15th Change Order 09/05/2023 MONROE OU / NGINEERING/ ]PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE': Plantation Key Courthouse& Detention Center CHANGE ORDER NO: 415 INITIATION DATE: 08/26/2,023 CONTRACT DATE: 12/13/2017 TO CONTRACTCOR: Eiltmore Construction Company 1055 Ponce De Leon Bllvdl. Belleair, Florida 33756 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)...... ........ ....... $32,818,441.14 Net change by previously authorized Amendments.............. ................................ $2,231,070.34 Net change by previously authorized Change Orders................................................... ($3,182,136.07) The(Contract Sum/(Guaranteed Maximum Price) prior to this Change order wa,s....... $31,867,375A1 The(Contract Sum) (Guaranteed Maximum Price)will be (increased') (decreased) (unchanged) by this Change Order................... $0.00 The new(Contract Sum)(Guaranteed Maximum Price) includiing this Change Carder is., $31,867,375.41 The Contract Time will be (increased) (decreased) (unchanged) by.—---................ 122 days The date of Substantial' Completion as of the date of this Change Order is ...... 07/31/2023 Detailed description of change order and justificatiow The County and Contractor had difficulties with getting the wastewater treatment connection i2ermit full approved and closed out with the Villa e of lslarnorada necessitating a titne extension. The substantial completion date has been extended from March 31, 2023 to July 31, 2023. Chancre order is 0.0% of original contract price. Not valid until signed by Owner Architect 'If applicable), and Contractor ARCHITECT. 8/25/2023 gyi.,r i S fards Aguila Arkliitects, Inc, [late r Bile ore Cnris"tFuction Company Coate i far, K n i g I,�� Digitally signed by Cary Knight Y DEPARTMENT DIRECTOR. t I Date:2023.09.05 08:34:36-04'00' Cary Knight Date Project Management Digitally signed by Kevin G. Kevin G. Wilson, P.E. Wilson,P.E. COUNTY/ASSISTANT ADMINISTRATOR: Date:2023.09.05 14:34:56-04'00' Doman Gastesi Date Kevin Wilson Change Order Attachment per Ordinance No. 024-2015 • Change Order was not included in the original contract specifications. Yes Z No El If Yes, explanation: The substantial completion date needed to be extended due to issues with permit closul'os. • Change Order was included in the original specifications. Yes n No Z If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5% of contract price (whichever is greater). Yes El No M If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes Z No n If no, explanation of why: • Change Order is correcting an error or omission in design document, Yes E]No Z Should a claim under the applicable professional liability policy be made? Yes L] No M Explain: From To: Subject: Re:PKJCDF-Fray App 52 May Date: Friday,August 25,2023 10:21:34 AM Attachments: i'mag.am4m ............... .......... ....... (1' CAUTION 11111"' Please provide a throe extension through July 31, 2023, to coincide with filial payment application date, permit closure issues, and completion of CCD8 painting. Jennifer LederhOUse Blitmore Construction Assistant Project Manager t: 727-585-2084 1 m: 727-426-0373 e:jlecierl)OLlse@bilti-norefl.co" n I w:www.bilt�Tiorecoiistr(�ctio).coiii a; 1.055 Ponce de Leon Blvd, Belleair, FL 33756 Ihis e9ectroiiic uraysrnission Tnav contain information which is con(rrleritial and privilefed. 'i"he infurnratison transwined is rla� ,nderl only for this pem'.in or entity wwhrch it is adctreswd ifycRil are lr,'x the intended 4ec'ipwnt:any neview,6e8ransonissuorv,dissnininartion or other arse of,or taking of anyadion in rehance upon,this information bypi:isons of entitic'sother than the intended reciii is proinibiried.If you i this transmission in error,pleaw contact the seridex and delete flue nlaterial frorn any system that CoWains it,inciridmg,but not himilied to the rlestrr,vct4our of psper t1ild rotherr physical reproductions of this transrrission.R&ceipj by ANY indlvjdual or enioity is not a waiver of am/legal privilege Qe.f,.attorney rhent,work Product,etc) Furthermore, this electronic.transmission does not consfitute art e-signahuie, nor any other form of e-rdenitificaiinn or eakAhorwitiorl. By this transilmssion Utrnme Construrimill does not intelid to evidence a hiloing agreement,or to iiripiy that 1he author has airy arjthorty to C,,rltelr f1to a bidding agreeirient on bih,-O of Riltitiore Construction. ........... . ......................... ...................