 7 Vv/~u/'VVU ~u.v~ r~A ~u~ J/V il~Ui )./ ",,'j :'- I " 1/" " I," -. I' ')''\.\ 1/ I.' '. I' . " I " , ~ l- I/ ,t' W ! ".. w ", 0::: I .). l- I/ tfl , " , , .. " , . 1,/ 1\ ", () " Z I ~ 1(' " w " ...J I'. u. 1// ", I" " I'> " ,<, "'., , I ---- "'\ "~ \ /' ,,, '. i "'-,. L..........., ..,>, ;,,' >', I i( , " .. '\ "..-' , "', .- " -' " \'. "" l)l'HlhU hNlilNhhKlNG CUKP. / - ~J.J-- ~ 005 fe..- !.J:;..,) ~ /' Monroe County Facllltles Development ~ lWl.1lr SEP 19 2006 ..') o liME ....~.._ . .,. Re:C~MD BY: ,__pO, "'M'~ ,+ I [XJSTING AHND IlIJlG.1 ~ I I _ce. ,.J.::/ll'C nw at IMIl I ~ I I =e. 11 ll"l:"" ':;7. JA (r /' I . . . I"'th-+"lIAi~"11 i I rffj- "j- II I I I -1IllII1._&oII. I I lIAO... ,..... ~ftcIi c.=vt__ ~ I - I _ I " 'I ~":.:'..J -- r-.:ooc 1''''-II;:;::-bt''lllIAl '_I I '",./~ ~ 1'.,,) I l...._______J IT1""J L I .. I .. r I ............._"'-""""'TO< ~ _l'I'1I_......=../' ~1IIIl4"'"_. ,/ / ,. / I / I I i I FroM ArUActj I lIROPtm " \ \ ........'. ...... , I''''"' rJ Ul~ INEW JUDICIAL aUILOING I ~~ ;"""1 .0 ! o. , .0 i 1 ..... .,.... ---- i I, ;.-. ^ " . ~,.~~.a'...' ...-.. . "..I._.m ~, : I I ::, ! I I ! J; I ./.... -- ,/ ==::J TlG //' (/ /' .- '" -d:L7'" '_/ SITe 'O~ .~,.........\ ~ '- I -( '1 :-.;:;..;;..-- ==~ Vie'. - - ~ .~ /1 ; r-......... , . --- -L" . ..L V ~ J...s....:.s. v v '"l' u I V '" ~ V.l.. Ul~ L LJ:\U \ ) o 1 ,/ / .-/' f % _ 6' 11Ve CIIl:75 loll/<.. _EOI.U ~ ry-'-'-" ~IO ou::T'! m-.~ eE'RIIlQ! IU"A /IC'l:: 'f " L .' } 6' L '1 "" "I ~g,CE OI'r~ IC/lINC II'4CCll Oll'Cll vrunu. ~ ...-rt_ ~ ~~ _A~ ~.AIL .. ., + '1 / <:f\ (N~V0) ~ SD := + B - - .--- L' 5C -;;. + ':{ ~/. '. ,'---=----- -.-.-' sp\ ( GirD) - -18 ... I I I I ... ) ...-- ...- , -.- f0 L,/ . :.. ................... (' "- 00" ,. ' 1'" " /. '- ...... ' /'\, K " '" """ /"'- (. , ~ WM_ TN'S: >, I=: 0:.::: (~.. '-.", _.....IIlOIJND ~......re:ll'miliO( 2-" ~ CUCTS ...... SQtClUl.( .0 No.6 ~nM f~===1 \/ '" '\ ... "-..j 0", , /' .' "- ( '. '''', , 1'(>"\..... ' . , ... ' , )', I., . 1(:\ ~ "'-'" i)..... '. I'" '. I '}\ ; .,,1*' . i. ,-.' !.:' " I ...... 1 . i --- ""'aN""~NC (;U1<1-' . 7 D-~ / ". @006 Munroe COvnl'J !'qclllffes D0VGlop~enr SEP .1 9 2006 I- W W " I- (J1 TIME:...__.,.~~_._, RECEIVED 6Y: ~--.;J1._--- I ~ ~ I -~. ~~ Pm! f'IIiA,I.4t.....~ -4 E (j Z ~ W .J \.l.. [LXlSnNG ~NO SI.ilC.1 ::.' QW..~ ~ ~~ t=> ..... ~... inl'"'v I , ~ ,., ,.., I~O:W JUQICI.'(. BUI~OINC J .. 1=> 1:1 1:1 I I ! ! j---' :--- .., . , I '.../' : I ' 11" r' r r r ( ~ ~~~~~.1 ---- '1Y\A. TC.l^. ( SH~E, '~. "7.'\'~ .7X ;. :. c..... v. r ~ ! '_1'1 TrG c;;edJ= 7 .- /;:::- ; " ( I " I IOU) COUIW'lOlJSc:j r t:(ISTlNQ ol.Ccq ~ ~..- I ~-=4 (1Fl<.l.l~1 i PRQPro:' \ , \. ,......-----, " -......, --- Yfw:..r;~ ~...... '.:l'\o()of...~&e"'I.~ , I ~, : I ; ~I ' ' /D " ,,!~ J~'''--'- '-.-,-. "'" I ;L '; Fr;~~ j~tice Cente~;:'*, "" " PlemiAs SIReI J ~ Weft, f\Qri41 !. i ' 0. ,..~,-"..__.._, :\..1 .... - ..~ ~"" , ' ' . :'?', .. o ... , "0 , .s:: ,I :, ~ jlii 0. ,,": " ... IT] ~ J:l~ I:lJ N IZI. 4J . . ~ e II s j Ii Cl Ii ~ // "'",- 0. {t I i. _j__ J Cdlf. --...:- /~ ./'. ~./ /",.// /' //' ,/ // /" /.- /-'" \. /' (111\ '!;/', ,(I , ,1\r'\\"--~ ..... . , .;:...- '/;, r .-......... 1 '- " ""'iTE PLAN -- I .:::In'''''- "~,.:::;, "\.",>-- "~\ l/VW':,~ ,/ t.O F 2- ===:: -- . r,./QMAS ~', " , , ' STR'~-=.~ .....w....."".. ......"'......'-J . ........._.."'~ 007 Iacksoa Square Reuovacions ~. .. '}'f.-J .....;..- PiStori.ao Il1C AJam --... Jt".a.-.UMIAl__ .......... .aICl IOI.tIlIJ* , r . ~............. Franyi~ Eari=a~ lll~. '........ZNI_ onroe County ,~ "'" FaCilities Development. SEP 1 9 2006 TIME: " RECEMD BY:--=':ur-- ..._ WI ",R"l.,,,",,,,,LIof1C1t'111IiIC .., IUJfYll ~u." ~ ... &oK ,''''' _...... ;0....0.. ~"'" & 1.IJ.Clt ~ lI!l'll5/Ol Il:'t ~_.flll. s rTE P LAi" """ '/'5'.,'.0' - ~..., ...."',~ '-""", ~t. j4/1. -"I '\ ~O.Ol L TIG Q;{2. ~7 Ul-'.l..l.UU nl"\.:rJ.l~.c.nl\J.l~u \.tUl\r. 19J UUIS ":.Vl~. .' / / i!:~ . ' . . 7 k~J- PATRICK PDWER CORP. Electric~1 Contractors and Engineers COM,'vfEACIAL · INSTITUTIONAL · INDUSTRIAL June 06, 2005 The Tower Group Mr. Greg Galmin 405 SW 14Srh Aveoue, Suite 1 Davie, Florida, 33325 CDN.~ONROE COUYrt VIlI/JCTlON ~ENU AU 05 1L,m: Ref: Freeman Justice Center Subject: Cost Proposal- RFP #H PROPOSAL After carefully reviewing RFP #1, described as: Site Liehti.a2 Revisions. on draVYing number EO.O 14 revision dated on 03423405 "Site Revision". there was a cost' impact found on our scope of work as c: credit f~r the amount of $3.434.00 Our proposal is good for 3Q days 01' untilconditiotlS change. AD. example of change on conditions 'Will be pouring of the slabs. Lavout. Cor;n~. Cuttiml and Patchin~ has not heen included in our DrODosaL Please contact me if I can be of any further assistance. Monroe County . FaCilities D~ve'opmeOt Sincerely. Iv~ M::r Project Manager SEP 1 9 2006 TIME:__ 4'"l., RECEIVED BY:--ill " cc: Micha~l J. Driscol1, PPC Jose Clausell, PPC " 5691 1'1 E. 14ch A'/snw3 · Fort Lauderdale, Fforida 3333a. Teler;ho.1S (95::1J 491-7745 0 Facsimile: (SS('tJ 772.2126 TTG eel!- 4/:. 7 ~_c ~~, _.......,_ .............I..-.L ..1.1."..(" VV"'T ....,v ...,"tV~ OK~~rY ~o~~~,,~E (305) 29.4-4641 .- C';,~'p OClober 6, 2005 '.,. J~; "~ ~~' '~" Greg Galmin The Tower Group 40S SW 1481h Avenue, Suite 1 Davie, FL 33325 U l' ~ u~u CI' b 11,CC1< 11, li l;UKt'. l4J 009 / 'j):J- (.'.... "'---- GA.'., - CQ7C BOARD OF COUNTY COMMISSIONERS Mnyor Dixie M, Spehar, District J Mayor Pro Tern ChDrles "Sonny" McCoy, Oistric Geotge :'IIcugent, Districl 2 David p, Rice, District 4 .Murray E. Ne/aon, District 5 Monroe County J::aclllfles Development SEP 19 2006 TIME: RECE~'-~---~' Dear Mr. Galmin, Re: Freeman Justice Center-Credit to Owner for Deleted Light FixtuTes In reference to the Tower Group Ch.ange Order Request reoeived in our office August II, 2005 in the amount of $3,434. for credit to Owner on dele1ed exterior tight Bxtures at the Freeman BulIding; the format appears to be acceptable to Monroe County. Tbe fom~at and content appear to be consistent with your contract and with previous credits to ilia Owner (Chango Orders #1 and #3) whelrein there are no Iloe items inolusive of overhead and profit as cited by Gonzalez as hill basis for recommending disapproval oftbis Change Order Requeat in his August 30, 200'5 memo to our otllce. We are at n loss to explain Mr. Gonzalez' recommendation for disapprovaL Therefore please aocept this letter as DLlthorization ftom Monroe County to notifY your sub-contractors that the proposed oredit to the Owner is acceptable. Sincerely, ~~~ Alan French ~ 1100 Simonton Stn:ct K~y WC::s:, FL 33040 Tel: 305-292.4429 Fax: 305-295-432 J -~, --"-V' _U'<J...... --"-V..L.L J."L'l.A uv"t: '-'IV V"t:U.l.. VI'll l~J) ~l'IlilNhhJ<lNG CURP. 7 ~-::j- · ARCHITECTS 141 010 ~. CURRIE · 'SOWARDS · AGUILA ~w''''- .- -- ----~~ --~--- --.-----.--- -...- Robert O. Currie, AlA ' Jess M. Sowards, AlA ~ -- Jose N. Aguila, AlA o ~,., - (2.\00 September 8, 2006 John Chandler The Tower Group 302 FlemIng Street Key We~t, F!orlda 33040 Monroe County Facilities Development Re: Freeman Juetrce Center Project No. 050906 SEP 19 2005 DC'ar John, (1M!:: RECEIVED BY: -- You are directed to provide prop06ale for the followIng: 1. The added e><terlor lightIng for the parkIng area, as defined by the new approved photometric drawings, ", ' ~ 2. The added eally port related Items a~ defined by drawIng "5PC-11l from C5A and drawing 5-01 from Pll5torlno. Th'e 'ncludee but Ie not limIted to, wall5. columne. l7eame. canopy, access doors, ~ecurlty folding eates, overhead door, and vtlnts. t" 3, Garage area BXhaust fans as shown on drawIng "M.1" from C5A/TYEC. 4. New security fence and gate at !South west corner of building at FKAA property along Thomas street ae shown on "fence" drawIng from CSA. 5. New louver at !South west corner of garage .135 shown on "G-Louv" drawing from CSA. If you have any queettons. plesee call m~ at the office. Thank you. Sincerely, '- Hank Goldman cc: Clark Brle9~ The Tower Group, Inc. / fORMERLY ROBERT 0, CURRIE PARTNERSHIP. INC.' AlA Fl.ORIDA fIRM Of' TtH Yl!AR 2000 1 .3 4 No rt he a s( Firs t A ve fl u e . 0 e ! ra y fl e ac 11, F 10 r Id a :l:l 4" 4 ' 5 6 1 .275.4!i1 f'; 1 . r a x, 5 6 I .2.11.3 .8 I B-1 . ^ A 0 0 n :< 27 I www.currlearc.com "7i7.f' fey !~.;/ i~h't l~' f?,~ _....-r ............' .....V'V'V' ............1..""' ~.nA UU~ tJlU V"tVJ. U1H 1l'..V f<..NlilNf<..f<..J<lNl:i CORP. 7 R -=:f- 141011 SUBMITTAL NO. 16500-05 PACKAGE NO: 16000 ..... .. rhe Tower Group, Inc. 405 Southwest 148thAvenue Davie, Florida 33325 Phone: 954-476-3200 Fax: 954-414-3111 TITLE: Photometric Analysis-Parking Lot PROJECT: Freeman Justice Center (FrC) DRAWING: Sun Val1eyLt~ Dwg. #Ll STATUS: NEW BIC: CSA REQUIRED START: 9/6/2006 REQUIRED FINISH: 9/15/2006 DAYS HELD: 0 DAYS ELAPSED: 211 DAYS OVERDUE: -9 RECEIVED FROM TTG IC SENT TO CSA HG RETURNED BY CSA HG FORWARDED TO TTG Ie Revision No. Description / Remarks Received Sent 001 Photometric Analysis 2/7/2006 2/8/2006 Original Drawing is 18x24, copies are llx17. Review Comments: - Min. 2 ft-candles - Max. 12: 1 light-to-dark 00'2 Photometric Analysis 9/5/2006 9/6/2006 Drawing Returned Forwarded Status SeplllsPrlnts Date Held Elapsed 2/17/2006 2/20/2006 DIS 6 o 13 . NEW 7.. Q.."onroe County 0 .-aOll!fte< r'>r;ve1ooment SEP . '. . .. 1 t"J "'_'J.J lIME:_ RECENED BY: SHOP ORA ING SUBMITTAL REVIEWED REJECTED 1:1 REVI EWEO AS NOTED 0 REV1SE AND RESUBMIT 0 SUBMITTAL NOT REQUIRED Cl RET~&: WITHOUT ACTION ' / 8'1':. DATE: ~/ ~ CURRIE SOWARDS AGUILA A CHITECTS 134 N. E. 1ST Avenue Detray Beach, F/orld& 33444 THE TOWER GROUP, INC. THIS'REVIEW IMPLIES GENERAL CONFORMANCE WITH THE" DESIGN CONCEPT OF THE PROJECT AND WITH 'NFORMATlO~, alVEN IN THE CONTRACT DOCUMENTS ONLY. REVIEW OF THE SU8MITTALS BY THE TOWEA GROUP, INC, IS NOT TO BE INTERPRETED AS A DeTAILED INVeSTIGA nON OF INFOAMA 1'1 Of. PROVIDeD IN THe SUBMITTALS OR AS AI'f1AOVAL TO OEVIATE FROM TH; ReOUlAEMENTSOF THE CONTRACT DOCUMENTS 'to AflPROVEOAS SUMS1TreO 0 REVISE AND RESUBMIT fa APPROVED AS NOTED 0 REJECTEO AND RS-SUBM!: o REVIEWED JATE: oG H: 'ROJECT: I!OP DRAWING ~: ~ f ~~I r:~ r2.~' '~-7~ ~~. , LtC:: I,:..IJ I E ... .~~ ...~.. L.:.::l ::I .nPlll","~~;~~ 0 \ ' 1I., ,.....' oj" l' .'..'; "' ~ ""I ' ,. L,_,__..."_~__. The T:."wer Group, Inc. ~~W''1.\V.t.fJ\ll__r__'''''_ - 1iJ)~~~~W~~1 lf1) SEP 7 2006 l1V CURRIE SOWARDS AGUILA ARCHITECTS ...._....t..,~__ __. .._~.~~__--=,::::._._--~ ... ~......... .......... ..,. v "'~V..L _1 l"'l~.If~l"lM'Il wur....... 'Mtul liMIt ....y:,'~ 0.....,.....,... -- _,,.,,.,.W ~. ..~. en r- '"l r- to ,.... v "! I"'i r- .... r- to ~ V r- r- "1 r--: r .... .... ~ 0 .... r-i ~ ... lJ"~~nLl nlH:J11~nnKll'Hj L;Ul<l'. I4J 012 "^lIl1uneJcfslIlIl/flljlll' :.IM6t I W . l:J3J.N30 30l.lSnr N'rfW33l:J:/;(/If i (.paJO l\f) 1.I01l."';~O IOIlWJwnll1 JUJOd-,(e-llIfOc/ _ ~ ~! ~ ~ : II II f'i !a J ! II' tl i . J '" IIf I 1" 'I' III I ~ d ill Ii J J * ~ ~! ~ . I II ~ . : .S __ - . . ~ -- 1:.'i::J I .1 Iliff II Iii ! 1 ; t;tJ'f' If~ !]. /!!ijf f :s ~o]~... il lJ !a:d:3o'O i ~ ~ I !:l b ._~ ~ ~)1 'ii!r:m!t1ifr~... <0 ! __l11Imt : dOiS II"" "..~ ,. , I "lL" .... T''/ ----- , f II~j ~MI i .~ 19 2006 .,...-.............~~----- l'he rower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 CHANGE ORDER REQUEST No.00045-Rl Phone: (954) 476-3200 Fax: (954) 474-3111 TITLE: Security Door Hardware Changes DATE: 9/11/2006 JOB: 0417 PROJECT: Freeman Justice Center (FJC) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 CONTRACT ~tToe CounJ Facilities Development SEP 1 9 2006 nMf:___~ RECEfI/ED BY~'-"-' .----- ~~~.~ -~---"_<oo___....____ RE:EST To:TTG DESCRIPTION OF PROPOSAL From: CRAFTMAS Number: CROm The Monroe County Sheriff's Office (MCSO) requested that TTG furnish Southern Folger Model 10300E electromagnetic locks for the holding cell doors. TTG included all the door and door hardware changes in Change Order Request #23, which was ultimately approved as Contract Change Order #12, except the material costs for holding cell door hardware and the electromagnetic locks, which were pending final verification of door swings and locking preferences. With the door swing and locking preferences confirmed, we are pleased to submit our proposal for the security door hardware changes, Change Order Request (COR) #45-R1 COR #45-Rl supersedes COR #45 in its entirety. COR #45-Rl excludes the costs to furnish the MCSO-specified Southern Folger electromagnetic locks based on the enclosed correspondence from Southern Folger's regional distributor, Craftmaster Hardware, explaining the manufacturer's restriction of sales to certified contractors and end-users only. MCSO must furnish Southern Folger Model 10300E locks, as indicated in TTG COR #45, in order to comply with the door frame modiifications that are part of Contract Change Order #12, as well as to comply with the door hardware specified by this proposal. TTG proposes to implement the holding cell door hardware modifications for a Contract Price Decrease of$4,507.64 and no change to the Contract Time. This proposal is based on the attached quotes from Craftmaster Hardware for the original scope of holding cell door hardware and for the revised scope of holding cell door hardware. Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount 00001 Storeroom Electric Lockset 12.000 EA ($393.00) 7.50% ($353.70) ($4,716.00) (Original Scope) 00002 Storeroom Lockset (Original 11.000 EA ($2.26) 7.50% ($ 1.86) ($24.81) Scope) 00003 Dummy Lockset (Revised 19.000 EA $58.85 7.50% $83.86 $1,118.15 Scope) 00004 Bronze Closer (Original Scope) 23.000 EA ($150.00) 7.50% ($258.75) ($3,450.00) 00005 RH Aluminum Closer (Revised 1.000 EA $155.00 7.50% $11.63 $155.00 Scope) 00006 RH Cushioned Aluminum 7.000 EA $165.00 7.50% $86.63 $1,155.00 Closer (Revised Scope) 00007 LH Cushioned Aluminum 11.000 EA $165.00 7.50% $136.13 $1,815.00 Closer (Revised Scope) 00008 Bronze Kick Plate (Original 23.000 EA ($21.00) 7.50% ($36.23) ($483.00) Scope) 00009 SS Kick Plate (Revised Scope) 19.000 EA $J2.50 7.50% $] 7.81 $237.50 00010 Door Silencers, J OO/PK 1.000 PK ($10.50) 7.50% ($0.79) ($10.50) (Original Scope) 0001 J Door Silencers, 1.000 PK ',----/ $10.50 7.50% $0.79 $10.50 100lPK(Revised Scope) Unit Cost: ($4,193.16) Unit Tax: ($314.49) Unit Total: ($4,507.64) OOA\[1l@WtillnlJ L-l.~-. R-L O\tl-0"204, Craftmaster Hard"vare Co., Inc. ~J..!?;J Wholesale Security Hardware -. - 190 Veterans Drive Tel (201) ?s8-0Soa ext. 100 NorttwaJe, NJ 07647 ~ax (201) 768-3883 E-mail: msoingeIQ@craftmaster."et WIMV .craftmaster .net August 18, 2006 Mi. John Chandler The Tower c.?rouP Re: Your P,O. 3 0417-0451or (Freeman Justice Center) /' ,I Dear Sir, ; Due to OUl' contract with Southem Folger Detention EquIpment Company we can no longer sell their products to arlyone except local, county, state & federal correctional ir1$tit1Jtlons or a limited list of detention contractors who have completed Southem Folger's certffication process. We would be able to sell the products to Monroe County r they issul9 us a purchase order directly. I'm sorry for any irlconvenience this has caused. Please let me Know If I can be of further assistance. Monroe County FaCI/fNes Development ~ Yours truly, t,spngeld President SEP 19 2006 TlME:____~__ RECENED BY: -_. ---.-------.. I Craftmaster Ha1ware Co., Inc. WHOLESALE LOCKSMITH ~L1es - DOOR HARDWARE 190 Veter~ns Drive Northva1e, "J 07647 TOLL-FREE: 800~221--3212 local: (201) 768-08081Fax: (201) 768-3883 FCld 1.0. .13-2733361 I I I j' Qu_t1.... .a6d fo. ... day. unless renewed in writing, ATT:MR.JOHN S.CHANDlER We appreciate the opportun' y to quote on the following... ;;::.ep I I UOlu:'l-oa I ne lower Group V.J, V"_iI ..;:.......Y'-J "'""..tJ.I. ""'t.I~IVV...1UU..J '-"'..... I 1'lH,;) I 1:.1""<; ~~mwW6.\1:W Quote For: TOWER GROUP INC 405 SW 148TH AVE,SUITE 1 DAVIE, FL, 33325 305-296-2587 Ljr:;. R:j.. p.5 I"""AI.:ll:. tJ.j C..:RC03 Quote Date l'1e Sep a. 2006 Qugle Number 0010Z79 Customer No. J $P CQ999 HOUSE2 Ship Via U.P.S. CUST.EXP. Terms C.O.D. I Quotation I i . Qualltity una 118m Number D crlption J BE-93K-1DT-150-Si~,DUMMY I.OCKSET CLOSER RH LC-4111CUSH-RH-l CLSER lC-4111CUSH-LJi.. CLSER HG-190S-8"X34 -32 ,!'LATE STAINLESS STEEL DOOR SILENCERSf1001Pf<) . I I I I I I i JJ '^ .{ ,{ Ij 19 EA-I- i EA LCl4011-A1..-RH 7 EA-I- 11 EA-I- 19 EA _fo 1 PK IV/SR64 A. Un It Prlc:o !xt. Prlc:o 58.8500 1,118.15 ~ 155.0000 155.00 ~ '95.0000 1,155.00 165.0000 1.81~.OO V/ 12.5000 237.5Cl / 10.5000 10. I 1. t " i :' j- j\ Please refer to quotatio er. Quotation Submitted by: -. Total: 4.491.15 . PLUS ANY APPLICABLE TAX. OR FREIGHT CHARGES 09/11/2006 MON 10:41 [TX/RX NO 7728] f4J005 "">::OJ..! I I 1I0 I U .Ltoa I ne lower Group ~-_f' to,J~1I ...._....."" .u.... (U'\.,hJUV,,", 305-296-2587 p.3 $ C"""'~,= L,iS R:+. Q~a:4' .2 Craftmaster Ha ware Co., Inc. WHOLESALE LOCKSMITH SU PLIES - DOOR HARDWARE 190 Vetera,ns Drive Northvale. r!lJ 0'7647 TOLL-FREE: ~OO~Z21-32'2 local: (201) 766-0808 ~IFax: (201) 768-3883 Fed 1.0, lt13-2733361 I I , i I I ~ . ~ " ~W~IFl(j Quo1& For: THE TOWER GROUP,'NC 405 SW 148TH AVE,SUITE 1 . DAVIE, FL. 33325 Quota Date ,Par Sep 8, 2006 Quoto Number 0010278 CUlItomer NO., SP C9999 HOUSE2 Ship Via U.P.S. CUST.EXP. Terms C.O.D. I Quotation' ~ Quotations valid for 46 days unless renewed in writing. to quote on the following... Qalantir, um It.... Nwn1:ler ee;cription Unit Pric. I 12 EA -1- BE-93KW7-DE~15[)"S3-813,STOREROOM ELECTRIC U . /393.0000 LOCKS ARE PRICEO W/CO E WILL NEED J<e'rt.rA.V 11 EA -I ee-93K7-1SD-S3.slOREROOM LOCK,613 J 2.2550 23 EA -1- LC41f1-4116-HA~ING-695FIN.lSH..oARKBRONZECLS J150.0000 CLOSER ABOVE IS A HAN elSER,AND NE 0 TO KNOW SIZE 1 THRU 6 23 EA -1- IV-8400-10X24-613 ICK PLATE 21.0000 CHECK SIZE 10X2 ?? 1 PK rVl5R64 DOOR SILENCER,1DO/PK) fO.~OOO Please refer to qootation Q01 Quotation Submitted by~ Ext. Price 4,716.00 // Z4.81 / 3.450.00 ../ 4~.OO 10.50 Total: 8,684.31 ~us AHV APPUCABlE TAX OR FREIGHT CHARGES 09/11/2006 MON 10:41 [TXlRX NO 7728] [4]003 THE ~ TOWER GROUP General Contractors Construction Management Construction Design-Build Planning Site Development Infrastructure Consulting Estimating Scheduling Value Engineering Post Construction CGCA38309 ltC; Monroe COunty Facilities D~velopment AUG 09 2006 TIME: RECEIVED BY: , ~\/ August 8, 2006 0417 -02183 Attn: Clark Briggs, Senior Project Manager Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Fax: (305) 295-4321 Re: Freeman Justice Center (FJC) Subject: COR #49 - Change CHW to 3-Way Control Valve Dear Mr. Briggs: Please find enclosed Change Order Request #49 for the additional work to change the 2-way control valves, shown on the Contract Drawings for the chilled water system at each of the six air handling units, to 3-way control valves with bypass branch connections. The total cost for this extra work is $8,317.40. This change was initiated by RFI #214, which identified that the chilled water piping system had been erroneously designed with 2-way control valves and constant volume pumps. The Engineer's response to RFI #214 corrected this error by changing the 2-way control valves to 3-way control valves. A detailed breakdown for the costs of the labor, material and equipment associated with this change is attached. This change does not affect the critical path of the project. Please process a Change Order in the amount of $8,317.40 as soon as possible. Sincerely, (/}/.';! c-/f)lJ!t~ John Chandler Project Manager Encl. COR #49 (6 pages) '-.- i" ~ '1'- ~ I I ,_,/:;. t /.... I, I . I L_! .jillj I I [J~( I I l(~~. 0 O (, J 0 _ oLLrl~~; ~~=-~'-" cc: TTG/MO (COR-49). FF (COR-49) CSNH.Goldman (Fax: 561-243-8184) 405 S.'!v. 148t1iil,venue ' SUite One. Davie. ~Ionda 33325 . Tel 954; 476.3200 . Fax 954. 474' 3111 7601 SIN Lost RiVer Road' Stuart. Flonda 34497' Tel. 772 '287"7525" Fax. 772'287.7524 9440 Philips Highway. SUlie#5 0 Jacksonville. Florida 32256 . Tel. 904' 292" 18 11 ' Fax 904" 292 > 4865 The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 CHANGE ORDER REQUEST No. 00049 Phone: (954) 476-3200 Fax: (954)474-3111 .=:;:::::"-======---- TITLE: Change CHW to 3-Way Control Valve DATE: 8/8/2006 JOB: 0417 CONTRACT NO: 1 PROJECT: Freeman Justice Center (FJC) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 RE:RFI To:CSA DESCRIPTION OF PROPOSAL From: TTG Number: 00214 Change Order Request (COR) #49 proposes to furnish and install 3-way control valves and bypass branch, in lieu of 2-way control valves shown on the Contract Documents, for the chilled water piping at all six Air Handling Units. This change corrects HV AC design error in accordance with the Engineer's response to RFI #214. Please process a Change Order to increase the Contract Price $8,317.40 for this extra work. There is no change to the Contract Time as this change does not affect the critical path of the project. Item 00001 00002 Description ESSI Change less sales tax Weathertrol Change less sales tax Stock# Quantity Units 1.000 LS 1.000 LS Unit Price $721.60 $6,974.02 Tax Rate Tax Amount Net Amount 0.00% $0.00 $721.60 v 0.00% $0.00 $6,974.02 ./ Unit Cost: $7,695.62 Unit Tax: $0.00 Unit Total: $7,695.62 Subtotal: $7,695.62 ./ Description Sales Tax Profit Markup Percent Markup Amount $237.00 / 5.000% $384.78 J Total Cost: $8.317.40/ Electronic Systems Southeast, LLC PROPOSED CHANGE ORDER No. ESSOO 1 2263 Boca Raton Blvd., Suite 2 10 Boca Raton, FL 3343 I Phone: (561) 955-9006 Fax: (561) 955-9007 TITLE: Change to 3-Way Control Valve PROJECT: Freeman Justice Center (FJC) TO: Attn: John Chandler The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 DATE: 8/8/2006 JOB: 0417 CONTRACT NO: 0417-035 RE:COR To: MCCM From: TTG Number: 00049 DESCRIPTION OF PROPOSAL Per the Engineers request to provide 3 way CHW Valves, ESSI respectfully requests a change order for the difference in cost between the 2 way & 3 way valves. BeIimo 2 way CHW valves: 2 Model B238NM24-SR $488.00 4 Model B248NM24-SR $1184.00 Total $1672.00 BeIimo 3 way CHW valves: 2 Model B33 IARB24-SR 4 Model B349ARB24-SR $652.00 $ I 676.00 Total $2328.00 The difference in cost between 2 and 3 way valves is $656.00 Plus 10% profit & 10% overhead Request for Change order is $794.00 A quick response would be greatly appreciated; the valves have already been shipped to the site. (Contract only allows 5% profit & 5% overhead). Item 00001 Description Difference in cost between 2 & 3 way valves Stock# Quantity Units 1.000 LS Unit Price $656.00 Tax Rate Tax Amount Net Amount 0.00% $0.00 $656.00 / j{ / :~ Unit Cost: Unit Tax: Unit Total: Subtotal: $656.00 $0.00 $656.00 $656.00 Description Overhead Profit Sales Tax Markup Percent Markup Amount 5.000% $32.80 5.000% $32.80 7.500% $49.20 Total Cost: $770.80 Aug 07 06 03:46p Anthony Burke \.1'-" ....., ~U'(JU ..l.y.....u ~O...::I-'.J='tJtJl 305-296-2587 p.2 t~~l tA~1 PAGE Bl/el I ';1 l7l1ctrrmlc ~~IJI$ $'g~lf8t...H;f, Z'Z'~~ (foea Raro~ Soulrv;,rtJ. sult~ Z'IO (fOC1 ft~n. nOrl~<1 :T3"~ ! E551 August 7,2006 The Tower-Group, Inc. 405 SW l48th Avenu~, Suite #1 Davie, FI33325 Att.n: John Ch.and]er Fax #: 305-296..2587 Re: Freeman Justice Center RFCO #1 CHW Valve BeIimo 2-way CHW valves Qnty. Req. Model # 2 B238 NM24-SR 4 8248 NM24-SR ! I j I I I t As per the Engineers request to provide 3-way CHW Valves, ESSl respectfully JqUll:st a change order for the difference in cost between the 2-way and 3-way valves. i I I i Total! ;lt~~ $167~ I I , I ! Total I $ 652: llilQl $2328 Dear John: ESSJ's Cost $244 each $296 each Belimo 3-way CHW" valves Qnty. Req. Model # 2 B331 ARB24-SR 4. B349 ARB24- SR ESSl's Cost S326 each $419 each I The difference in cost between 2-way and the 3-way valves is $656 Plus .LO% pro,frt and JO%" overhead -'5',<, <] !";7f f~ I ~ /J,," The request for change order is ~ 77{;, Cc' . - I I A quick response would be greatly appreciated; the valves bave already been shipped to the site. If I can be of any further assistane<: please do not hesitate to call me. ~ Boca Raton; ra77) 9SS 9006" Fax, (56'1.) 955 9007 OR/07 I :2OOfl MflN 1 S: 4:\ fTX IRX NO 7:1Rfl1 ~ on:! Weathertrol Maintenance Corporation 7250 NE 4th Ave. Miami, FL 33138 Phone: 305-908- I 000 Fax: 305-908- 1039 PROPOSED CHANGE ORDER No. WT009 4 TITLE:Change to 3-Way Control Valve PROJECT: Freeman Justice Center (FJC) TO: Attn: John Chandler The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 DATE: 8/812006 JOB: 0417 CONTRACT NO: 0417-004 RE: COR To: MCCM From: TTG Number: 00049 DESCRIPTION OF PROPOSAL Additional work to furnish and install bypass branch for the change from 2-way control valve to 3-way control valve, based on response to Project RFI #2 14. Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount >' 0000] Material by Weathertrol ] .000 LS $2,504.02 0.00% $0.00 $2,504.02//' 00002 Labor by Weathertrol ] .000 LS $3.3] 1.00 0.00% $0.00 $3,311.00 ~ 00003 Insulation Subcontractor ].000 LS $550.00 0.00% $0.00 $550.00 Unit Cost: $6,365.02 Unit Tax: $0.00 Unit Total: $6,365.02 , ----- ~ Subtotal: $6,365.02 Description 5% aIR on Items 1 & 2 Profit 7.5% Sales Tax on Mat'ls Markup Percent Markup Amount $290.75 5.000% $318.25 v $187.80 _/ Total Cost: $7,161.82 ~/ By: By: Hector Ruiz John Chandler Date: Date: ExpedItIon 1...'9 Aug 08 06 03:21 p Anthony Burke i'lV\l. 0, LV'JO ':'forM 305-296-2587 NO. 752 p.1 P. I IJr weq:t~~~f~91 ~ CHANGE ORDER REQUEST Change Oreler Request#: 04..790.0017 Date: 61712008 PraJle!: Freiman Juatice Center. To: The Tower Group @ Freeman Justioe Center Attn: John Chandler 600 Whitehead St. Key West. F1. 33040 Project #: 04N79C From: Weathertrol Hector J, Ruiz 500 Whitehead Straet Key West, FL 33040 Ph.: (305) 296-2521 Fax: (305) 29e..268r . Ph.: (305) 908-1000 F~: (305) 908-1039 We hereby propose to make the followIng ohanges: Change tile two way control valve to three way contral valve Change Ordef Price Original Contract Amount J~ur $1,269,365.00 Tnls pci.:; Is good for 0 days. If oondltlons change, this price Is void. We are requesting a time e)(tension or 0 aay& In conjunction with Ihls ohange, Hector J, Ruiz 81712006 Author Date The Tower Group, Inc. o Accepted Th& above prlC&i and apecilicatlons of this Change Order request Bre iatlsfaotory and are I":ereby llcoepted, All work to be perrormed under same terms and conditions as specified in or/glnal contract ur.less otherwise specified. Authorized Signature Date of Acc~ptance -:: I'l. n j n () I"" n .n,-. ..,..,T r~ -1 1"'" . ... () r rn V I n v ~ 1 f\ "'T r- 0 0 1 r::n (\ " -t Aug 08 06 03:21 p M\)\]. 0, i VIJO Anthony Burke I :'1trM 305-296-2587 NO. 752 p.2 P. 2 !/9J CHANGE ORDeR REQUEST SUMMARY Project: Freeman Justice Cel1ter COR tt. 04-790.0017 Labor I uborType Pipefiller -Welder Help~r MH,.. J IJHr Surden [ Jlrlng. Tax Total :u 565.00 $0.00 10.CO SO.OO 51,430.00 1B $58.00 SO,OO 10.00 $0.00 $1.0-44.00 18 S4MO SO.OO 50.00 $0. D<I $837.00 '-- SubtolaJ $3,311.00 Quantity Card Tax Tml 9 $31.50 $19.85 1303.35 9 too 50 141.90 'Si40.40- e $7&.50 nU7 5GCUr 20 ....81 $6.73 "02.93 e 5128.00 153.713 1821.76 6 $20.50 USi S131.81 SIIb1atlll $2.504.02 " Material IlIIe ~r1.1 Oi.e1ectric IInlonl Olule<;trIo flanges Reduclny iees Bile Stl pipe PIU~\I~ Wela neck 'lsnge. Subcontracts rUbcontractor Insulation O.-crJptJon .Extra insUlatlon lor ~u connection Subtotal TotI. 3550.00 "60.00 $5,815,02 .~ $i72:2B'"~ S' ~7;; _.$66&;~ <; '/e'> - -.t55e:oo-- 9K C;t;C.f i7V .-W.Sft.-. trk 1 ,. <;""J /$-19;3:r .-~ ~ .$8,012:"83'-" Tota/Coat Overhead Pro fit Subcontract MarKup Subcontract Bond .1ot€ ~l /E4 f.'t;/' If';.," t,.I 'q ~. . L;;..L/ #> ~/[I e2 ~~ ~" ....~~.... .................. 4_ ~r-. .............~,-.--..-.~ -"'-"-" __.r-,..,-. r"'1-.....,.,-. The'rrower Group, II 405 SW 148 Avenue . Suite One Davie, FL 33325 "l-fANGE UKUEH ~(JlJ~~l No. 00050 Phone: (954) 476-3200 Fax: (954) 474-3111 TITLE: Room #3047 Artwork Lighting DATE: 8/9/2006 = PROJECT: Freeman Justice Center (F JC) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 JOB: 0417 c Monroe County Facilities Development CONTRACT NO: 1 AUG 22 2006 f1ME:_________ RECEIVED BY:__ _ RE:LTR To:TTG DESCRIPTION OF PROPOSAL From: CSA Number: 06-07-20 Change Order Request (COR) #50 addresses the cost to furnish and install additional lighting for the artwork being furnished under separate contract for Room #3047. This change was requested by CSA Architects, on behalf of the Owner, via the enslosed fax memo (3 pages). TTG proposes to furnish and install two (2)Omega Model #OM4-75MR16L V-RADJ-CS-EBfixtures, or two (2) Portfolio Model #H7493T/DT-9473 fiitures for a Contract Price Increase of$515.87 and no change to the Contract Tirrie. t Please fornarda Change Or'deras acceptance of this proposal and indicate the-deSire? fixture and lamps. Item 00001 Description Labor. Material & Equipment byTTG Stock# QuantityUoits 1000 LS Unit Price $447.46 Tax Rate Tax Amount Net Amount i 0.00% $0.00 $447.46 (I: Unit Cost: Unit Tax: Unit Total: Subtotal: $447.46 $0.00 $447.46 $447.46 Description Overhead .' Profit Sales Tax on Mat'ls ,t'1arkup Percent Markup Amount .//5.000% r"". ~,$2137 5.000% -'-S $22.37 $23.67 Total Cost: $515.87 r / ) ~ I f ~"-'--'-~-~,,-~.~.~-.- ~ "S-u 0::: 0 0 0 <0 ..- OJ M ci <t ..J ..J <t .... 0 .... !:: Z W::E :::> 0::: 0 0 0 - OJ <<! 0 0 :5 ..... ..... ~~:g crOI/) W.....~ ..J....M <t<t* ~:E O:::..J ....<t 0.... We uj.... .... zuJ:E :::>'" " w g:g (,J. . -1/)1/) 0:::1/)1/) . j~'~'~ , ~ .,~,' i,US, c t: Q) CI) E:O ' w an ,(ll " 0::: :E to;- to) :::> W v to) ~ !:: E E ii: ON <t ~N C) Q)..... W E ::e 0 e OO..-<or--M r--..-COI/)<O..... Mll'itcill'iM"": COV.....Nr-- ~~M*~ ~ * , " , , , ' ~ ~.;, -.~ : J t',":; :~'-: \ ; " ~[, ,) 'I i" '0 ) j , '. " .. ;"' ~'.. ,,' ~,. .l ", ~ "l ; ,': ; :.. !:: zwtz :::> , ' , >- I-NO o ..... '~:AtJ 03N3;)3~ ~'~._--~-~~-"-~~~::i'^'1l geaz GG sn\1 lueWdo/ef,aa S€lUII/Oi:)~ ^wno:) eOJUOVV ' stJ ~~ ~~ CURRIE - SOWARDS - AGUILA - ARCHITECTS Archl~ct~. Planners & Interior De51gnere - AA 0002271 134 NE 1--=, Avenue. Delray Beach, Florida 33444 Monroe County Phone (561) 276-4951 Fax (561) 243-8184 e-mail r~cp@curWcfR'pc~carW~lopment AllG 22 2001) FACSIMILE ~hYl, Company: TT~.- From: 1!(~wJ!~;~::~---- To: Fax No.: 305 .1..9~.;2.?87 Rs: Job No. Date: 11 of F'~eee - rl"lcludl"i3 thf5cov~r ./"> ,-' .3 COMMENTS: -" .( 7X~~e-.~~I~: ~re - . ,. -}l~),r'/" Tt" a 'Z I~e I{ .s -, _ :,.. /%q~ '~'. ~)G!i:'.U ~ ">';' .' 4JJh~, 4r~~:rt;Art_ > ".;'l>. _,," __'_"" _, _' i" f.u;/,/;;,~~ -<.br~';: :~," ~:. -', " , . I~ ,KJ r~~'e - ~If . Ii; c;. :-(l'd1t~~ , /, - /. -~. .. ..,Ii-'.'" :....I-_~.-/....-.._..._';~~ ~.. ':.~, .-,." . :.. Copy: ------~ 1. I d7'~ NO$$ PM.1tJlfJ Od1Ww~ (JJ1<11l'.~VL~ f<W(~)~.r~ (3'\l)01ttfBJ<ttl.:~. (4\ , '~~ ,~J r ~~~'<n~. b ~ :, - ~;,!;,;~.:tg~i,!',:..:< ~ ~-H'b I r 5 (2" , J '( i::\ __--------- cJl 0, ,..... s=, "" - ." , ", c,. ..... )<-,--"-,,, '. ,"7", ,.,.~ = ]Q ,.,.,.J':~'-"'-i";"j,;;f, 'r"-"" '. , .' 0 .L. r ....-.. B r ... ",_" :', " ',"'''''' r \' o ,~FO .. ~ ~ M",;.~ j")1J - ..,;f., ) " '. ' , "~ " " f-q .'" " ','~~ '~. _'J' ~ mo' - ~:..-H-!.~t" .. ' <':~ - -0. -"0 ~- ., ~1 .....: I'",'" :'~ ... ~,_,,~ :3'-" ..~ .. j , ~ , ...... . ,,~ ~ , Ir.~ 'Cj l 't. ',' <C~~ , , t:1 ". 1/ :', .,........1/, .' . .' . I , t' T . <D ... ------ ...- - r . 0 -Q r D '. ) r ~ ~ 21)'-" r- 0 0 ~ - I I B e ^ , I ':-::,,":"i, .! i':",;""': 7<+ :;::;~;~. , .' '".; .' l "'.".... ,:h:'i~ f. 1 J. \l' -:c i' '.," '-~ D B -(f). ( I I ~ .., v .... .... '01 ~ m - - - - - - - - - - f ~ - - - - -~- -- . r 1 e -.. .. I \0 ,'-I -'." :;;~';","",',\."i":';' 1\ ,I '4' -'. ...;,. . i ~ - ..... .. r ..... :~ Is~: ,7, c1 ,.,1. '." ,;.,. r- I III \ I I G \ 11'\ I I , J.t-. f'" I f : G 1- -:c : .;';;" .' 'I' '''' r-tl;:-'",.> J. ~ , ro o o Q~5; '1 ~. -u.lJ ~ '0' /l . . r . '0 ,.' -' - .' -~'/-"'.: , " , -:c.. J. T 1 ..' B o ~ I g 0 r ,., 14' .. 1 - r c~ro 0 B ^ .... 0 0 r ) I, "'"""'- . 4 o -c il' -J"i A-- -.;;; -<) .. kl S1) T ;1" . <-." J' -,~ ._._<', :_ '..I ,,, ,'C; .'" l' ,'>: .,~' {,' "1;-'; .,.' , '.' ,.:.: J!L, ;.' r\-/ . ~ .<::#~." --'._' '," . t: ~'-'_ ",S .;..~"9P1I f':mf "~i.~;~,'~~;,',;AU~:a:~'~M' ' }:,:~f " ;~;~\;;.iN~:,::~'~(;~;:~ii2);/'.' ',,, :~.~'lic\i ;w;i~i~~i;{(~;,:;~;.,:; t ,',..o;,.,~."~,,.,..,t,;>~~;' l~>~1t'i\ ~ ~ ,', r ;:,,~,',. ,';<~ ~7~rf~1t~~;f}~,,~,S'~~f~~~i: " -,- ? ,.", ,.... T.J,:,'"l;; " " ., ..,'\j ':;";"'\" ~ -:Co , 'r : C!] ," ,...! -': ,,\.-:1 . '.~l _>:: ./. . "..,..",:.,~,,: ", ."" :,' ",...,,-- ........ ~~,; : .. - l- o -0 G 0. - >- ,-- ....J - I..- -- -~ t_;= CJ -~ c -- - o L-. \6'-.- o -0 B -c r-o o I~I~I~I~\T'S QUOTATION .!::T) 1850 N.E.146 Stttet . Miami, F~rila 33181 USA Cupllrate Oftke: (305) 947-5451 - FAX (3OS) 940-34!AJ www.flrreysnm . E-Mail: &ITeys@fate.u.et Date: 07121100 Qltote: Pnject: FREEDMA1'i IUSTICE CENTER Pa&e: 1 Presented 111: TIlE TOWER GROUP ATTN: JOSE CLAUSELL Monroe County Prices quted: F.OB. Miami Facilities Development Prices valid Jilr: 90DAYS Lead time: 60DAYS AUG 22 2006 (&sOd on ~ility Of of <b~ dol.) Tenns: Prices Cl.uoleda~ based ~~_. Iisled. Anychattges >MIl ~fi5~cfx,r:r -- Otder will be processed u?m recaipt of (1) Signed approved quotation;. qoan1i tie s Qulltatlon Sllllmitted II y: l\ob.lIJlJ MaceiIas Direct Line: (305) 919.Q 151 Celll1ar(305) 812 -1313 (2) Pu:chaSll Orde r cottfllIl1inlt. .. ~~II'( ...r~. .. CAr&. oc l'lVMBER.um II!SCBIPl'ION UNIt Pm CE IOULPmCE ~ , . ~ ; PJdEGA. OM4-1~16LV-RADJ.CS-!:Il $155.00 $31000 , ~ .i .~ i .i t .. t .- l , !ALL LAMPS INCL UDED UB1DTAL COMPUTE QUOTE MUSTBE USED,NOPARTIALS AX iALL QUOTATIONSARE SUBJECT TO APPROVAL. TOTAL f :.. :.. TYPE: DESCRIPTION A low brightness 4 liZ' aperture low voltagel1ine voltage adjustable accent fixture for a wide variety of lamp types. Optics allow the lamp axis to pivot about the center of the aperture at the ceiling line, allowing maximum fight output with no flashback. ZOo truncated cone allows full range and flexibility of aiming. SPECIFICATION FEATURES A...Reflector Spun 0.040' aluminum. Available in low iridescent clear, haze, straw, wheat and specular black Alzak~ finishes. Torsion springs pull trim tight to ceiling. Trim is keyed to prevent improper orientation in housing. B...Trim Ring White painted die cast trim ring or self flanged reflector. 'ALOG#: p@ SPECIFICATION FEATURES C...Aiming Mechani,sm Stable lamp aiming and locking mechanism. allows smooth 3580 rotation and 350 elevation adjustment. Lamp aiming scale enables consistent setting across multiple fixtures. D...Sock'at Adapters Keyed quick connect plug allows interchangeable lamp types. Easy 'installation via single spring clip. E...Houslng "One'piecedle cast l' deep collar. Housing is paint'ed optical matte . black to eliminate stray light. F...Unlvarsal Mounting Bracket Accepts l/Z" EMT, C Channel, T bar fasteners and hanger bars.. Provides 5' total adjustment. ~G ..J unction Box . 'Listed for eight #lZg (four in, four ,out) 900 C conductors feed through branch wiring. Six liZ' pry outs and 4 integral Romex traps. Access to junction box through panel in side of housing. H...Transformer lZV dual tap lZ0IZ77V magnetic transformer mounted to ensure quiet operation. Transformer can be bypassed with SA99 socket adapter for line voltage lamps. H749430T has dual output lZ/5.5V taps (for 5.5V PAR36 lamps) as well as 1 ZO/277V input transformer. In s ul a tionDe te c tor Self,resetting insulation detector opens circuit if insulation is improperly Installed. 5tJ PORTFOLIO H7493T 9473 H7493DT 9473 Mom e County Facllltles evelolS'l'5l1lV Labels U.L. listed, C.S.A. certified. damAUG location, ISEW union made. T1ME:__. RECEIVED BY:_ ..==' ~ ~ ~: I "" "" . ,_ ~m~J""~~' h ~ . .~~ ~~ /Ill-'::';~'fll ,." ",. Top View . ]zmml L 13 112" j 1343mml E.......... D B.. S,A96 SA99 Lamps nOt included ORDERING INFORMATION: Complete unit consi.ts or housing. ballast and trim. Socket Adapter H7493T=>4" Low Voltage Directional with 120/277V Input Transformer H7493TCP.4' Low Voltage Directional with 120/277V Input Transformer,Chicago Plenum H7 4930T - 40 Low V oltage Direc~onal with 120,277V Input Transformer and Dual Output of lZV and S.SV H74930TCP-4" Low Voltage Directional with 120/277V Input Traflsformer and Quat Output of 12'1 and 5.5V. Chicago Plenum COOPER LIGHTING Trims Finish Options 2 2006 to 75W MAX M R 1 6 75W MAX A R7 0 AR111 PAR36 PAR20 PA.R30 ~ 4 1/2" ADJUSTABLE NorEs: Accessories should be ordered separat~ly. For additional options please consult your COOper Lighting Representative. Aluk is a registered trademark of Aluminum Company of America. Ace e 5 S 0 ri e $ SA91 "",MRIS 7SW Max H277 -=>;-Step Down Transformer. SA93 = AA 70 SOW Max 300 V A Max SA94=AA111 7SW Max HSZ6 -C Channel Sar Hanger. SA96 = PAA36 SOW Max IZ60 Long. Pair SA99:: Converts to 120V, H850:= C Channel .Bar Haflger, PAAZO/PAA30 7SW Max 50' Long. Pa" RM822:;r. Wood JOIst Bar Hanger. 22" long, Pair FK5 % Field Installed Fuse Kit. 5 Amp LZOO SERIES = Optical Lenses for PAR Lamps, use witJ'1 LC30 Lens Clip I LC30 = Lens Holder for PAIl30 I Lamps and L200 Sefles Lens AiJV985 JOO DR37 c DeRated Wattage Label 37W DRSO 2 DeRated Wattage Label, SOW I I WF:=; White Pain red Flange ISelf Flanged 1 onlyt 9471 :os Reflector, Self Flanged 9473 c Reffector. Metal Trim Ring, White 1I = Low Iridescent Clear H:lfHaze S ~ Straw WH: Wheat WMH;:r:Warm Haze S = Slack W::II:White BS = Slack Saffle 194730nlyI WB = W'hite Baffle 19473 only} PHOTOMETRies Fixture Performance Data Lamp Beem Spread SOW PAR3S VNSP 8.5" x 8.5" Lamp Bum Sproad 3SW ARll1/3ISS 3",. 3" Lamp !leam Spr.ad 07SW MR181 NSP 14".14" Lamp 075W MR1S FL !learn Spread 420 .. 420 Lamp AR701 SISP Beam Spread 100 x 100 ~-- 0 FC L W 00 Tift Horizonral Illuminance S 5'0" 452 7"6" 201 10'0" 113 12'6" 72 1.0 1.5 2.0 2.5 1.0 2.0 2.5 3.0 1'6" 1'0" 2'0' 2'5" o FC L W 0" T~t Homontalllluminanc. 10'0' 500 1.5 1.5 12'6' 320 2.0 2.0 15'0' 222 2,0 2.0 17'6" 163 2.5 2.5 5 l'S" 1'6" 2'0" 2'6' o FC L W 0" rut Hotllontalllluminanca 5'0" 582 1.5 1,5 7'5" 259 2,0 2.0 ' 10'0" 148 3.0 3.0 12'5' 93 3.5 3.5 5 l'S" 2'0' 2'5" 3'0" o FC L W 0" Tilt Horlzontallllumlnanco 5'0' 95 5.0 5.0. 7'6" 42 7.5 7.5 10'0" 24 9.0 9.0 12'5' 15 .11.5 11.5' s 4'0' S'S' 7'S' 9'8" o FC L W 0" Tilt Horilontalllluminanc. 5'0" SOO 1.5 1.5 7"6' 267 2.0 2.0 10'0" 150 2.0 2.0 12'6" 96 3.5 3,5 5 1'6" 2'0" 2'0" 3'5" 0 FC L W 5 lamp Beam Spr.ad 00 Tit Horizont~ lUumin'ance AR70lSOFL 300 x, JOO 5'0' 164 2.5 2,5 2"6" 7'6" 35 3.0 3.0 3'0" 10'0" 20 5.0 5.0 5'0" 12'6" 13 6.5 6.5 6'0' 0 FC W S Lamp Beam Spr.ad 00 T1It Horizontal lfkJmH1aoce 3SAR111/3/SP 100 x 100 5'0" 560 1.0 1.0 1'0" 7"S' 249 1.5 1.5 1'5" 10'0" 140 2.0 2.0 2'0" 12'S" 90 30 3.0 2'6" 0 FC W S Lamp Beam Spr.ad 00 Tilt Horizontal Illuminance 75ARlll/10lSP 100 .Il 100 5'0' 1143 1.0 1.0 I'D" 7'S" 508 1.5 1.5 I'S" 10'0" 26S 2.0 2.0 2'0" 12'S' 183 30 3.0 2'S" ,,- COOPER Lighting S7J H7493T 9473 H7493DT 9413 Monr',' ',;'UI1'Iy' FQClliil1!o f - ;-')Ot")('-"on'!' I , N.........'.} nM!:,: 0 FC L W S 0 't;;S!VED ~Y:~'W-<""S ._, -. ------ 30" rut Horilontal'IIuminanca 30" r~t Venicallnumiflanca 5'0" 288 1.5 1.5 1'0" 2'0" 33S 2.0 1.0 1'0" 7"6" 128 2.0 2.0 2'0" 3'0' 150 3.0 2.0 2'0" 10'0' 72 2.5 2.5 2'S" 4'0" 84 5.0 2.0 2'0" 12'S" 45 3,5 3.5 3'0" 5'0" 54 S.O 3.0 3'0' 0 FC L W S 0 FC l W S 300 Tdt Horrzonta' lUuminance 30" T~t Verticallluminanca 10'0' 318 2.0 1.5 1'5" 5'0" 249 2.5 1.5 1'0" 12'6" 204 2.5 2.0 2'0' 7"S" 111 4,0 2.0 2'0" 15'0' 141 3.0 2.5 2'0' 10'0' 62 5.0 3,0 2'6" 17"6" 104 3.5 3.0 2"6" 12'6" 20 9.0 5.0 4'0" 0 FC L W S 0 FC L W S 300 rilt Horn:ontal lIIumiMnce 30" Tilt Verticallluminanc. 5'0' 397 1.5 1.5 1'5" 2'0" 513 2,0 1.0 1'0" 7'S' 177 2,5 2.5 2'8" 3'0" 255 3.0 2,0 2'0" 10'0" 99 3.5 3.5 3'0" 4'0' 143 5,0 2.0 2'0" 12'S" S4 4.0 4.0 3'S" 5'0' 92 S.O 3,0 3'0' 0 FC l W S 0 FC l W S JO" Tdt Horltontalllumllvnca 30' TIlt Verticalllumlnanc. f 5'0" 12 5.0 4.0 4'0" 2'0" lS1 3.0 2.0 2'0' 7"S" n 7.5 6.5 S'O" 3'0" 72 5.0 3.0 3'0' 10'0" IS 10.5 8.5 8'0' 4'0" 40 7.0 4.0 4'0" 12'S" 11 12.5 10.5 10'0" 5'0" 2S 10,0 5.0 5'0' 0 Fe L w S 0 FC L W S 300 Tilt Horizontal muminance JO" TIlt VertlcallHuminanca 5'0" 404 1.5 1.0 1'0" 2'0" 625 2.0 1.0 1'0' 7"S' ISO 2.5 1,5 1"S" 3'0" 27S 3,0 1.0 1'0" 10'0" 101 3.5 1.5 ,.S" 4'0' 155 4,0 1.0 1'0' 12'6" SS 4.0 2.0 2'0' 5'0" 100 5.0 2,0 2'0" 0 FC L W S 0 FC L W $ 300 Tift Horizontal Ufumittance 30" nt VartlcalluUminanc. 5'0" SO 2.0 2.0 2'0" Z'O' 133 3.0 1.0 1'0" 7'S" 27 5,0 5,0 5'0" 3'0' 59 4.0 1.0 1'0" 10'0" 15 S.S S.S S'S" 4'0" 33 S,O 2,0 2'0" 12'S" 10 a,s S.S a'O" 5'0" 21 7,0 2,0 2'0" 0 FC L W S 0 FC W S 300 rtlt Horizontat IlIummnce 30" TIlt Vertjcalllluminance 5'0" 357 1.5 1,5 l'S" 2'0" 435 2,0 1,0 1'0' 7"S' 159 2.5 2.0 2'0" 3'0" 193 . 2.5 1.5 1'0" 10'0' S9 3.0 2.5 2'S' 4'0" 109 :.. 3.5 2.0 l'S" lZ'S" 57 4,0 3.5 3'0' 5'0" 70 4,5 2.5 2'0' 0 FC L W S 0 FC W $ 30" Ttlt HorizontallUuminance 30" Tilt Vertical Illuminance 5'0' 731 1.5 1.5 1'0" 2'0" S92 2.0 1.0 1'0" 7'S' 325 Z.5 2,5 2'0" 3'0' 39S 2,5 1.5 1'0" 10'0" 1 a3 3.0 3.0 2'6' 4'0" 223 3,5 20 l'S' MOf}r~ ~Unty4.0 4,0 3'0" 5'0' 143 4.5 2.5 2'0" ~rl(;IIIt1es DEl'lelOpmeni Notes: n~J1b: -Illuminance values are cosine corrected initial values ",:,rth no cant~pg~I('19!'f1)jrmr;~e!I~-.,cti~~~o~~~?_T,,-~!!;~'!QQnJ,...~--o-__ !urfaces. Total illumination may increase from contnbutlons from oth~'s1irla'as,' -" . Changing fixture spaCing will aHect illuminance level. . f1fuminance in footcandles. Lux conversion tactor: 1 Fe = 10.76 LUX U,(\ n (". '200!:: l~ 1:1 ;(. 2:, _ IJ 00 ~ Oi$tanc. trown : From C*'ng : _..l---~_______ Distance AhJog W&H Nor. S~ecifications ~nd Olmensiol"l3 iublect to Ch"nge w;r1"<lvt notico_ Visit our website at www.cooperlightiog.com Customer First Center 1121 Highway 70t South Peachtree City, GA 30269 770 48S,4800 FAX 770468.4801 ADV985100 Coope, lighting 5925 Mclaughlin Rd. Mississauga, Ontario, Canada L5R 188 905.5074000 FAX 905,568 7049 (4.' ~g U~ ut> lUAja Anthony Burke 305-296-2587 p.2 CHANGE ORDER REQUEST No. 00051 - fhe Tow'er Group, Inc. .)5 sw 148 Avenue ~.. uite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-311 1 TITLE: 2nd & 3rd Floor Lobby Ltg. Changes DATE: 8/912006 PROJECT: Freeman Justice Center (FIe) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 JOB: 0417 Monroe County CONTRA.cf~'2)~ DeveloP1ent AIIG 09 2006 TIME: ~~~"-'-".---. .~. . RECEIVED BY:_'~'~----J~<f'I..-_. RE: RFP To: DESCRIPTION OF PROPOSAL From: Number: 06-05-18 Change Order Request (COR) #51 addresses the cost for the changes to the 2nd & 3rd floor lobby lighting based on the attached lighting specifications sheets (2 pages) and two unnumbered 24x36 drawings signed "Approved" by Holly Elomina, and dated 5/18/06. These specification sheets and unnumbered drawings were subsequently incorporated into Drawing #ID-8, dated 7/21/06, delivered to TTG by Monroe County on July 25, 2006, TTG proposes [0 Furnish and install the changed lighting for a Contract Price Increase 0[$20,429.91 and no change to the Contract Time. Please forward a Change Order as acceptance of this proposaL Item 00001 Description LabaT, Material & Equi"mc:nt by TTG (See atta:hed breakdown, 1 page) Stock# Quantity Units 1.000 LS Unit Price -s~ / &9-/;-' 9~ Tax Rate Tax Amount Net Amount 0.00010 SO.OO .-$.J7,54H3.//- , I &J'1./:)J ~ Unit Cost: 1~91S:-1).W,545.93 Unit Tax::.. .$0.00 Unit Total: $17,545")3 ~ Subtotal: J{.,..>7'~.9J.$~4~.93 Description Markup Percent 'Markup Amount Overhead ,,,,>'''';!)' i'~) (,9 ~ ,_ 5.000% 7 ~3 J" $'8-71.30 /SU;3Y!> ~DJ . Profit " 5.000% /)~:5)'- S877.3D Sales Tax on Mat'ls 9"'/1 ,~t $+;+i9.38 Total Cost: $20,429.91 J 9 {)y-/I ;] ,---- ~ , f ,j -I ~ ~j ~\ I ! a: 00 0 ~o It) CO '<tCO 0 co 07 ~I~ :1 ..... C!~ N ~O Nit) 07CJ) 0 I"-CO I 0 0(:) an cON &rio ll'i~ 0 c:ri-.i ~i~ a::J ..... N ..- coo <t co ...J ..... W!L ...J iA- <( I t- O t- < !:: 0 ...J ~ C/) 0 ~ ~ <( Z W W W W W C,) U 0 ~ C:::M I- ::l IN I/') I- 0 iA- I- a:: ..J 0 (:) (:) (:) It) 0 It) 0 0 0 0 51@) I@) j C! ~ CC! C! C! q ..- (:) q 0 (:) N N N 0 ... CO') M .,... 0 '" \. "- ~ .,... I- \ " ...J J , ~ 6 \ r::;- C::: Z (:) (:) 0 0 ..... '<t co e <t 0 0 ~ C! ~ "": ~ .,... e j M 0 UJ ex an ci l"- e ..... CD N ..,f 0 { ~ CO 0 W N .,. N ~ .,. N It) .,... e \~ oCt 0:: cl ~ (:)~ ~ W .,. .. It'J ~) ...J :J N (:) ..... \} ~ In 0 :!!: if:jI) .,... ~ 'J.] i2 W '\ j I- ...J -... 0 ~ ---. W 0 ~ ...J --.; W I- 0<....... !:: ~ tp Z W W LlJ W 0 () 0 w ::l (:) 0 0 0 CD co (:) 0 v e W It) q ~ C! It) "! ~ ": ~ C! 0 ,...: 0 I"- 0 lri co II) ('II CI) e i2 r) .. ~ W It) M ~ en I"- 0 r) ":. It) ~ ..... N iI'fo lit D.. ~ ..... .. .. ~ ..... ~ .. W C> l- . (J) W W W UJ -' z rn e::: w 0:: e::: e::: 0:: CD (J) ii: w 0 I- , 0:: ;:) :J ::l ::l oCt cr X Cl. J: ;:) :e ~ l- I- t 0 w a:: 0 Cl. CI ~ w X (.) 0 :e w IXI :J jjj !:: u: u:: u: ii: :E :e I- 0 VJ a:: . . .. i!: III [Q ~ < c (/) (:) X u. c( ~ c:( CJ) 0 0 0 ..J ..... 0 0 N a.. CD .,... oiS CD 0 l- . Z I.lJ W W W W W LlJ UJ WW ::l ~ (:) Il)CO co ~..... CD ~ en en (:) CJ N ..... ..- Sd L8SC':-96Z:-S0S 8)jJn8 IiUOl.jlU\j C'>> >.... 01 ~ -..,' t'-=' .5'1 8SV:0 ~ 90 60 Bn\j M;.JY U";;:J UU Iu._a Amnony tsurKe 305-296-2587 p.4 ~)u~I~E'~'S c;-/ QUOTATION 1850 N.E. 146 Street - Miami, Florida 33181 USA Corporate OffICe: (305) 947-5451 - FAX (305) 940-3450 www.farreys.com - E-Mail: farreyS@gate.net Date: QUOte: Project: Page: 06/22/06 ADDED TYPES FREEDMAK JUSTICE CENTER 1 Quotation submitted by: Manny Maceiras Direct Line: (305) 919-0l51 Cellular: (305) 812-1313 Presented to: TO\VER GROUP ATTN: JOSE CLAUSELL Prices quoted: F.O.B. Miami Prices valid for: 90DA YS Lead time: 60DA YS (Based on aVaJJabiHly as of above dale) Terms; Prices quoted are bllSed upon quantities listed. Any ~hanges will invalidate quote. Order will be processed upon receipt of ( I) Signed approved quotation; (2) Purchase Order confirming quantities Ql'ANTlTY TYPE CATALOG Nl:l\lBER AND DESCRIPTION Ul\1T PRICE TOTAL PRICE NEW fIXTL"'RES 9 OA 51,147.50 SIO,J!7.5(J 6 OB 5337.50 S!.025 00 PLUS FREJGHT ON BOTH lTEMS.... TB.D. / - i /'~'~ ,/ " '- , ) - I,.f() r~ IALL LA.\1PS INCLUDED SUBTOTAL SU,J52.SO jeOMPLETE QUOTE MUST BE t:SED,NO PARTIALS TAX 5302.91 IALl QUOTATIONS ARE SUBJECT TO APPROVAL. OT.~ 513.1:5.41 :/ I"\....I~ V-...J 'j~_J IV,""t-"'tCl /"\IILJIUrIY OUrKe . .... - 305-296-2587 ~ American Glass Light Product Spec Sheet: Fixture Name: Betsey Uplight ... -- ,.:.- .l!,; T~PL OA ~-- .-.. . "'''. Catalog #: 5533-U Selected vVidth: 33" Selected H~ight: 37" (std) Se!ectej Lamping: (i!.) 26vV Quad Tube Compact Fluoiescent Selected GlasslPanel: Black & VVhite Sandblasted G!ass Selecter.! Finish: Satin al:.Jminum/nickel p.5 -~ I . ,'" " ,.~, ~ . " ..h '.. ..' . . -, ,:... , Additional Deta1ls: \Neight for standard tamping 23"y.'idth: 10 Lbs. Weight for standard lampi.1g 33 width: 30 Lbs. Uses (3) 60'N A lamps at 16" height Please contact us for iamp speciTicat;cr; and ballast remoting information. Meta! halide lamping requires remote ballast. Extensioi. option available, Dimensions, finishes, and lam ping ship standard as listed unless spedal oreie;- options are requested. 120 volts IS standard unless other vottage is ordered. Your NOles: 't/hen specifying this product, please indicate all selected options so we have complete information when an order is placed 1J~,IO~vjc?r2-- QlV\- (0) r ~~~~C4-? ~(wv. \~ http'!\\",,,,,\\ am::nc:anglass light, com!SpecSheet.asp 1~?t1l~0Yl 1I L1JW1 u /-t}tO 0v6t 5117/2006 f \.'..~ Vv 'v I V."'T""'TQ /""\1 III IUIIY Dur ,,'=' 305-296-2587 p.6 American Glass Light Product Spec Sheet: ,C;j Fixture Name: Lucy Sconce 'Ty fiE- . Qb '., t" ;' .::~.~ , . '. ".:. ,~"?~:"> . ;?'~?' .,~. Cata log #: ,8010-8 Selected Width: 10" , .;: ~., Selected Height: 9 1/2" Selected Lamping: (2) 40'/'; Candelabra Selected Glass/Panel: \/\/nite Sandblasted Glass (std.) Selected Finish: Sa~:n aluminum Ac:fditional Details: Projection: 4" Distance from top to center of wiring box: 2 1/4' Weight standard la:11:Jing: 4 Lbs. Dimensions, finishes, lamping and voltage are standard as listed unless special order options are requested. 120 volts IS sta ldard unless other voltage is ordered. Your Notes: When specifying this product, please indicate all selected options so we have complete information when an order is placed. I~' . ',;y" f'\{l____ ~x:~rvV, I V- D- ~~V~. - ("'\ ~ (z) ~~~. .~-1J ( f '\ (rJ 'I (~1..M)rJ.- fl. l-'L- J ~l1O,~ ltO'e ~~ XI \- llP) - ~) U\Fvv ~\: ~\JM?XV\.rvf'VV' h . 1 j h 'co Sh '-/16,:'_006 rtp.. \\'\\,\ arr:.~ncang ass,ig t :om.)pcc eet.asp MONROE COUNTY ENGINEERING DIVISION CONfRACf CHANGE ORDER PROJECT TITLE: Duck Key Recreational Pathway CHANGE ORDER NO: 1 Total Previous Change Orders Current Change Order % of Original Contract Amount % of Contract after Prior C/O's Original Contract Amount Revised Contract Amount Change in contract time Revised date of Substantial Completion $0.00 $7.308.26 1.015 $720.146.79 $727.455.05 Detailed description of change order and justification: Cost to install and furnish one additionalliqht pole at Section 4+50. The price includes one liqht pole. liqht pole base and electrical system connection. Item #9 Item #10 Description Electrical System Conduit Liqht Pole With Base Unit Cost 1 LScev.$3603.25 1 LScev.$3705.01 CONTRACTOR: .. SR. PROJECT MANAGER Rick Torcise Vice President It) C "'------I _ Albe#~_ ~ S.ltoppel, P.E. t' " / ' ,i~/ l, ~ _-/(rl ( ( L, - I ( ~ / Thomas J. Willi COUNTY ENGINEER: COUNTY ADMINISTRATOR: CMD007-11/03/97 Amount $3603.25 $3705.01 Total $7,308.26 q );1 r>(P Da 9 ~c'l(jb ate' "7 ,'v It) , ? \.;V Date /C'1 Atlant,c Civil, Inc. TRANSMITT AL No. 00025 9350 South Dixie Highway, #1250 \1131111, FL 33156 Phone: 305-670-9610 Fax: 305-670-6787 PROJECT: Duck Key Rec Pathway, Monroe TO: Monroe County Engineering Department 1100 Simonton St., #2-216 Key West, FL 33040 DATE: 9/27/2006 REF: A-31l: C.O. No. 1 ATTN: Albert Edwards JOB: 06048 WE ARE :"001 FOR' AC IIINTAUli'1\!. 0 Shop Drawings 0 Approval 0 Approved as Submilted 0 Leiter Ii!!" Your Use 0 Approved as Noted 0 I'rinls Ii!!" As Requested 0 Returned After Loan 0 Change Order 0 Review and Comment 0 Resubmit 0 Plans 0 Submil 0 Samples SENT VIA: Hand Delivery 0 Returned 0 Specifications Ii!!" Attached 0 Returned for Corrections 0 Other o Separate Cover ITEM NO. COPIES DATE ITEM NUMBER DESCRIPTION STATUS NEW Executed Change Order No.1 Remarks: Please return a fully executed copy for our files. Thank you. cc: Signe~ .-;e~_fJ Dan Pickel I \;JcJil;,-,n 1/ Change Order Attachment per Ordinance No. 004.1999 · Change Order was not included in the original contract specifications. Yes [8J No D If Yes, explanation: The space between project designed light poles at this section was too far apart. This change was made with the County Engineer's approval. · Change Order was included in the original specifications. Yes DNa [8J If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes No X If Yes, explanation as to why it is not subject for a calling for bids: · Project architect approves the change order. Yes D No [8J If no, explanation of why: N/A · Change Order is correcting an error or omission in design document. Yes DNa [8] Should a claim under the applicable professional liability policy be made? Yes D No [8] Explain: MEMORANDUM TO: Board of County Commissioners From: Debbie Frederick Deputy County Administrator Date: October 3, 2006 RE: Change Orders Attached is a proposed change order for the Duck Key Recreational Pathway (Change Order #1 is for $7,308.26 for installation of one additional light pole at Section 4+50.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. -1 j llJ(~( LUI ~111 The Administrator intends to approve this change order on Wedn.esda.y, October 1, 2006. ~ -., i j . ( . \ ,~" / <j' . "<L ..[ i i:. ,:: I reI. .~ ~ Debbie Frederick Deputy County Administrator DLF:cac Campo-Abra From: Campo-Abra Sent: Tuesday, October 03, 2006 11: 15 AM To: County Commissioners and Aides Subject: Duck Key Recreational Pathway Attachments: 00002683_10999.tif Please review attached change order #1 for Installation of one Additional Light Pole at Section 4+50. Abra Campo Sr. Administrative Assistant Office of County Administrator 1100 Simonton St, Suite 205 Key Wes'~ FL 33040 (305)292-4445 10/3/2006 ri:lg~ 1 U1 1 MONROE COUNTY / ENGINEERING /FACILmES DEVELOPMENf CONTRACf CHANGE ORDER PROJECT TITLE: Big Coppitt Key Park Avenue F. Big Coppitt Key, Florida CHANGE ORDER NO: 1 INITIA TJON DATE: September 17, 2006 CONTRACT DATE: June 16, 2004 TO CONTRACTOR: Charley Toppino and Sons P.O. Box 787 Key West, FL 33041 The Contract is changed as foUows: The original (Contract Sum) (Guaranteed Maximum Price) ......... ... ............ ... ............. Net change by previously authorized Change Orders ... ... ... ...... ... ......... ... ...... ... ... ...... The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was... ... ... The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanaed) by this Change Order ...... ... ......... $0.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $706.492.25 The Contract Time will be (increased) (decreased) {unchanged} by... ...... ... ... ... ...... '" ... 90 Days The date of Substantial Completion as of the date of this Change Order is ......... ...... .....December 16, 2006 $706,492.25 0.00 $706,492.25 Detailed description of change order and justification: To extend the contract time for substantial comDletion 90 claw. from Seotember 17. 2006 to December 16.2006 due to delavs in obtain in a the bui/dina Dermit. This Chanae Order is .00 %f the oriainal contract amount. Not valid until sianed bv Owner. Construction Manaaer and Contractor ARCHITECT: NlA CONTRACTOR: , (7~ ~AJ--v-~.,. ~. C artey Toppmo and Sons, I Datr 9 2Co/D(O I Da'te c -2/--d Date -- 21)/ ()t Date J olyo{/; Date DIRECTOR, FACILITIES DEVELOPMENT: o . ppe P. : i . . -- . ~ ~/< /uu C')? clcl Thomas Willi/Debbie Frederick-Deputy COUNTY ENGINEER: COUNTY ADMINISTRATOR Change Order Attachment per Ordinance No. 004-1999 . Change Orderwas not included in the original contract specifications. Yes f81 No 0 If Yes, explanation: Change Order is for an extension of time due to delays in obtaining a building permit. . Change Order was included in the original specifications. Yes 0 No f81 If Yes, explanation of increase in price: . Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes D No ~ If Yes, explanation as to why it is not subject for a calling for bids: . Project architect approves the change order. Yes D No f81 If no, explanation of why: . Change Order is correcting an error or omission in design document. Yes DNa f81 Should a claim under the applicable professionalliabiUty policy be made? Yes 0 No f81 Explain: MEMORANDUM TO: Board of County Commissioners From: Debbie Frederick Deputy County Administrator Date: September 29, 2006 RE: Change Orders Attached is a proposed change order for Charley Toppino and Sons, for Big Coppitt Key Park. (Change Order #1 is to Extend the Contract Time for Substantial completion 90 days, from September 17, 2006 to December 16, 2006 due to delays in obtaining the building permit. The contract sum will remain the same.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. Lt'<<j. Lj-\JYJ The Administrator intends to approve this change order on. Monckrf, October f: 2006. J1 (-- ...- . /,_~'t- =AJ Jmi(K Debbie Frederick Deputy County Administrator DLF: adc Page 1 of 1 Campo-Abra From: Campo-Abra Sent: Tuesday, October 03, 2006 11:22 AM To: County Commissioners and Aides Subject: Big Coppitt Key Park Attachments: 00002684_11 001.tlf Please review attached Change Order #1 for Charley Topplno and Sons for an Extension in the Contract Time. Abra Campo Sr. Administrative Assistant OffICe of County Administrator 1100 Simonton St. Suite 205 Key Wese FL 33040 (305)292-4445 10/3/2006 MONROE COUNTY / ENGINEERING /FACILlTIES DEVELOPMENT CONTRACf CHANGE ORDER PROJECT TITLE: Freeman Justice Center Jackson Square Key West, FL TO CONTRACTOR: The Tower Groug. Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 + The Contract is changed as follows: CHANGE ORDER NO: 17 INITIATION DATE: August 3, 2006 CONTRACT DATE: June 16, 2004 The original (Contract Sum) (Guaranteed Maximum Price) ........................................ $13,804,000.00 Net change by previously authorized Change Orders ......... ...... ...... ......... ...... ...... ...... $ 962,413.68 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ......... $14,766,413.68 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ................. $ 67,183.46 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $14,833,597.14 The Contract Time will be (increased) (decreased) (unchanaed) by .................. ( ) N/A The date of Substantial Completion as ofthe date of this Change Order is ... ... ". ...... ...January 25,2007 Detailed description of change order and justification: Furnish and Install the Domestic Hot Water SYStem In the Freeman Justice Center to Include: · Mater/als. Labor. Profit - Weatherlrol Maintenance Com $61.043.13 · Electrical Services. The Tower GrouD w/overhead 1.268.50 · 5% Protit- The Tower GrouD 3.112.56 · Sales Taxes 1.759.27 Toml $6~18~46 This Chanue Order is .49% of the or/ulnal contract amount Not valid until Signed bv Owner. Construction Manaaer and Contractor ARCHITECT: CONTRACTOR: 11lo l~~ The Tower Group D1e 9/1/ O~ Date DIRECTOR, FACILITIES DEVELOPMENT: 9-/fftJb Date /Q4/ot I Date COUNTY ENGINEER: COUNTY ADMINISTRATOR Q9/27/2006 WED 5:01 FAX 3052923435 16th Jud Court Admin @001/002 ~ra.~~~ ~"""'~~-"i .' .. -~ ... , .. GOD 'W1l SIXTEENTH JUDICIAL CmCUIT OP FLoRIDA.. MONROE COUNTY COURTHOUSE ANNEX 500 WHITtHf;AD ST~f;f;T KEY WEST, FLORIDA 33040 T~~~~~O~~(30olee&'o.~o SlJ"'CO~: "'_'3"23 TELEFAX (3Ql:il Z61Z'343:l September 26, 2006 Mr. David Koppel Monroe County Engineer 1100 Simonton Street Key West, FL 33040 Monroe C FQcltltles D0ve~unty oPment SEP 2 6 20D6 RE: Freeman Justice Center liME; RECEiVEDBY:-'->>~--'---IJt+-;..__~ .~.--.........~, -. Dear Mr. Koppel: Please see attached change order requests from the Tower Group: · Change Order Request 00041 in the amount of$67,183.46 Back in December, 2005, during a construction meeting, the Court asked if there was hot water in the building. After determining there was not, we requested the installation of a hot water system throughout the building. The clientele that frequent the courthouse are not always the cleanest <.md countless times we have had to clean up urine. vomit an.d other bodily fluids using cold water. In addition, all users and staff ofthe courthouse havc to usc cold vvatcr to wash thcir hands aftcr using thc rcstroom. Thcsc are not sanitary practices. In this regard, the Court is offering to pay the above amoun.t using the Courthouse Facilities budget. By using this existing budget, .there would be no additional costs to the Capital FtUld in approving this change order. If you need any additional information or have any questions, please do not hesitate to contact me. Sincerely, Holly H. ElomlOs Administrative Scrviccs Manager Cc: Richard G. Payne, Chief Judge. John Chandler, The Tower (Jroup {/Ltc~~~~~ ;'!dltt;;'L~C""~. r~-i C~=.C<.c H< .c a;;:~~=~ Of. ..~ .O~=.=~. =='~-J'~='=f:_,",,=,_~ "==-~=='~.='''--4~~_ [9/27/2006 WED 5:01 FAX 3052923435 16th Jud Court Admin $e.,-Z6-Z006 14:46 @002/002 From-MONROE COUNTY ENGINERING +3[]SZS5lt3Z1 T-444 P. 004/008 F"355 CHANGE ORDER 1(J1;VUji;~T No. 00041 - . . The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL ~3325 Phone~ (954) 476-3200 Fax: (954) 474.-3111 TITLE: Domestic Hot Water SysteDl PROJECT: Freeman Justice Center (FIC) TO:' Attn: Clark Briggs Monroe County Facilities Development 110'0 Simonton Street Key West, FL 33040 . Phone: (305) 295-4306 Fax; (305) 295-4321 DATE: 8/312006 .JOB: 0417 CONTRACT Nqr, 1 onroe county FaCilities Development SEP 2 6 2006 liME: ~. RECEMD8Y:=-~' ._~ - RE: peD To: TTG From: WEA THmtT Number: wr007 A '" DES~1'IdN'Q~.Pl\PP-osAi..' ," ,'.' :':' :".,.~'. :."..; ...:,.: :~....: ;,: :~.;?:- ~~::i;.;:;':,~~:.:~;~' .'. -- '. :: ~,~'.:~.: ,,,,', :.' .:. ::: :..-:':: " ': . ..:.' Change Order Request (COR) 1141 proposes to furnish and install me Domestic Hor War.er: ~ fOT the Freeman Justice Center for a Contr.lct Price Increase of$67,183.46. . The seope ofwol1c t'orthis proposl'1l is oased 01:1 TYEe Imtwing #1"-1.0 dated 6/14/06, tlP-I.l deud 6/14/06, #P-12 dated 6n4l06. #P-L3 dated 7/11.100, and #P-2.1 d:lt2d 6/14/06. The cost oftll\:: proposed work is based on Proposed Ch~ie Order #WT007A by Wcathertrol Maintenance Corporation (r;;op)' ilttaehcd, 5 ~c:;) and the Wat" Heater EleetricBl esdnlate by no (copy attached, 1 page). We reserve our right to a Contract rune ExtenSion for thtS additi~ work, pellding an impact imalySis to assess me c;hlimges, if any, ro the Critical Path for the Project. I~ 00001 Desmp'tioD' .. ftlmisb lU'I!I Install plpln~ WUlm' I~. pumps and plumbing nceessorics (peO 1IW1O(J7 ^ l=9 SilIca t=) flni:;h lIlUI instllll clc;;Pi, services for pumps IUId \VIltcr heater l~ j;ales t;ur,; Stock#'. ':-. ." .QmW:titY .':u;urs ,-.: :'. ' ~T1iiit'Ptiee.--:';'':'-TaX.:iatc:TliX 'Am~u'n:t ,Net'AmOUnt . 1.000 J.S $61.043.13 0_00% ~o.OO $6l.D43.13 ~ 00002 1.000 J.S Sl,20UO 0.00% so.oo Sl,2.08.IO ./' '. ..' ..... ~ .. - - Descnption' ..~. .-. . '.. Sales Tax for Item # 1 Sales Tax for Item #2 5% Overhead for Item #2 Profit Unit Cost: $62~251.23 Unit T~: $0-00 tTnit Total: $62,251.23 Subtotal: $62,251.2.3 . .... . I I ~". MaJ"wp.!P.erc,mt. .MarkUp Amomrt $1,720.24 v $39.03 $60.40 ./ / $3,112.56 5.000% Total Cost: $67,183.46 j' Change Order Attachment per Ordinance No. 004-1999 · Change Order was not included in the original contract specifications. Yes 181 No D If Yes, explanation: The installation of a hot water system is requested by the 1~ Judicial Circuit · Change Order was included in the original specifications. Yes D No 181 If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes D No 181 If Yes, explanation as to why it is not subject for a calling for bids: · Project architect approves the change order. Yes D No 181 If no, explanation of why: The Architect is not required to approve Change Orders for the Freeman Justice Center. · Change Order is correcting an error or omission in design document. Yes DNo 181 Should a claim under the applicable professional liability policy be made? Yes D No I2l Explain: ..- CHANGE ORDER REQUEST No. 00041 The 'rower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 TITLE: Domestic Hot Water System DATE: 8/3/2006 JOB: 0417 CONTRACT NO: 1 PROJECT: Freeman Justice Center (FJC) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 RE: PCO To: TTG From: WEATHERT Number: WT007A D:Il:SPRIPTlONOF.PRQPOSAL . ..........,; Change Order Request (COR) #41 proposes to furnish and install the Domestic Hot Water System for the Freeman Justice Center for a Contract Price Increase of $67,183.46. The scope of work for this proposal is based on TYEC Drawing #P-1.0 dated 6/14/06, #P-1.l dated 6/14/06, #P-1.2 dated 6/14/06, #P-1.3 dated 7/12/06, and #P-2.1 dated 6/14/06. The cost of the proposed work is based on Proposed Change Order #WT007A by Weathertrol Maintenance Corporation (copy attached, 5 pages) and the Water Heater Electrical estimate by ITG (copy attached, 1 page). We reserve our right to a Contract Time Extension for this additional work, pending an impact analysis to assess the changes, ifany, to the Critical Path for the Project. Item 00001 J)esdtivtl())\8to~R# . Furnish and install piping, water heater, pumps and plumbing accessories (peO #WT007 A less sales tax) Finish and install electric services for pumps and water heater less sales tax QuantiiySUnits<i 1.000 LS 'Unit Pri~e'.: ,'T~:x:Rate~a.'s;~molitlt'Net'Aftl1ount $61,043.13 0.00% $0.00 $61,043.13 00002 1.000 LS $1,208.10 0.00% $0.00 $1,208.10 Unit Cost: Unit Tax: Unit Total: Subtotal: $62,251.23 $0.00 $62,251.23 $62,251.23 5% Overhead for Item #2 'Nl~~kti)}.'Pcrc~Jft",'Marf{up .Afitc>u.nt $1,720.24 $39.03 $60.40 $3,112.56 5.000% Descriptid]). Sales Tax for Item #1 Sales Tax for Item #2 Profit Total Cost: $67,183.46 -t ~ ...I < ii: ..JW <~ ~:E 0:::...1 1-< ul- We mI- l:: z :::> ffi::!: I-W <I- w- ::I: 0::: W I- < ~ o:::~~~~gg~~~g~gggggggg~g gN~ciciciciNNciciciciciciciciciciciwN j ...I < l- e I- I:: zww:E:EUUUU:E:E:Eooeoooooww :::> 0::: eooogooooogooooooooooo m'l:tNO ,OOI()OO ,cooOOOOOONcn <N~M~cio~~~~wcicicicicicicioMN ...l .,,'" ~" ~ -...... " "', "- " 'l:tOM~M~OI()N~~NI()ON~OONOO 'l:tOI()~~~~O~~N~MNNcnN'l:t~OO ci~NM~NNW~WWM~NW~NN~cici 000000~'l:tN'l:t0000M000M00 ~ 0~00 0 0 o 0 WWUUUUUU:E:E:EUUUUUUUU W'l:tO~OOOOO~ONO~N~'l:tNOOOO 'l:tOI()'l:tNN'l:t~~NN'l:tM~~~~~NOO ~ci~ci~M~~NNci~N~~N~~~~cici O:::00I()cnOM~cn~~~~~O~~O~~00 ~~ 00~~~~~~~00~~~~~~ CI) CI) o:::CI) 0:::C) 0:::C) ~~!::l-oO:::I- C)o~CI)C)oz 0:::0::::::>-1-05!::wwW~I-::I:~ZI--CI) 0::: mmo:::>ul-uo~O:::o:::O:::..JUCI)<-u::I:~ w WwzOw o>->~w~o:::..J CI)< I- ..J..Jozz~~z>~>~zml-~~~O:::~~ oeuozzuoN~OOZuCI)oZ ~O::I: ~~~uoo u~~~UO-I-UOU I- M~W~U I-I-~ ~l-ul-:E u~l-oO::: ~~i~~~~:E~~~:EI-~W~I-~~:E~ :E:E u...Jw w::I:::I:::I:W:E...l. w:E-I < <<~ u...J~ I-I-I-~w~~ w~~ ~ OO-~ U.M~ _. . M~ ~NM ~ M'l:t~ ~~ (;;~ (;;M I:: zwwttwwtttttwwwwwwwwww :::> 1-C1~~~I()'l:t'l:tNOI()O~OOI()NN~I()NNON~ I()~~N ' ~ cncnM~MM N~OMO~ ~M3ci~~ ~'l:t NM'l:t 'l:tNI()0N 00 0 ~~ o o Cl)O~ O:::M~ ::I:NI() o ...I ~@)@) o I- ~O:::ZI_V\ , Ow; Om 0 '" ~<o:::;::; 0-1~~ mr::: ~ ...I ~~ 1-0 I- WeathertroI Maintenance Corporation PROPOSED CHANGE ORDER No. WT007A 7250 NE 4th Ave. Phone: 305-908-1000 Miami, FL 33138 Fax: 305-908-1039 TITLE: Domestic Hot Water System Addition DATE: 8/1/2006 PROJECT: Freeman Justice Center (FJC) JOB: 0417 TO: Attn: John Chandler CONTRACT NO: 0417-004 The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 RE: COR To: MCCM From: ITG Number: 00041 D19$CRIPl'IO~() F PR()POSA L Based on Weathertrol COR #04-790-0015, dated 8/1/06, with corrections in accordance with the General Conditions of the Prime Contract. iteM nesct1ijJdhn' 00001 Material by Tasca (less sales tax) 00002 10% Mark-up on materials for Tasco 00003 Labor & burden for Tasco 00004 Lodging & Meals for Tasca ': Quantity Uoits 1,000 LS Viiit Price'" ,,~li~'Rat~trai~lJi~tlftt!~~ti~iHoitnt $24,574.83 0.00% $0.00 $24,574.83 ....,/ 1.000 LS $2,457.48 0.00% $0.00 $2,457.48 v' 1,000 LS I, 000 LS $23,004.00 $8,100.00 0.00% 0.00% $0.00 $23,004.00 ./ $0.00 $8,100.00 - Unit Cost: Unit Tax: Unit Total: Subtotal: $58,136.31 $0.00 $58,136.31 $58,136.31 Description Markupp~rc~nt l\1nrkup Ambudi Sales Tax on Tasco Material $1,720.24 Profit 5.000% $2,906.82 Total Cost: $62,763.37 By: By: Hector Ruiz John Chandler Date: Date: Expedition @ weC!.,f~~~t.rQ! ~ CHANGE ORDER REQUEST Change Order: Request #: 04-790-0015 Date: 8/1/2006 Project: Freeman Justice Center To: The Tower Group @ Freeman Justice Center . Attn: John Chand'er 500 Whitehead St. Key West, FL 33040 Project #: 04*790 From: Weathertrol Hector J. Ruiz 500 Whitehead Street Key West, FL 33040 Ph.: (305) 296-2621 Fax: (305) 296-2587 Ph.: (305) 908-1000 Fax: (305) 908--1039 We hereby propose to make the following changes: Oomestlc Hot Water Syatem Addition (AO.Smith Heater Revision) Change Order Price Original Contract Amount $, b11 1C/3. 37 .~ $1,269.385.00 This price is good for 0 days. If conditions change, this price is void. We are requesting a time extension of 0 days In conjunction with this change. Hector J. Ruiz Author 8/112006 Date o Accepted. The above prices and specifications of this Change Order request are satisfactory and are hereby accepted. All work to be performed under same terms and conditions as specified in original contrac.t unless otherwise specified. AuthoriZed Signature Date of Acceptance CHANGE ORDER REQUEST SUMMARY Project: Freeman Justice Center COR #: 04-790-0015 Subcontracts !SUbconttaetot Tasco Plumbing Description Domestic Hot Water System per Plans Dated Ot/07/06 Total $59,471.07 Subtotal $59.471.07 $0.00 Total Cost Subcontract Cless.-Ftx) Markup Subcontract Tax $i9.471.B7 )"B, 13b,31 .$2,973.55 2" Cj06.82 i>- {, 1).,0, 'vi- ~ ..s&a,Ms.07 02,7'3.'37 Bond Total MEMORANDUM TO: Board of County Commissioners From: Thomas J. Willi County Administrator Date: October 2, 2006 RE: Change Order Attached is a proposed change order for The Tower Group, for the Freeman Justice Center. (Change Order #17 is for $67,183-46 for installation of the Domestic Hot Water System.) This will be funded by the Sixteenth judicial Circuit Court. See attached letter. According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. [(tel 4-111 The Administrator intends to approve this change order on Tuesday, October,,3, 2006. TJW:cac Page 1 of 1 Campo-Abra From: Campo-Abra Sent: Tuesday, October 03,2006 11 :31 AM To: County Commissioners and Aides Subject: Freeman Justice Center Attachments: 00002685_11 002.tif Please review attached Change Order # 17 for The Tower Group. Abra Campo Sr. Administrative Assistant OffICe of County Administrator 1100 Simonton St. Suite 205 Key We5~ FL 33040 (305)292-4445 10/3/2006 '-~ v ~r}\,0 MONROE COUNTY / ENGINEERING /FACILffiES DEVELOPMENT CONTRACf CHANGE ORDER PROJECT TITLE: Freeman Justice Center Jackson Square Key West, FL TO CONTRACTOR: The Tower Grou~. Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 CHANGE ORDER NO: 19 INITIATION DATE: August 16, 2006 CONTRA.CT DATE: June 16, 2004 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price) ... ... ...... ... ... .................. .... $13,804,000.00 Net change by previously authorized Change Orders ...... ...... ... ............ ... ...... ... ... ...... $1,052,648.48 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was... ... ... $14,856,648.48 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ...... ...... ..... $ 37,288.84 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is... $14,893,937.32 The Contract Time will be (increased) (decreased) (unchanaed) by... ... ...... ... ... ( ) N1A The date of Substantial Completion as ofthe date of this Change Order is ............... ...January 25,2007 Detailed description of change order and justification: Time and Materials for the comoletion of the Securitv Uoorades not included in Chanae Order #12. This includes Patchwork. Corina. Cuttino. and Chiooina. This Chanae Order is .27% of the oriainal contract amount Not valid until sianed bv Owner. Construction Manaaer and Contractor ARCHITECT: N/A L1J~ re 1 J5/0~ Date CONTRACTOR: The Tower Group DIRECTOR, FACILITIES DEVELOPMENT: J - ~~L!Jtb Date 9~ Jr d Date COUNTY ENGINEER: COUNTY ADMINISTRATOR Change Order Attachment per Ordinance No. 004-1999 . Change Order was not included in the original contract specifications. Yes 181 No 0 If Yes, explanation: This Change Order is for labor and material to complete the Security Upgrades that were not included in Change Order #12. . Change Order was included in the original specifications. Yes 0 No 181 If Yes, explanation of increase in price: . Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes 0 No 181 If Yes, explanation as to why it is not subject for a calling for bids: . Project architect approves the change order. Yes 0 No 181 If no, explanation of why: The Architect is not required to approve Change Orders for the Freeman Justice Center. . Change Order is correcting an error or omission in design document. Yes DNo 181 Should a claim under the applicable professional liability policy be made? Yes 0 No 181 Explain: - The Tower Group, Inc. CHANGE ORDER REQUEST No. 00054 302 Fleming St. (Job-site Trailer) Key West, FL 33040 Phone: 305-296-2521 Fax: 305-296-2587 TITLE: Security Revisions T &M DATE: 8116/20M~ki..>\:v'fuih\ . COHSTftllcnON MANAGEMEm' JOB: 0417 1 8 2006 CONT~T~~ruN MANAGtM'"NT MCEIVID BY: Auo 1 d i..vvJ {\ -' TIME: i~\. ./ ~ff~=~=~L="=" PROJECT: Freeman Justice Center (FJC) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 RE: COR To: MCCM D.ESCRIPTI6N.0EiPROPOSt\:I& From: TTG Number: 00023Rl This Change Order Request is for the cost of labor and material for structural and demolition work performed to complete Security Upgrades. This work was specifically excluded from the Scope of Work in COR#23. Finishing work such as stucco, paint, and the installation of door frames will be addressed under a separate COR. A detailed description of the work and itemized cost breakdown is attached (20 pages). ~ ,-"=,,,,"_;0,," 'coo- . => '-'- _r'" -~~'- Item Description Stock# Quantity . Units Unit Price Tax Rate Tax AmountNet Amount 00001 EGB Job Work Order #2675 1.000 LS $4,460.40 0.00% $0.00 $4,460.40 00002 EGB Job Work Order #2676 1.000 LS $4,327.05 0.00% $0.00 $4,327.05 00003 EGB Job Work Order #2679 1.000 LS $1,521.19 0.00% $0.00 $1,521.19 00004 EGB Job Work Order #2973 1.000 LS $4,102.88 0.00% $0.00 $4,102.88 00005 EGB Job Work Order #2975 I. 000 LS $3,612.00 0.00% $0.00 $3,612.00 00006 TTG Week Ending 5/19/06 1.000 LS $4,95000 0.00% $0. 00 'It:(j()~,4;95Q.!JfJ 00007 TTG Week Ending 5/26/06 I. 000 LS $3,000.00 0.00% $0.00 $3,000.00 00008 TTG Week Ending 6/2/06 I. 000 LS $1,000.00 0.00% $0.00 $1,000.00 00009 TTG Week Ending 6/23/06 1.000 LS $3,500.00 0.00% $0.00 $3,500.00 00010 American Cutting & Drilling I. 000 LS :$6,49CI6 0.00% $0.00 U#*~}6..{,7 8'f)S'.. 00011 Waste Mgmt (dumpster) 1.000 LS $484.79 0.00% $0.00 $484.79 Unit Cost: Unit Tax: Unit Total: MONRUE Cl)UNlY CONSTRUCTION MANAGEMENT Time and Material Summary for Security Revisions 8/17/06 AUG 1 8 2006 liME: ~~~ / m:CEMfJ B't; ~ .;. / Description of Works Stair #1: Work in this area was put on hold. Door frame was cut-out ofthe stairwell. Door G 126 relocated to exterior wall line B/1. 7. Hand and machine excavation for new footing and new masonry wall line 8.2/1.5-2. Cutting and patching of masonry to receive devices. (Finishes to be made good and replacement of door frame are not included in this summary). Stair #2: Work in this area was put on hold. Door frame was cut-out of the stairwell. Door G 133 relocated to exterior wall line 817.3. Hand and machine excavation for new grade beam, footing and masonry walls line A/6-7 and 87.2-7.5 x 7.2/B-B.2. Cutting and patching of masonry to receive devices.(Exterior sidewalk, replacement of door frame, and finishes to be made good are not included in this summary). Stair #3: Work in this area was delayed. Door G 1 0 1 was cut-out of stairwell to be replaced and opening was cut-into exterior wall to receive a new door. Block wall at Judges Entrance was demolished and rubble removed from site. Spoils removed and area re-graded. (Finishes to be made good, replacement of frames and Exterior Stair not included in this summary). Stair #4: Work in this area was delayed. Masonry wall at G 122 partly demolished and rebuilt to receive devices. Door G 124 frame was cut-out of stairwell. New opening cut into stairwell to receive new frame. Wall at G 125 was demolished, hand and machine excavation for new footing and masonry walls for relocated door G 125. Masonry around existing utilities at underside of 1 st floor slab. (Finishes to be made good and replacement of door frames not included in this summary). Sallvport: Work in this area continues to be delayed. Saw-cut and remove exterior wall at G 1 02. Masonry walls at bathroom and storeroom demolished to below grade and rubble removed. Cut and patch masonry to receive devices. New ramp and steps at Gl07. Re-grade for floor slab. (Finishes to be made good, replacement of frame G 1 07 and new structural work at G 102 & G 1 03 not included in this summary). Electrical Room G029: Delay to work in this area. Hand excavate for slab thickening at sub-grade conduits. New masonry walls. (New door and frame installation and finishes to be made good not included in this summary). Garage Parking: Additional fonnwork and concrete for slots for rolling gates. Machine re-grading of garage area after installation of electrical conduits. Holding Cells: Work in progress to slab on grade was stopped in this area. Rebar was removed and replaced. Masonry walls at G007 and GO 17 demolished and rubble removed. (Replacement of door frames, finishes to be made good and structural work at Holding Cell entrance walls not included in this summary). \'\ \\ \ 0000 0000 0000 000'<:1" I'-<DI.!)<D ') '~ '\ 000 000 aNN '<:tl'-..- '<:t <D (") (") ~~~~~~~~~~~~~~~~~ I.!) I'- 0) N X =t:t:W 0> "0 L- a ..x: L- OCOOOO SO"-"-(")~ MONkltt. (,;i.II.H'1 h CONSTRUCTION MANAGEMENT AUG 1 8 2006 llME: m:CEIIIrn f:j1f; n. ~ " ,j / '/' .0 o --, \ \ \ \ \ 000 o coco 00 I.!) I.!)(")CO triON I I'-I.!)N 1'-0(") 00)0 0)<D(,,) 0)..-..- N- (")- '<:t- ~~~~~~~~~~~~~~~~~ ('") I'- 0) N X =t:t:W L- Q) "0 L- a ..x: L- o >. Sa .0 o --, 0 I.!) 0 0 ('") '<:t ('") ) \ \ \\ \ \ \ 0 0 0 o I.!) I.!) '<:to) 0 0 I.!) ON I'-'<:t..- a I a I N I 00 I cON"": N 0 ..- ..- ~I'-~ '<:t <D ('") ..- ..- ..- ..x: L- o S 0) I'- <D Nx =t:t:W L- Q) "0 L- a ..x: L- o S .0 o --, ") \ \ o I.!) I.!) 000 ..-<DI'- NON ..-N('") '<:t '<:t ~~~~ ~~~~~~~~~~~~~~~~~ >. a<D ..- I.!) N I.!) N N ..- z. 'C :::l U Q) if) co <.9 w \ \ \ \ 00 00 , . I I.!)<D 1'-0) NO ') o o o <D ..- <D I'- <D N X =t:t:W L- Q) "0 L- a ..x: o >. SaO) 00 00 00 (,")<D <DO) ~~~~~~~~~~~ .0 o --, ) I.!) '<:t ~I.!)I'- NN <D ")'::. ':o.'~ I.!) 0000 I'- 0000 <D ,.,. I NxOOOCO =t:t:wR~~~ ~ o o <D ..- '\ ", '" 0000 oo'<:t'<:t OCONO O'<:t..-<D '<:tNN'<:t -<i' '<:t- ~~~~ L- Q) "0 L- a ..x: L- o S .0 o --, ..- ~~~~~~~~~~~ !:!!. 0.. ]j co 06 ) (5 0 CO <D 0 N <D +-' If- ('") co .0 -- 0"- ('") ..- :::l a (f) \ ') ) \ ) 0 0 0 0 0 I.!) 0 0 0 0 0 0 0 0 0 0 0 0 0 I'- 0 0 0 0 0 0 I.!) 0 0 0 0 '<:t I.!) 0 I.!) I.!) I.!) I.!) 0 0 N 0 I'- <D I.!) N <D 0) 0) 0) ..- I.!) ..- ..- ~~~~~~~~~~~~~~ '- >- '- Q) -c>- c 2 Q) L- Q) E ~ :::lo L- '- Q) 0__ co c Q) 0 ill '- Q) 0 E :t co L: 0.. Q) E 0 L- ~ L- co U5 L: co 32 (f) (f) 0 U .0 ..x: L: L- o..Ex Q) co .0 -- C Q) U 0 (f) E- '- ..x: :'Q 0 ~ co u 0 0::: co 0 u.. co :::lci:~ u.. -l .9 0 ..x: co E (') 0.. co (f) Q) C0 0 C0 JoqE?l 1E?1J81E?L^J IU8Wd1nb3 I E.G. BRASWELL CONSTRUGTION INC. I E.G. BRASWELL'LEASING CORP. I 6471 THIRD STREET KEY WEST, FL 33010 305-296-0305 phone 305-296-4321 fax egbraswell.com ,\0 --c\ ('A ~o~" CONSTRUCTION MANAGEMENT AUG 1 8 2006 nME: ~CEM!l S"f: ';,"\ ~ ) i,~ II '\(''\ RATE SHEET as of 05/01/06 2" TRAILER PUMP $85.00 I HaiR +$2.50 per GY Pumped 3" TRAILER PUMP $110.00 I HOL!JR + $2.50 per.cV Pumped 32XL BOOM PUMP $135.00 I HoiliR+ $3.00 per CY~Umped. ' (four hour minimum on boo~ pump) , . , One hour travel time on all pump jobs I EQUIPMENT RENTAL I HpUR BACKHOE $ 95.00 FORKLIFT is 95.00 TRACKHOE $155.00 MUSTANG $ 65.00 WI DEMO HAMMER $ 95.00 LABOR RATES LABORER CARPENTER IRON WORKER FINISHER FOREMAN SUPERINTENDENT PROJECT MANAGER ~ 50.00 $ 60.00 ~ 60,00 $ 60.00 $ 70.00 $ 90.00 $100.00 :... E.G. BRA.SWELL CONSTRUCTION, !~JC. 5640 LA.UREL IWENUE KEY WEST. FLORIDA 33040 (305) 296-0305 J(Q) 19J ~ (Q)1Ri ~ (Q)1RilQ)[g 2675 CUSTOMER'S OROER NO. PHONE HELPER STARTING DATE MECHANIC BILL TO /~./ jL.~' ':. ') " < M~'NR1)llL_I'H 'j ORDER TAKEN BY ADDRESS "I / o DAY WORK o CONTRACT P EXTRA CITY JOB NAME AND LOCATION ~ ~~--~-~._.-~.y JOB PHONE \ DESCRIPTION OF WORK /'! ) ~ (;.~~ / ,...... I' ~ f" " j~ ,f ..,. It / - 'f c,.(./", /( ,..:/ -<;::-;' /;,' / ~ ~.., i.~. ~-' ;/:,,4 ..< ::' ,. . .f) r '7 i.- ,~. 80" 'Fe" ,,- ('1 --/. / ~ {~......... ~" ,.; t.? I , ,. r / .... /"/'7 ~'1. .':5 0'/ (I: .I ;" / " 11 ,1,.;- 1,.."._ >-' ;-;' " j', f..;/' ) ~(,., I --'./ ~) /~~'c:.,~' r:" ~ - of; ..-.,., TOTAL MATERIALS TOTAL LABOR (. C I /+~(k!,{ TAX Signature --:0-0"--/", J I . _,1., . "'" ..,,' /( 0 No one home ~~t:"::,- ...-" l- ~ TOTAL AMOUNT $ o Total amount due for above work: or o Total billing to be mailed after completion of work I hereby acknowledge the satisfactory completion 01 the above described work. E.G. BRASWELL CONSTRUCT!Oi\1 5640 L4UREL AVENUE KEY WEST, FLORIDA 33040 (305) 296-0305 J ~ ; .__. li\"..-I. ~~l2) ~ (QJUll ~ (QlUlllQ)~ 2676 DATE OF ORDER, CUSTOMER'S ORDER NO, PHONE MECHANIC HELPER STARTING DATE BILL TO '..-'~--- ,_)" _' _./ .F--- o DAY WORK o CONTRACT 'EXTRA ADDRESS CITY !ilECEMD 9V: ~~, JOB NAME AND LOCATION ,r-- - --r- ,/ JOB PHONE DESCRIPTION OF WORK, .,c:.., ,-""C -- ~ ,'_/'..~'.' ./ V" /' 'v / -< ,.-"j'-; ,r..' i / ,! " j /;"7 ~\ .5 0" /;. "'? '. ./1 _ (,1/i. v h./' fl .~ , ,. V V t/ /;..; /_- .J ') <- (..:;. ~'- / / :.:-, f ~) r / I? I<~~ :::: /;,:.- r: /J-" ~ _'-: /' -f-- 'I~A i ( TOTAL MATERIALS TOTAL LABOR "r-' C{/t-/ k~f, TAX TOTAL AMOUNT $ Signature o No one home 0 Total amount due '"11~""~ for above work: or I hereby acknowledge the satisfactory completion of the above described Vlork, o Total billing to be mailed aher completion of work t.G ORhS'NEII COr-.;.-,TRUC....IO" :"0 ;'". '-_ 1';01. -I I'., 5540 Ul,UREL AVENUE KEY "v\j~ST. FLORIDA 33040 (305) 296.0305 iNC. JJ(Q)~ W(Q)~~ (Q)~[Q)~ 2679 DATE OF ORDER '" ,/" ( ,.r / /........... ,t/ / 1/.,,'.- CUSTOMER'S ORDER NO, PHONE BILL TO ADDRESS CITY TIME: RECElVrn fff AUG 1 8 20U5 _.ft o DAY WORK o CONTRACT G~EXTRA JOB NAME AND LOCATION DESCRIPTION OF WORK; JOB PHONE i..-( '.:. ,., ,--( , j"-\ ,'. ;' .. '--.' '::/ r' ,"t /~. (r: (" ....;;:.tF1 <" / / '-;,r i- -:-q= /~/ .. / ,.,~ / .-0 / c;.: ,--'r ::::::. ,~ J. (Ii' ,/.~ / 1/ /.( ,~ ./ .( r r (~- ;- ,';.,J /" ~? " J '", (' ,/' (;- .' ,?:' /'~.,.. / I /-! /~' -~o..! :!IJIlI.:" ~ "t ~~, . I,.J ~- r ,>~ . ., . -; /' / TOTAL MATERIALS TOTAL LABOR ./ r /\ ;";( 'J i ,I L;',,.. t /, ..............., r"; I_Y" iL (II.... ;' '1 DATE COMPLETED l ,,\ I WOR100RDERED BY / ,.,ILl. \ I /f ! i '\ j/ ~{/', I 0 No one home Signature \" // \.-~-i:A' l...-/t_f TAX TOTAL AMOUNT $ o Total amount due for above work: or o Total billing to be mailed after completion of work I hereby acknowledge the satisfactory completion of the above described work, [,G. 8RASWELL CONSTRUCT1Qi\l, lNC, 5640 U\UREL AVE~,jUE KEY WEST, FLORIDA 33040 (305) 296-0305 ~(Q)~ ~(QJ~~ (QJ~[Q)U 2700 DATE OF ORDER CUSTOMER'S ORDER NO PHONE MECHANIC :.~. '- HELPER BILL TO --~,.. ~I I " ./ ( I .~/ (:""'7/'- (-:,/r;.:...../ ~ -' ADDRESS CITY ',- JOB NAME AND LOCATION Ie ~~~"....-' .if': ') I j b <,j / ( DESCRIPTION OF WORK f~,''''''l /r.~ I '" ,,- ;' ; ! / '.___ I" { I .t / I 3:/ () {." I ~' F'- ,,- 0 p-7 _.' j' /' ~ (~ -:.......'.. .: ,; ,') /.> ('-"'\ /' ,,' ,:y ,-"/"," /1 f- ,_,J;:->//(~ -.:J." <:~.. -r -' r~/ /) f:!i/" C,'// /... r / n~ /' .' /' { I ~-s ;;: )/oc:. f f j//? Cc- /1 ('y' o J~)~ r.., / c,;;>,,/ I " 1- ,&/"']!"; ,:"..... $ ,/ '/ ol:::c..> _r <:::~ .~...: / ',"" I ,..,--"", 1'/ / .r~., ~;.. " H I ~ j J ( 111 .1 ~ vI ..) i (J f'-....,... ____ ^ I IV '" i /;' 'Y ,/ uft.. I , :..--- v'" / " '::> ~> ;.-' ----- 'Ik ~,~,--- TOTAL MATERIALS .__rO" TOTAL LABOR -' E ,. " A ~,-----~ ..." ; : / / / TAX L ;0:, 1;~ i ( ,,.. , DATE COMPl.ETED ..! .rORK ORDERED BY /,1 /t /1 I.OTAL AMOUNT $ ,.' ./ i I "', Signature /-1 '- o No one home 0 Total amount due for above work: or o Total billing to be mailed after completion of work I hereby acknowledge the satisfactory completion of the above described work. c~ c-,u. \ I BRASWELL CONSTRUCTiON, SociO LAUREL AVENUE f<TY WEST, FLORIDA 33040 (305) 296-0305 !f'~C, ~(Q)~ \I(Q)~~ (Q)~[Q)~ 2 9 7-3 DATE OF ORDER CUSTOMER'S ORDER NO PHONE MECHANIC HELPER STARTING DATE BILL TO //;/ c; -.. .-- i ; ! '/! {~ L---C~ ( ') ;- ,. \;,- :"l~:-''; ORDER TAKEN BY M0tv;,,," '-', ~,.. i ADDRESS CITY o DAY WORK 2lliJJri:ONTRACT DEXTRA JOB NAME AND LOCAT10~_ r- / L..' ::.. "', 7 JOB PHONE DESCRIPTION OF WORK: .7 70' c:r' p:. F I /I~:(~, [3 ~_. ,~ l.2cJ -- ---- , . / "f!cJ /~_/ fr 'j /1 <c. /'5."., r' ;f 0 /'/ c ,0 /7 5Ie(~ / ;:::.,,.. ./ c) .X I /" ....' 1--., ~ r--:> uTe r 5 --r "'}f-"/ (/ / _ f )(... ~-. ~\/ " J u' \i ''-.- TOTAL MATERIALS TOTAL LABOR c ( f~ /2<:/::- "T-Y--(.- TAX Signature WORfiORDERED BY Ii { ~~ ! /' / 0 No one home /1 ......-....,~./f "\ .-; -----./ --..... TOJAL AMOUNT $ o Total amount due for above work: or o Total billing to be mailed after completion of work I hereby acknowledge the satisfactory completion of the above described work. -i' 'i 1 E,G BRASWELL CONSTRUCTION. INC, 564U LAUREL AVENUE ' KEY WEST, FLORIDA 33040 (305) 296-0305 JJ(Q)~ 11(Q)~~ (Q)~[Q)~[ 2975 DATE OF ORDER CUSTOMER'S ORDER NO, PHONE MECHANIC HELPER BILL TO c:J l-t~ 1? " C /,:>'-/ P CONSTRUCTION M AUG 1 8 2 OtJ liME: fl 0 \'EEMD BY;" -.:..b, ,QJ- ADDRESS CITY JOB NAME AND LOCATION ~f...,:.- ~ JOB PHONE ,--- .~---;-- 0/J ,/-- DESCRIPTION OF WORK: STARTING DATE "-1. '--'" '~ DA Y WORK CONTRACT EXTRA I fI7 " C, " Il I L/On? /) ;V - I j /,-, e /+ / G 0 /1/ I c.. /( ~ j r t>~~r / <:',/,- () r' /' / po hiP /J.."I-. I I 5 1""<:,' ..k/r, Tv ./ I )0'/ p c~ ;7 ,'7'/ . ::.:- c~. I" ~T.~ '<"/ / r', 1:1 " /0 'i/ (? j'- .,c' ._,n.-;.~ f . I A-t l_ '~ ,\ VJ tv' .>-- t S'Tr (r t I fJ ' . e(-1~J' r_/1PI61' . 6{r-J,' J ale U //4 I) tt t i I - ( TOTAL MATERIALS TOTAL LABOR T7 (,.. WORK ORDERED BY TOTAL AMOUNT $ J Signature' o No one home 0 Total amount due for above work: or I hereby acknowledge the satisfactory completion of the above described work, L TAX o Total billing 10 be mailed after completion of work TTG Security Work Summary date description from log 5/15/2006 Demo for security revision after sawcut- TTG 5/16/2006 Demo in sallyport - TTG 5/17/2006 Demo in GF block - TTG 5/22/2006 Rework -remove rebar GF cells - TTG 5/23/2006 Rework -remove rebar corridor - TTG 5/25/2006 Rework - holding cell SOG rebar - TTG 6/2/2006 Rework - control room SOG rebar - TTG 6/19/2006 Cut and patch masonary 6/20/2006 Cut and patch masonary men hours 3 3 3 2 2 2 2 4 3 10 10 10 10 10 10 10 1 o. MONROE COUldY CONSmlJCTION MANAGEMENT 10 AUG 1 8 2006 ~~~o ~r~ ---~jL--__ \ <D o (;)x ~LU <D 0) C "0 C LU ..>::: <1> <1> 5: o 0 o 0 o ci o 0 L{) L{) - - (') (') w-w-w-w-w-w-w-w-w-w-w-w-w-w-w- .?:- a 0 I"- \ 0 0 0 0 0 0 0 0 0 0 ..- ..- ~ o 5: <D 0_ -- x ~LU <D 0) c '6 c LU ..>::: <1> <1> 5: o N W-W-W-W-W-W-W-W-W-W-W-W-W-W-W- >. a .?:- ";:: ::J (J <1> (j) <.9 ~ ~ \ <D 0 0 0 0 -- - <D X 0 N LU 0 -- L{) (') 0) W-W-W-W-W-W-W-W-W-W-W- C "0 C LU ..>::: >. 0 <1> - <1> a <D 5: <D 0 0 0 -- x 0 (j) 0 ..- LU L{) -- L{) "'" 0) W-W-W-W-ff7ff7W-W-ff7ff7ff7 C "0 C LU ..>::: >. 0 <1> a (j) <1> 5: o o o o o (') W- W- 0 0 0 0 0 0 0 0 L{) L{) "'" "'" ff7 ff7 W- .!!!. 0.. 2 ro o(j (5 0 I~ .:a -- ::J 0 (j) 0 0 0 0 0 L{) 0 0 0 0 0 0 0 0 0 0 0 0 0 I"- 0 0 0 0 0 0 L{) 0 0 0 0 "'" L() 0 L{) L{) L{) L{) 0 0 N 0 I"- <D L{) N <D (j) (j) (j) ..- ..- L{) .,.... ..- W-ff7W-ff7ff7W-W-W-ff7W-W-W-ff7W- '- >. '- <1> 1::>- ro <1> '- E ~ ::Jo C '- t <1> <1> c ...... '- E ~ 0__ ro <1> 0 ~ <1> 0 ro .c 0.. <1> E 0 '- 2 ro Ci5 .c ro (j) if) 0 U ..0 ..>::: ..>::: o..Ex <1> -- .c '- ro ..0 c <1> u 0 if) E- '- 2 ro ..>::: 0 0::: ~ ro 0 ro ::J6:2 0 u LL LL -1 .Q 0 ~OJ E <.9 0.. OJ <1> ('") 0 C0 JoQ8l 18U8j8l^J juewdmb3 o o ci o L{) (') w- MONRUE (;!JiJlll) CONSTfU/CTJON MANAGEMENT AUG 1 8 2006 iiME: 1 .~B'~___~~_l! o o ci o o ..- W- o o ci o o (') W- Ameriyan Cutting and Drilling Company, Inc. 2920 NW 22nd Terrace Pompano Beach, FL 33069 Ofc: 954-917-0240 Fax: 954-917-0250 Bill To The Tower Group 405 SW 148th Ave., Ste, 1 Davie, FL 33325 P.O. No. Job#0417 Quantity Description JOB SITE: 302 FLEMING ST., KEY WEST JOB NAME: FREE1vlAN JUSTICE CENTER JOB NO.: 0417 As per job ticket 97220,97211,97212,97213,97214 & 97215' 1 .. 16' x 2' x 8" thick tie beam solid concrete cut. 2.. 12' x 12" x 8" thick concrete columns cut. I .. 12' x 18" x 8" thick concrete column cut. All cut and removed. 4.- 6" x 8" thick sheer wall core holes drilled. 12' above finished floor. Various locations. 3 ..3' x T x 8" thick solid concrete door frames cut and knocked out, all in various locations of building. 4..6" x 8" block core holes in wall 12' above finished floor. I -- 3' x T x 8" thick solid concrete door frame, cut and knocked out. I -- 3' x 7 'x 8" thick solid concrete sheer wall, cut and knocked out. I .- 3' x T x 8" thick solid concrete wall & two 4' verticals, cut and knocked out. Completed cutting 3' x 7' x 8" door opening, cut and knocked out. 3.. 10" x 8" block core holes 12' above finished floor. 3 ..8" x 8" filled block core holes 12' above finished floor, 3 -- 10" x 8" thick concrete sheer wall core, I 4' above finished floor on 1 st floor, chipped out second floor slab. Thank you for your business, Invoice Date 5/8/2006 . Invoice # 19146 MONfiVl GltJfill CONSTftUcnON MANAGEMENT AUG 1 8 2006 71&BE 1.11 m : f\\ RECEnftO Fi'/; _~ Terms e Net 30 ~ Rate 7,935.00 ~ Project Freeman JusticeCtr, Key W... Amount 7,935.00 T.+M S..fc (L~ 1)\ ~ I OU ~b1g0:~ ,:----- --- \2:: \ .". i. - \~\ .~~\ \>~ \ r ic i" Total ~., -....... \ ~~ \ -- $7,93500 :Ii ;.(l/ ,~/I ~~ .If" h -"/e'''>'1 292p NW, 22nd Terr" Pompano Bch" FL 33069 The Concrete Cutting Alternative Emoil: ocdcconcretecutting@juno,com Website: concrelecuHingdemo.com Dode: 305.372.8878 Broword: 954-917.0240 ING & DRIL~ING ~~llmFr~~~: g~~:~~~:~~~~ COMPA ;Zl C. ,1 Fox: 954.917.0250 ....... // 1 ,~ ''?v"!-( L~')/C~I) v,';; I (,'"'7 // JA J!, ~ , y J'c?S CfT)' ERICAN JOB nCKET NUMBER 9'722.0 . DmO{~~ ,~/ 1/ '. /AVh 'O'N<.- Day NEAREST CROSS STREeT OTHER MEN ON JOEl SAME DAY 2 3 / J I "~ ,~-..! 4 ~') 5 6 7 8 9 10 11 12 /;;/y;;;)1 ,\Ai!(t:' }~~/::;:'(.H ~Fir I') if> 'l OM ;,.0,,*,)'l:-'.,,.ijf.:^' ,. ~ ~ go)'/ e._-t.b_,,t./., ,Ice,] / i(// / l.. .' ~ ,>-<-_-F J,- 1...__ f,L tJ ", Q.", r1' ~ r _~J"_\ ':, >: ~"y.i:"'~ v~ 1"'<> It'" ,"""' (, ~ :>~, :~ <'''. I. $ "'1v" ~ /ji''-i''~~ "".:~ ~"J V"':'( ,d~:~ ,,? ~,,::tl(:.: ~ *::1dl~ ~ ~ ':! .. ,it'::":i." .y::- ~ ::. ~r-y."';< ~%(~;..Ji_'rft:<;':'-~ x.". <>......': . t[/':..."1,-'t/"~) c"...;J .-1:.' / .,1...>-/ .' r::~ (:;~ F:~ t... jt\~~:~r:(::{r,J'l'~ - i~::} r~t - "il. -~.1 ,') "/.5- ]' 1;"7 "" . f L! ' 1vlnL f3.UnH2D 1JTHj'Y'lES.-td,.1 ,.f-:t;!,,) ,lie: ,MS: NET 30 DAYS payment is due upon presentatlol] 01 Invoice, If any Invoice is not paid in lull will1in 90 ~~r' ~~er Its 1;1"ln<;) dar.. theCustome7h;,reby egrees to pey Interest at the rate of 1.5'10 per rnonth (18% per annum) upcn the unpaid portion 01 the Invoice, If eny action or suit is broughlby American Cuttin!1 & Drilling Co,. Inc, to collecl any amounl due 0< owing under Ihis bill, Customer agrees to pay all costs of colleclion Including reasoneble attorney's fees, WE ASSUME NO RESPONSI81L1TY FOR LAYOUT OR BURIED UTILITIES, JOB RELATED STANDBY TIME IEXPLANA TION P.O. ..... '....~_.t : , ., _r/ ;.'J' TOTAL HOURS ( . /) I . ,I / C"./ /}!~ B1'RUCK POWER USED [2t/TRUCK WATER USED D OVERTIME WORKED I j. ,/ -. // I ,:i/..yt~/ ~'..';>~?"~:;~:'t>:/,,'o-"/ l;UMPANY , JOB NO, :' ': ! x .....'-r..r._>--......~~.~-\ .,/It .-'~. .' - Af..;KNUwLc'WcU /' '~i . \ 2920 NW. 22nd Tarr., Pompano Bchj>fL 33069 ._' The Concrete Cuffing AlteiilaliV"er" ." ~ Email: acdcconcretecutting@juno.com . Website: concratecuttingdemo.com Dade: 305.372.8878 Broward: 954,917.0240 ING & P~Rll~I_NG ~~irFr~:~: ~~~:~~~:~~66 COMPf-.....V, I ,C. A .~ Fq' 954-917.0250 /1. < ) ~.J 0/ /i / /Ie . Z1./"'-1 '-'--'" /VVU ' ER leAN JOB ncKET NUMBER 97215 / /" OArcd~ ~~1/ oc / / ,4"/ / / ~/;/,<l~/ Day,,' / NEAREST CROSS STREET OTHER MEN ON JOe SAME DAY 3 4 5 6 / . '--r"'V f:)[ .~(:) fl t: :~~) r~ {:} ]\g ~};. ~ &3 ~ t." ~ ~l~ '\1 (/ 7 8 9 \0-<- ji i)1 " '-;/1 ; ; t"j r:::' <:) ~::::1 l~~ ~t~~.;\r. <::~ LJ ~'r; {:): JFl . 1/, ./"~ ...."'~ ...~; /f . "', '"i /-/. L \) 10 ", 11 ," B U H! E D UT~ L ~'ri ES,t./;{ ..~/ -'.' . ".'-, //:;_~~)-i..> " . .-' - ,~~ ... "'/Y~'~"-, /{ . \ )MS: ~,ET 30 DAYS peymentlsduQ upon presentellon 61 Invoice. It any Invoice Is not p~ld In full WlthiA'9Odtys aftar Its bill.n9 d'a~~h9reby agrees to pay Interest at the rale of 1.5% per '~-m"onlh (1 a~. per annum) upon the unpaid portion of the Invoice. It any action or suit Is brought by AmerlcanCu)tfng & Drilling Co.. Inc. 10 collect any amount due or owing under this bill, Customer agrees to pay all co$lS 01 colleclion IncludIng reasonable attorney's fees. WE ASSUME NO RESPONSIBILlrf FOR LAYOUT OR BURIED UTILITIES. JOB RELATED STANDBY TIME rXPLANA TION P,O: JOB NO. " ii'> ct-t\ f ,TOTALHOURS( /J /~::':::R~:~ . ,,:it" >.,;'~ /'./-( ')'"_/~::_" '~7:~j>,,'1 ,/;~:~:"::"~:"'C>.,i".// '.,/ A(;KNUW'Lt:l.Xit:U CCJMt'ANY . . ,/ x 292~0 NW,22nd'Terr" Pompono Bch" FL 33069 The Canaele Culling AllemaliVlJ"'C" Emoil: ocdcconcretecutting@juna,cam Website: concretecuttingdema,com Dade: 305.372.8878 Broword: 954-917.0240 Palm Bch: 561.832.8777 Toll Free: 888.289.5300 Fax: 954.917.0250 JOB OCKEr NUMBER 97214 II / //~6 CATE NEAREST CROSS STREET OTHER MEN ON JOe SAMEOA." 2 3 4 ,/ -;,,) ( \.. ) 5 .-/'~;./ ~ I~. 6 7 8 ,'(~ 9 ... ., 10 / . 7:rr/ ..::7:)':.s7' !.:\, j i 1 ....j ~ } ~ --frl , . ft." '"r~f ( {~, 11 u ()~; ~.:? -~~'-, ( i l'~: , EHJFHED UT~Lf"r~ES:::/oj//1"/,~'7.'o~;' ,; " --- -.-". - - . , J \, )MS: NET30 DAYSpaymonll. due uponprasentation of invoice, If any Invoice I. nolpeid In full within 90 d~'after 1.ls billing dale, the Customer he7ebyegreas to pay intorest slthe rate of 1.5'/, per '-e.TTfonth (18% per annum) upon Ih. unpaid portion ollhe invoice. If any action or .u~ Is brought by American Cuttlng"& Drilling Co., Inc, 10 collect any amount due or owing under Ihls bill. Cu.tomer agrees 10 pay all cosls 01 collection Including raasOf'able attorney'. fees, WE ASSUME NO RESPONSIBILln' FOR LAYOUT OR BURIED UTlUTIES, JOB RELATED STANDBY TIME lEXPLANA TION P.O; ,\ d {~ I Q--f~~CK POWER USED f2:r~RUCK WATER USED TOTAL HOURS ( f~/) )2] OVERTIME WORKED ''-/J1f.:,:C)(~V.''-f ,,' :/;/~;,v.~J,';;e,--' L;UMI-'ANY - . ',~ """.:'...........;/ i</ JOB NO. ;:)ti ~ ...'! x ! "..\ j./ _-c,.'f' ~ t \ ./.h ;,', (~ ' .r,,,.4 A(.;KNUWLcWcU 2920 N.W. 22nd Terr., Pompono Bch.. FL 33069 The Concrete Culling AlterffatiYb""" ~ Email: acdcconcretecutling@juno.com Websile: concretecuttingdemo.com Dode: 305.372.8878 Broword: 954.917.0240 Palm Bch: 561.832.8777 Tall Free: 888.289.5300 4. Fax: 954-917.0250 /1, V. :J '~7)i:;,h(-I CITY JOB nCKET NUMBER 97213 /' I CATE 0;(7/ G~k) , / / Ir:ks~/ Dey / N~AEST CROSS STREET OTHER MENON JOe SAME CAY 2 3 4 5 6 1/) 7 8 9 10 11 {::Jr- F:~~ ~, !':J: ':'7.- ,I r.'~ r?t tJ r~~~ ~ E:O **~~f;*ili r^'i~~:.:~~:(~l:, ~('. " . '4'1 / /~~ ..J ~ H__ 1 n;:;><::J</q)//; ....,.ir.'iY,L.U ~" I. \, \ MS: NET 30 DAYS paymant I. due upon presentation of Invoice. II any invoice I. not paid In full within. 9(rd~Y' aher ~. 6i1nn dare-:ffiil't;iTslomer nereby agree. to pay Intere.t at the rate 01 1.5"1. per' ~-n1tnth ('8% per annum) upon the unpaid portion olthe Invoice. II aey action or suit is brought by American Cutting & Drilling co..1nc. to collect any amount due or owing under this bill. Customer agrees 10 pay all costs 01 collection Including reasonable sltorney's lees. WE ASSUME NO RESPONSI81UTY FOR LAYOUT OR BURIED UnUTIES. . JOB RELATED STANDBY TIME P.O. \. '\ ,'(~ ~''1'1' p J I '-./, _.""'.f)" \ ... ,...', ',.' At.;"KNUWLI::WI::U B'-'TRUCK PO'NER USED UTRUCK WATER USED ;D OVERTIME WORKED ,/1 .4/ ,~ '. _ ~,. _ ."'.;Y _. _ . /di,.~A:',f ":__::')/{j;)~/l f .. {.;UMI-'ANY ; _'0' EXPLANATION I' ! A " i i 1 7'/ fTOTAl HOURS ( ) ~'--.--., / , /'J ,~ \ . .. " " -..... :'- \ \, ~ /, --- l JOB NO. r,1 "'i 1 - i x ..", -:;~lr~~~~ ----------,------~~~~-------.'_._-----------~-- --- --" '/ ~J^f /f f,~ " I./}" ~ '';'rt/1 n JOB ncKET NUMBER 972j.2 _.~--- OATE /)j' / NEAREST CROSS STREET OTHER MEN ON JOB SAME DAY 2 3 4 /0 5 L.:-S-rL 6 7 8 9 10 11 ~-,/J' TIME: ,:1 .. "''',_;-.: ~,.:....- . T' :r:'.. " ",W, ;""~ $"~ /.'<' f'" ,""", .. ~ if'"" '! 1(") I \ ~ ,.".,.. f r:{~ {,.~J ?,..::; t:: ~;::~ t.~: \~) ~\~ t;) ~ f:';~ ~ t.., ~ ~ '~~ fl~"-)? /.:;- / (2 ~.... ij,<b jtC /1. ,A. .Jj~, /J ;q--P V -c;."..-'i), /67':;;4,.;..., f <y J'1j~{&; F1 L A":t t..,J 'l~ ~~::} ~ :t j) I I h Ji I ,t't (1"#'1 .'"/ ...., . ~ l.- l-. ~."-) 12 / '" '\ )MS: NET 30 DAYS paymenl i. due upon presenlation pi Invoice. ,If anylnvalce Is not peid in full wllhinllO~s affer ils blm;;{aarf Ih;cu.;oi'iie11iareby agrea. 10- p~y Inl8r8.1 allhe rale of 1,5% par "-nionlh (18% per annum) upon Iho unpaid portion 01 the Invoice, II ery action or .u~ Is brought by American Cu.tl.,g &. Drilling Co" nc, to coll""l any amount due or owing under Ihl. bill, Cu.tomer agrees 10 pay all costs 01 collection including reasonable atlorneys fee.. WE ASSUME NO RESPONSiBILITY FOR LAYOUT OR BURIED UTiliTIES, t:~} tJf~l~E D Lrr~ Lrr~ E$i~;..-:(!,/,7";")/;}j:/. '",---If JOB RELATED STANDBY TIME EXPLANA TION ! ! /i ; > c \ /1 [}-rRUCK POWER USED S-':;UCK WATER USED [] OVERTIME WORKED I ,,/ /'~' ~'l.'~~~,.I./.,.,,__;~.,,_.. ", .." I .(' ., .". ~- ~~ - ~, . ->-(. () ~ ,-- ,'---.' ~UMPANY / i ,~ t'~--'-i-..,. \ I ,/ JTOTAL HOURS ( // ) P.O. , f, ,,- JOB NO. ;: ) '-j ; i I I x I \ \ i,/ /,rj /; .Ill: !l ~~'-~' } .f...... .,.,., t ._' - A~KNciWt.t:u<iC;u .' j.f"/f/;~ ~.::') . 29.;0 NW. 22nd Terr., Pompano Bch., Fl33069 The Concrete Cuffing Alfef'ijlilivi"'" . Email: ocdcconcretecutting@juno.com Webite: concretecuttingdemo.com Dade: 305-372-8878 Broword: 954-917.0240 Palm Bch: 561-832.8777 A Toll Free: B88.289.5300 //j' Fax: 954-917.0250 ,; /r) j '...___/ /C...-i/U \" <~~",? JOB TICKET NUMBER / / /.l,/r2/x.i1/ Day 97211 NEAREST CROSS STREET OTHER MEN ON JOe SAME 0,\ Y ~-1/'./] 4 _-:"J -;/' 4/ V'dF .: <:L~J ~A.i~F .'>' .. ;...., . ?J':J"7o'/.,' ).... ~ ~ ~ ?'J , / --y~ !C/ ..r- . / ~<'~'f /.-/Y::/~{~ j."i./'-T /').y.) ~/~/( /~. ,-J,r::).!;{.'>d 0/ .~.;; 3 5 6 7 (-.I;; .~.7C 9 (-:. -;~J:::' (~V'13~ t l\ 'f {) LJ T' A.:.....:- ;:-.''::... (..i{,':[ , I / l";iii{ j ,.' l:cA "'-, ,-- .'~,~ -JJ -;' l ( ~. 8 10 11 ... " I r;~ ~ ~.~ f).". ~,t.,:::::: f;'''~.~ ~~ ~ ~r' ~:~ *- -;'-'1'>;~: t"" e~ .... jF ': _ f J~ /~ J 1 2.. ". ~....->"" :~...J ~ *;.. M.-.... w.. t,} :; ~~;,..... ~ ~ ~ C..'~ :".,'::10 /" /i.r -~/~' ;,.-~~>;./ i' _ ~' 1- .z '" )MS: NET 30 DAYS payment Is due. upon presentetion of invoice. If any invoica .1. not peid in lull wlthin.9O 'jat. 'a~E'lili;;ngd;;it1nQ-Ctnl!Oi'ifa'rlfernbY 'agrees to pay interest at the rate of 1.5'-. per '-mOnth (18% per annum) upon the unpaid portion 01 the Invoice. It ary action or .Ult " brought byAmerlcen Cutllng & Drilling Co., Inc. to collect any amount due or owing under this bill, Cu.tome, agrees 10' pay all costs of collection including raasonable attorney'. faes. WE ASSUME NO RESPONSIBILlTf FOR LAYOUT OR BURIED UTILITIES. JOB RELATED STANDBY TIME EXPLANATION ,f A < i \ /i TOTAL HOURS ( ",f, ,.....- i , ! / 1 // .... - ...\ ~ , . '" - ~-- r:f ~~UCK POWER USED [~r~RUCK WATER USED [3' OVERTIME WORKED ... -..-/ ./1 P.O. JOB NO. ,!"\ i ~ " ~/ '...'~ '-! X I " i J 01., , "\ t/ /.; rl //1 # \ ,,~ ,,/'.,~ .,.... \.. J _""1 --_/ AGKNUwCt:UUt:lJ -.~." /,,- /./ /":" ,/ /C:'~'i/'J I \;U'MI-'ANY _/.;\~J' C): ;/ !lilateh 17,20062:21:13 PM EST / / 1,8~33S4153 QUOTATION JOB ~~ D QUOTE NUMBER 94065 The Concrete Clitting Alternative ERICAN ING & DRILLING COMPANY, INC. Dade: 305-372-8878 Broward: 954-917-0240 Palm Bch: 561-832-8777 Toll Free: 888.289-5300 2920 N. W. 22nd Terr. Pompano Beach, FL 33069 Fax: 954-917 -0250 Emall: acdcconcretecuttinQ(!Iliuno.com Webslle: concretecuttlngdemo.com COMPANYNAMI::: THE TOWER GROUP STREET ADDRESS: 405 SW 148TH AVENUE S-1 CITY, STATE, ZIP: DAVIE, FLORIDA 33325 PERSON REQUESTING BID OFfiCE PHONE NUMBER TIM CLARKE 954370-5400 DATE QUOTED I QUOTED BY OFFICE FAX NUMBER 03-17 -06 JUAN PEREZ 954 370 5401 (4) (2) (12) (1) (1) . ~ .. .. ~ JOB ADDRESS 302 FLEMING STREET JOB NAME FREEMAN JUSTICE CENTER NEAREST CROSS STREET WHITEHEAD & FLEMING JOB PHONE MOBIL 305296-2521 305986-4163 JOB FAX NUMBER P.O. NUMBER 305 296-2587 PAY REQ REQUIRED DYES WORK LAID OUT BY CUSTOMER WHERE TO MEET r_'al- ... ..... .. A-N-E ex: CITY KEY WEST MAP PAGE PAGER JOB NUMBER 0417 PROJECT NUMBER o NO GENERAL ON JOB JOB START CATE CAY & TIME AMERICAN CUTTING & DRILLING COMPANY, INC., PROPOSES TO SUPPLY ALL ~ LABOR TOOLS, EQUIPMENT AND INSURANCE NECESSARY, TO ACCOMI?LISH T ' Iw,. FOLLOWING SCOPE OF WORK 01: CUT AND REMOVE TO THE SIDE FOR CUSTOMER'S DISPOSAL $ 500 $ 800 $ '80 $ 150 $ 1250 3' X 7' EXISTING DOOR FRAME TO BE CUT OUT AND REMOVED FROM OPENING. NO OVERCUTS 3' X 7' X 8" THICK SOLID CONCRETE WALL OPENING FLUSH AT BOTTOM WITH NO OVERCUTS. 6ft DIAMETER CORE HOLES THROUGH AN 8" THICK SOLID WALL 12' HIGH OFF CUSTOMER'S SCAFFOLDING. 12" DIAMETER CORE HOLE THROUGH AN 8" THICK SOLID WALL 12' HIGH OFF CUSTOMER'S SCAFFOLDING. 16'6" LONG, 24" HIGH BY 8" THICK SOLID CONCRETE BEAM WITH (1) 36" WIDE WALL SECTION TO CUT BELOW GRADE AND CUT OFF 12" FROM THE RIGHT SIDE OF EXIS- TING OPENING TO PROVIDE A FINAL OPENING OF 16'6" W BY 11' HIGH. NO OVERCUTS ALLOWED. "PRICE BASED ON ONE MOBILlZA nON WITH A $ 500.00 TRAVEL CHARGE, $ 250.00 HOTEL CHARGE PER NIGHT AND $ 45.00 PERDIEM PER DAY. (5) DAYS TO COMPLETE $ 500 $ 1250 $ 225 "ALL LAY OUT PRIOR TO SCHEDULED ARRIVAL, ACCESS FOR TRUCK, EQUIP. ENT, OPERATOR, REMOVAL, DISPOSAL AND FINAL CLEA BY THERS. ACCEPTED BY DATE ~/ ~/1J " WE ASSUME NO RESP0NSIBtllTY FOR LAYOUT OR DAMAGE TO BURIED UTILITIES PRICES SUBJECT TO CHANGE IF CONDITIONS ON JOB \I ARY FROM THIS QUOT ATION NO YES WATeR AVAILABLE 0 I3J 100 DISi IN SlOE WORK POMRAVAJlABLE tSl 0 _ D'Si O~RT1ME NECESSA~Y OUR SCAFFOLDING tSl 0 HEIGHT VACUUM REQUIRED HEIOHT OF WORK :u.: FEET PLASTIC & TAPE TRUCK TO WORK AREA 2Q.: D1Si EXTRA MAN REQU1RED ST ANDBY TIME WILL BJ CHAR GED AT S 125.00 PER HOUR PER MAN Frid<1.v. Match 17. 2M6 2:21:13 PM EST NO YES I ACCESSlllllm o I 0 STA.ft.s 0 LADDER 0 BUCK 0 E1.E'W 0 ~LANKS 01 o I SPECIAL EQUIPMENT REQUIRED 00 1~~'~~~TSAWTiT/!C <:;f-({);f(fY It tf-y~o(n ~ I ' iI I -+ C'\'8 I . 'f'1'~ ~ r- l/ 1175:/ (;07 .&S (,Vt;].6) 3f'r~~~ &710- 53 ~ ~ ~ ~ ~ 18~33341~ ~ cp~ $ 2000 :>u.ti'/( $.1600 $EC.tre! $ 960 ' $ 5ob-. $ 1250! : $ 225 ; $ 7,935.00 PERQUOTE WI..$TE MANAGEMENT Customer: Acc:;ount Number; Invoice Date: In"oice Number: Due Date: WM ezpay Account 10: I4J 003/003 Page 2 of 2 THE TOWER GROUP 990-oo12556-109~ 06/16/2006 0183994-1096-6 Due Up<Jn Receipt 00012~11315.52001 _ ~17/2006 10; 56 FAX 9544242510 THE TOWER GROUP '''''''. W~ Management of It' . ,rids KeYs h,,_)pp1no Industrial Drive KeyVl.'est FI.. ~S400 _~"""'i:L~~~~~~~~-~~ Date Ticket ~ . . Quantity UIM Rate Amount ~/06 75390 20 Yard r.olloff 1.00 461.70 06I0E./06 75517 20 Yard rolloff 1.00 461.70 06/1(.106 75812 20 Yard rolloff 1.00 461.70 06/1 N06 1 ,00 Fuel !urcl'large 1.00 135.72 Total Current charges 1.520.82 . MONi~;Vt c.;.", III . CQNSTftYCTlON MANAGEMENT AUG 1 R LULo \. I ! r' ! "1 \., nME: RECEIVro BY.. -----.-..---~ I \~../ . ~ ,-~ ..-'.- ~_._._- -...--'. ._----~_. ..~ \d A. L.,J.pnml.!tJ on Rcayt:It'U f':lpn r. ')070 MEMORANDUM TO: Board of County Commissioners From: Thomas J. Willi County Administrator Date: September 21, 2006 RE: Change Orders Attached is a proposed change order for The Tower Group, for the Freeman Justice Center. (Change Order #19 in the amount of $37,288.84 is for Time and Materials for the completion of the Security Upgrades not included in Change Order #12, This includes Patchwork, Coring, Cutting and Chipping.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. i9 The Administrator intends to approve this change order on Friday, September ~ 2006. Thomas , illi County Administrator TJW: ode Page 1 of 1 Cyr-Connie From: Cyr-Connie Sent: Thursday, September 28, 2006 5:04 PM To: County Commissioners and Aides Subject: Change Orders Attachments: Change Order #20.PDF; Change Order #19.PDF Please see attached. Connie Cyr Aide to the County Administrator The Historic Galo Cigar Factory 1100 Simonton Street, Suile 2-205 Key West, Florida 33040 Office 305-292-4441 Fax 305-292-4544 Gyr:-J;~Qnni~@mQnfQ.~GQJlnty~t1,gQY HELP US HELP YOU! Please take a moment to complete our Customer Satisfaction Survey: http://monroesurvey.virtualtownhall.netlsurvev.lJhp ?9acc 14ael b Please note: Florida has a very broad publiC records law. Most written communications to or from the County regarding County business are public records available to the public and media upon request. Your e-mail communication may be subject to public disclosure. 9/28/2006 , I MONROE COUNTY / ENGINEERING /FACILITIES DEVELOPMENf CONfRACT CHANGE ORDER PROJECT TITLE: Freeman Justice Center Jackson Square Key West, FL TO CONTRACTOR: The Tower Grou~, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 CHANGE ORDER NO: 20 INITIATION DATE: August 18, 2006 CONTRACT DATE: June 16, 2004 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price) .................. ... ...... ............. $13,804,000.00 Net change by previously authorized Change Orders ......... ............ ... '" ...... ......... ...... $1,089,937.32 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ......... $14,893,937.32 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ................. $ 57,500.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $14,951,437.32 The Contract Time will be (increased) (decreased) (unchanaed) by.................. ( ) N/A The date of Substantial Completion as ofthe date ofthis Change Order is ......... ... ... ...January 25,2007 Detailed description of change order and justification: Install Vulkem 350R/351 watemroofina behind stone claddinG and brick facinG in two coats. Cost $90.000.00 profit @5% 4.500.00 Total for entire buildinG $94.500.00 Credit from Southern CaulkinG & WatemroofinG orevlouslv uo to 20' 37.000.00 Total ChanGe Order $57.500.00 This includes all associated costs relatinG to the exterior wateroroofina and commetes this item. This ChanGe Order is .416%( the oriGinal contract amount Not valid until sianed bv Owner. Construction Manaaer and Contractor ARCHITECT: N/A 1l1~ i/ ~ /5/0~ Date CONTRACTOR: The Tower Group DIRECTOR, FACILITIES DEVELOPMENT: J COUNTY ENGINEER: .]!~oL / COUNTY ADMINISTRATOR Change Order Attachment per Ordinance No. 004-1999 · Change Order was not included in the original contract specifications. Yes 121 No 0 If Yes, explanation: This Change Order is for waterproofing for the brick and stone that was later added to the specifications. · Change Order was included in the original specifications. Yes 0 No 121 If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes 0 No [8J If Yes, explanation as to why it is not subject for a calling for bids: . Project architect approves the change order. Yes 0 No [8J If no, explanation of why: The Architect is not requited to approve Change Orders for the Freeman Justice Center. . · Change Order is correcting an error or omission in design document Yes ONo [8J Should a claim under the applicable professional liability policy be made? Yes 0 No [8J Explain: o~/ -?1I 2006 16: 39 FAX 954 370 5401 UNITED ENGINEERING CORP. 141 008/01 The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954)474-311 I CHANGE ORDER REQUEST No. 00052-A2 TITLE: Waterproof for Brick/Stone - Alt. 2 DATE: 8/18/2006 JOB: 0417 CONTRACT NO! 1 'Monroe County FOCllltles Development PROJECT: Freeman Justice Center (FJC) TO: Attn: Clark Briggs Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax; (305) 295-4321 Aue 21 2006 RE: pca To: TTG From: SC&W Number: SCOOIR2 DESCRIPTION OjfPRo.POSAL. " '.. ,.'. ", d':' , Change Order Request (COR) #52 addresses the costs and time for the extra work to include waterproofmg behind all the brick and cast stone cladding, from grade elevation to the tops of the parapets. COR #52 includes waterproofing between grade elevation and Elevation +20'-0", which was included in our original scope of the Contract Work but proposed for deletion in COR #18 to facilitate cost analysis of alternate waterproofing systems. This proposal, COR #52-A2, is Alternate #2, and based on Southern Caulking & WaterproofIng's (SC&W) Proposal #SCOOI-R2 to utilize the Vulkem 350RJ351 two-part waterproofing system by Tremeo applied in two coats as recommended by Dan Kennedy of Tremco (Re: August 17, 2006 e-mail from Dan KennedylTremco to Hank GoldmanlCSA Architects, copy attached, 1 page), Unlike the Contract-specified Vulkem 201 waterproofmg system (Re: ITO COR #52-AI), the Vulkem 350R/351 system does not require parging or multiple mobilizations as it is a UV-resistant product. The attached Schedule (P3 Filename F24A) is our July 2006 Schedule Update (P3 Filename FJ24) modified to remove the sequencing and constraints of the Contract-specified waterproofmg system and replace them with the sequencing enabled by the Vulkem 350R/351 waterproofmg system: all "parge" work Is deleted, all waterproofing is performed in a single mobilization, and brick/stone work is sequenced to prioritize window casing installations, The modified schedule demonstrates that the brick and cast stone cladding work will be eight (8) work days removed from the critical path to completion ofilie Project. If the Owner and Architect prefer Waterproofing Alternate #2, Vulkem 350R/351 by Southern Caulking & Waterproofing, then please process a Change Order to increase the Contract Price $94,500.00. Provided that the brick/stone contractor prioritizes the cast stone window casings to enable the earlier window installations afforded by the use of this waterproofing system, there is no Contract Time Extension associated with this work.. nME: RECEIVED BY: .Pv Item 00001 " Description , . Stacie#' Install Vulkem 3S0Rl3S1 behind stone cladding and brick facing in two coats (SC&W Proposal #SCOO l-Rl) QuantttyUJlits ' 1. 000 LS , UnitPrfce $90,000.00 Tax Bate Tax, Amount Net Amount 0,00% . $0.00 $90,000.00 Unit Cost; Unit Tax; Unit Total: Subtotal: $90,000.00 $0.00 $90,000.00 $90,000,00 Description Profit , , lVlarkupPercent. Markup AlUtJunt 5.000% $4,500.00 Total Cost: $94,500,00 0&/21/2006 16:40 FAX 954 370 5401 eS/86/2Ba6 23:19 9543468685 UNITED ENGINEERING CORP. l4J 010/0J ~&~E 84 'SOUTHERN CAIlLK1NG & WATERPROOFING. INC. 7546- West McNab Rd" Suite B25J NOrth LauderdaJe~ Florida 33068 (954) 34i-9717 -Fax (954) 346-8605 5 C:'COI ~2.... Monroe County Facilities Development 08107/06 Tower Group 405 S W 14Slb Ave" #1 Davie, FL 33325 Attn; JOM Chandler JOB: FREEMAN JUSTICE erR, #3 TIME: RECEIVED BY:_ AUG 21 20J6 , PL Dear Mr, Chandler, .. Soutbcm ~uJkin8- &: W8terp~fing, ~. (Sea: w, Inc.) .is pleased to quqte you on the above referenced ,project. We propose to furnish all labor, materials and equipment necessary to complete the scope ofworlc outJined below. Specification No,; 07100IWaterproofing Scope of work proposed is as folJows: 1, InstaU~;cOBtSVu.~em #350-#351 Waterproofing behind stone cJadding Iii: brick lac't. . ,- Note - Vulkem #350-#35J. WatC%pt'oofing has ultra~violet protection in the top coat oithe material. There would be )10 problem with exposure time & the building could be done aU at one time. - TOTAL COST OF JOB: $90.000.00 MATERIALS: Vulkem #350-#351 WatetproofiDB if Work deemed aece...ry by t.ll. eOlltracior or OWDCr and dot .li5tcd .peei8adly in tile price breakoub will b. ... ..In to Ibe ...f..I...tnet ......L A.,.requeat t.r est.. ",.rk must be ..b..ilted I. wriU.g I. sew.) lac. prior to ,COmmencement or ea... work. Set w~ Ine, will W&.n'aoty oW' labor and materials fur ' the period l'equired in Lbe spcciticatktn documents. SC&W, Inc. hereby reserves the right to submit Ii revised proposal if the above is not accepted within 30.Days ofth.e above date, :.. DAElru Accepted By: Title: Firm Name: Date: t'HERNCAULKING & WATERPROOFING, INC ,6 West McNab Rd., Suite 825, North Lau&rdale, Florida 33068 .954) 341-9717 -Fax (954) 346~8605 ~~~ 07126/0(; , Monroe Cou tv FaCl/Il/es Deve/on , " pment T ower Group 405 S W 14SUl. Ave., # 1 Davie, FL 33325 Attn: Job.."\ Chandler '::iMo .:~G(!:} , ~ JOB: FR.EE~rA..N JUSTICE CTR. Dear }off. Chandler, Sbuts,;rn C~6 \k U1g &: W ~erproofiog.lt>::,(SC&: W. Jm::.) is pleased to qllbt. )"U on the alx> '" ;ef.,r,nc:ed 'project. We propose to furniSh alll.abOr, materials and equipment ~essa.ry to complete the scope ofwork outlined below., ' "," ", ,,'0' " ", ,"...," ", . .' .--"";.- , . , .... ....... ~ " ..~; . ;. .~'~ ". ';. ".; 'Specification No.: 071 OOlWaterprooficg . '" 0 , '" , ---; c J- () -$'29,090:00 ,~.v. ~ . 8,000.00 .,_., 'i ~:-; :'.' :}.::, ~,"" ';; , ..~ . ,'. 7.. ~. "ScopeofworkProp1sed~as, foUa'W'S: :' ; l.~ oe'1ete Fluid APT.llied Wat~Qofi.ng behind cast stone cladding. . ' 2.' Delete clear water rePeUent; coa:ti.og tocaststone c\a..dding. , q':, r, ';" . . . ,- .' ," , ,- TOTAL COST,OFJOB-:-S3,7,OOO,OO (.if ." . . MATERlALS: As per~s. ',:, . . :,",':"'> .,' co ." ;' , - , :""";10;.1;",,, 0<1. ~~ri I;>y iii 0 "".l,jet. r ,0 row. or a. d "olu..ud .podlicaUy iu Ib 0 P rle. bmkou.. will , ","be; a" oit~ t9 !~', ~rI~i".].eon fr'aci ~';;,o..~ i,j.oy r<<I u est for es,n ....orle. m o.t be rob inilted lD wrlliJI ~ to ; . 'seW ..,111c. prjo~to,"~!:Dme.c:t::m9t,o! at,.. 'tVork.. SC&:.W. Jnc.,wi11 wuranty our labor and mate-ria!sfor , . tho' p.mod~ub: ,d in the spec ificatlon do<;uicerits, 5 C&: W. [ne: hereby _rves the right to submit a, rev;is<:d' 'proposal if the above is not ~epted within 3D-Thiys oftbe above date. '.. :.. :.. :.. :.. :.. DAZ-n' Title: r\ccepted By: f i.rm 'Na roc: Date: The Tower GrouPJ Inc. MEMORANDUM TO: Board of County Commissioners From: Thomas J. Willi County Administrator Date: September 21, 2006 RE: Change Orders Attached is a proposed change order for The Tower Group, for the Freeman Justice Center. (Change Order #20 in the amount of $57,500.00 is for Installation of Vulkem 350R/351 waterproofing behind stone cladding and brick facing in two coats.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. .1.'1 The Administrator intends to approve this change order on Friday, September ~ 2006. ~~ Thomas J iIIi County Administrator TJW:adc Page 1 of 1 Cyr-Connie From: Cyr-Connie Sent: Thursday, September 28, 2006 5:04 PM To: County Commissioners and Aides Subject: Change Orders Attachments: Change Order #20.PDF; Change Order #19.PDF Please see attached. Connie Cyr Aide to the County Administrator The Historic Gato Cigar Factory 1100 Simonton Street, Suite 2-205 Key West, Florida 33040 Office 305-292-4441 Fax 305-292-4544 cyr-connie(ciJrnonroecounty- fl.gov HELP US HELP YOU! Please take a moment to complete our Customer Satisfaction Survey: http://monroesurvey.virtualtownhall.net/sunJev. vhp ?9acc 14ae1 b Please note: Florida has a vel}' broad public records law. Most written communications to or from the County regarding County business are public records available to the public and media upon request. Your e-mail communication may be subject to public disclosure. 9/28/2006