Item J2
BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date: December 16. 2009
Division: Growth Management
Bulk Item: Yes ~ No
Department: Planning & Environmental Resources Dept.
Staff Contact Person: Christine Hurley Ext. 2517
AGENDA ITEM WORDING:
Approval of a two (2) year extension, retroactive to October 16,2009, to Rockland Investment
Corporation, to apply for final plat approval for Rockland Key Commerce Center subdivision.
ITEM BACKGROUND:
The Planning Commission granted preliminary plat approval for the Rockland Key Commerce Center
on Rockland Key on January 11, 2006. On November 17, 2009, a request by the applicant was
submitted to the Planning Department for an additional two (2) year extension. The applicant has
made substantial progress toward satisfying conditions for fmal plat approval, but needs additional
time to obtain necessary permits from State agencies.
PREVIOUS RELEVANT BOCC ACTION:
BOCC granted two (2) - one (1) year extensions to file for final plat approval expiring on April 18, 2008
and October 15,2009.
CONTRACT/AGREEMENT CHANGES:
STAFF RECOMMENDATIONS: Approval
TOTAL COST: N/ A
INDIRECT COST:
BUDGETED: Yes _No
DIFFERENTIAL OF LOCAL PREFERENCE:
COST TO COUNTY: None
SOURCE OF FUNDS:
REVENUE PRODUCING: Yes
No
AMOUNTPERMONTH_ Year
APPROVED BY: County Atty -2L OMBlPurchasing_
Risk Management_
DOCUMENTATION:
Included
Not Required_
DISPOSITION:
AGENDA ITEM #
Revised 7/09
.,/;rr-:- ".
I~':" "'1/1 '23 ._\\
t .' ' -. ',~ .\
t.,' - M-:-J
\.. . 'I"
~---~ .
~.;~ -/
,~~/
MEMORANDUM
MONROE COUNTY PLANNING & ENVIRONMENTAL RESOURCES DEPARTMENT
We strive to be caring, professional and fair
To: Board of County Commissioners
Through: Christine Hurley
Growth Management Director
From: Kathy Grasser, Comprehensive Planner
Date: December 1, 2009
Subject: APPROVAL OF THIRD EXTENSION OF FINAL PLAT
APPROVAL FOR ROCKLAND INVESTMENT CORPORATION, INC.
Meeting: December 16,2009
I BACKGROUND
The Planning Commission granted preliminary plat approval for the Rockland Key Commerce Center
on Rockland Key on January 11,2006. The BOCC granted two (2) - one (1) year extensions expiring
on April 18, 2008 and October 15, 2009, respectively. On November 17, 2009, a request by the
applicant was submitted to the Planning Department for an extension, which was verbally
communicated as being for two years.
The applicant is Rockland Investment Corporation, Inc. The development project is known as
Rockland Key Commerce Center. The preliminary plat was approved with specific conditions to be
satisfied before filing for fmal plat approval. The conditions included requirements for obtaining
necessary permits from State agencies and the provisions of fmancial guarantees and maintenance
agreements for infrastructure improvements. Applicant responded to a third Request for Additional
Information from the South Florida Water Management District for its permit. Since then, mitigation
has changed and additional survey work is required. The applicant is making every effort to fulfill
these conditions.
Pursuant to Section 110-98 (t), Limitation on Approval of Preliminary Plat, Monroe County Code, the
applicant may request an extension from the BOCC to request approval of the final plat. Unless an
extension is granted by the Board of County Commissioners, the approval of the preliminary plat is
automatically rendered null and void. Therefore, the applicant is requesting an extension to apply for
final plat approval.
II STAFF RECOMME~DATION
Approval of extension of fmal plat approval for Rockland Investment Corporation, Inc
Z104
SENT VIA FEDEX
November ) 7. 2009
The Craig Company
Comprehensive Planning
fiesortff ourism Plannmg
Land Use Regulallor
Development Feasibility
Site Design
Expert Witness
Mr. Townsley Schwab
Acting Director Planning and Environment.al
Resources
Monroe COllnty
2798 Overseas Highway
Suite 410
Marathon, Florida 33050
Mailing address: P. 0, Box 970
Key West, FL 33041-0970
Re: Rockland Key Commerce Center
Plat of Subdjvjsion Approval
Office loemion. 610 White St
Key West, FL 33040
Phone. 305/294-1515
Fax. 305/292-1525
E-mail: barb@cralgGOrnpRnycom
Dear Townsley,
On January 9, 2006, the Planning Commission granted Preliminary Plat approval for the
Rockland Key Commerce Center. This is a subdivision of property that is zoned and historically
has been used for Industrial purposes. Since the original Preliminary Plat approval, we have
requested and received three extensions due to 'the extensive regulatory permitting requirements
for a project of this size.
Although much of the required infrastructure is in place, the South Florida Water Management
District permit is still pending. In March we responded to the third RA[ (Requests for Additional
lnformation) from SFWMD. As a result of this process the requirements for mitigation changed.
However, another RAI was issued that required additional survey work and we expect to have
our reply submitted in early December. Until that permit is issued, the project cannot proceed
with the civil engineering work required to construct the storm water drainage system.
Furthermore. the changes to the mitigation plan have resulted in a shift of the driveway entrance
15' to the west. As a result, the FDOT permit is in the process of being modified. \Ve have
submitted all required plans to FOOT and are awaiting the US I connection permit.
As to be expected, gi ven the economic situation facing not only the Keys economy but our
nation as well, development schedules for new projects have been extended_ The Florida
legislature recognized this situation with the pflssage of SB 360. We respectfully request that the
Board Of County Commissioners grant us an extension to Sec. 9.5-84 of the Monroe County
Code.
I thank YOll for consideration of this request. If you bave any questions, please feel free to give
me a call. Again, we appreciate your help in this matter. Please let me know if you require
anything further.
\. \
i"" l.. "!
Barbara Mitchell, LEED AP
V ice President
Sincerely,
-~ (
! )r'"., J("I.. L
{L ': (.
Cc: Donald L. Craig. AICP
William Kemp
Steven Henson
Allen Perez PE
, .
F-
IX, ~- ~>'--, T.1..t. ~ ~Z104
/;/' ,f , '>.~
;/ I . ~ ;--
/...... .... r'
r., f . , u.A '" ) Comprehensive Planning
. anuar} '-1. ~(" i~ ~ . "14'... ~ I, ResortITourism Planning
! V J- l 2rJ. ' .' ,';' Land Use Regulation
Mr. TO\\ nsle) Sch\\ab 1.;':-1:, '4 -fed} <:\ ~1~f-,'," j/ Developmen~~:~~~~~
Actmg Director Planning and En\Jronm RI4!r. I '1 a / -""/ Expert Witness
Resources - J, ".' 'ibJ>.f
Monroe County -'. ,:_'" ,.:f:i) Mailing address: P. O. Box 970
2798 O\erseas-Hlghway -'-. 'J r. Key West. Fl33041-0970
SUI te 4 I 0 Office location 610 'Mute St
Marathon, Ronda 33050 Key West. Fl33040
Re: Rockland KC\ Commerce Center
Plat of SUWI\ Ision Apprmal
Phone 305/294- 151 5
Fax 3051292.1525
E.mall barb@craigcompany com
Dear Tonnslq .
On Januar) 9. 2()()(). the Planning CommIssIOn granted PrelIminary Plat appnnal Jor Lhe
Rockland Kc) Commerce Center. This IS a subdJ\lsion of property Lhat is loned and hlstoricall)
has been used for Industrial purposes. The reqUIred regulatory permllllng lor this site is
e\.tensi\c. We requested and Here granted an extension lor Fmal Plat appnnal last year.
Attachment I SummanTes 0/ Lhe status oj the regulatory pem1iLs that are reqUIred for this project.
It has ah\ ays been the intention of our client to complete the i nfra..tructurc prior to apprmal of
the Final Plat. Significant progress has been made to accomplish that goal. The \\ater mam hus
been e\.tended, the underground electric and communication Jines arc in place. the public sewer
and reuse water main lines ha\ e been installed and the preltminary site preparallon for the mad
system has been completed. A FDOT NOI (Notice of I ntent to issue a pcmli l) has been receJ\ed
for the US I access and dmmage modifIcations that are required.
Our engIneers ha\ c been \\orklng "jth South Rorida WaLer Management Distm:t for the O\erall
project dramage permit sInce September .2006. The Emjronmental Resource Permit (ERP) has
noL been issued and it \\ ill reqUIre. according to the latest correspondence. at least another YO Lo
120 days for processmg. The additional re,iew requires site mspections b) SFWMD r:x;rsonneL
Furthermore. the construction required for the dramuge system nill require at least si\. months
for completion. As u result, \\e are requesting an c\Lension for one year in order to ensure the
ERP has been issued and the \\ork commenced.
Upon rccelpt of the ERP, \\e \\ III submIt a complete application for Final Plat apprmal. Thus,
\\C respectfully request that the Board 01 Count) CommiSSioners grant us an c\.tensJ<m Lo Sec.
9.5-84 of the ,\;10nroe County Code. I appreciate your conSIderation of our request and look
forward to your response. Please let me knO\\ II )Oll reqUIre anythll1g further.
Slncere/y,
81Mb w"- }whAlLL( /,0tL
Barbara \l!itchell / j
Vice PreSident
C.:: Donald L. CraIg, AICP
William Kemp
Sle' en Hensnn
Allen Percl PE
Lt'b" \AJ04"f . O..O..-'-'.<;:).......'M.....o.
.
, '
.
.
.
Append!\: I:
ST A TUS OF REGULA TORY PERMITS FOR
ROCKLAND KEY COMMERCE CENTER
RNAL PLAT APPROVAL
ApplicatIOns & PenTIlts:
.
Rorida Department of Transportation (FDOT): DIi\'c\\ay Application 2006 A 692 17.
original submittal on IO!l8i06
F-lorida Department or Transportation (FOOT): Drainage Application #2(X}6 D 6928.
original submittal on IOII8/06
Rorida Key Aqueduct Authority (FKAA): Water Mam E\:[ension Permit # 1688-06
Issued September 20, 2006
FOEP: Geneml Use PenTIlt to construct extension of Public Water Supply Dlstnbution
System #268632-001-DSGP
Keys Energy: Underground Electnc & CommuOIcations Infrastmcture Job # ER 2882-
06 dated 4/2 1/06
.
.
.
.
Pendmg:
· South Rorida Waler Management District (SFWMD) Emrronmenta] Resource PenTIlt
(ERP) #060925-15, submitted September 16, 20C)6
· Monroe County Engineering Department: Ctxmlination is pending Final Plat apprmal.