04th Change Order 12/04/2023 DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
M.C.A.INSTR..8800.2
Enclosure(1)
3/28/2017
Page 3
MONROE COUNTY/ENGINEERING/PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECTTITLE: KWIA Concourse A&Terminal Improvements CHANGE ORDER NO.: 004
INITIATION DATE: 8/31/2023
TO CONTRACTOR: NV2A/Gulf Keystar JV CONTRACT DATE: 8/17/2022
The Contract is changed as follows:
The Original(Contract Sum)(Guaranteed Maxium Price) $ 101,461,771.00
Net change by previously authozied Change Order $ 8,298,429.81
The(Contract Sum)(Guaranteed Mxium Price)prior to this Chage order was $ 109,760,200.81
The(Contract Sum)(Guaranteed Mxium Price)will be i'puxre au„ed^ by this Change Order $ 116,816.11
The new(Contract Sum)(Guaranteed Mxium Price) including this Change Order is $ 109,877,016.92
The Contract Time will be(u.undlhMautp;edu by 0 days
The date of Substantial Completion as of the date of this Change Order is 3/9/2026
Detailed Description of change order and)ust7ficatfom
Per the attached PCO,this Change Order includes the additional cost related to mechanical scope of work to address RFI#76 for the KWIA
project,(20-2039-01)
Reference:RFI#76
Revised ductwork layout as shown on drawings included in RFI#76.
Furn[sh and install(4)Non-Powered Roof"Vents model ESD-635PD as indicated on drawing M122B.
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
p# Title Schedule Impact Amount
pC
0 Turnkey Intl.Revised Ductwork and Roof Vents o1 $ 116,816.11
Total:I S 116,816.11
This change order is 0.12%of the original contract price.
Not valid until signed by Owner,Architect(if applicable),and Contractor DocuSi#ned by;
/ 11/30/2023 1 10:43:07 PST
ARCHITECT: r 4�',
0roou8iq
rea by: 4� .�. DATE:
� 29/2023 1 20:35:44 PST
CONTRACTORS:
019093827A75487,...
DATE:
DIRECTOR ENGINEERING: N/A
DATE:
DIRECTOR PROJECT MANAGEMENT: N/A
� DAtt' ..
Executive Director of Airports III
DATE:
12.4.2023
COUNTY/DEPUTY ADMINISTRATOR �° 2 �
DATE:
IDS t)S
li:M1 p�l�&' Cl�'COUNTY A, NI�f'�
AS SIS J° AERCl?NTY ATTORNEY
Cate 12/1/23
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
cuw euiLorxc
KEYST A PCCO #004
NV2A/Gulf Keystar JV Project:20-2039-01 -KWIA Concourse A and Terminal Improvements
Program
9100 South Dadeland Blvd,Suite 600
3941 South Roosevelt Blvd.
Miami,Florida 33156 Key West,Florida 33040
Phone:(786)233-5060
Prime Contract Change Order #004: Turnkey Intl. Revised Ductwork and
Roof Vents
TO. Key West International Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
DATE CREATED: 8/31/2023 CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar JV)
CONTRACT STATUS: Approved REVISION: 0
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE: REVIEW DATE: 1 0/2 0120 23
INVOICED DATE: PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
REVISED SUBSTANTIAL SIGNED CHANGE ORDER
COMPLETION DATE: RECEIVED DATE:
CONTRACT FOR: 20-2039-01:Key West International Airport TOTAL AMOUNT: $116,816.11
Concourse A
DESCRIPTION:
Per the attached PCO,this Change Order includes the additional cost related to mechanical scope of work to address RFI#76
for the KWIA project.(20-2039-01)
All costs for services are included in this Change Order to perform the work as described herein.This Change Order does not address any other costs
affected by this scope of work.
Referen=RFI#76
Revised ductwork layout as shown on drawings included in RFI#76.
Furnish and Installl(4)Non-Powered Roof Vents model ESD-635PD as indicated on drawing M122B.
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER
T
PCO# itle S�Impacl Amount
�
003 Turnkey Intl.Revsed Ductwork a � $116,816.11
y and Roof Vents
Total: $116.816.11
The original(Contract Sum) $101,461,771.00
Net change by previously authorized Change Orders $8,298,429.81
The contract sum prior to this Change Order was $109,760,200.81
The contract sum will be increased by this Change Order in the amount of $116,816.11
The new contract sum including this Change Order will be $109,877,016.92
The contract time will not be changed by this Change Order.
opt
404W44afarvWcFarlan Jobnson,Inc.) Key West International Airport NV2A/Gulf Keystar JV
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156
j
�d�� P
w. ATE
SIGN RE. DATE SIGNATURE AT AI"UR
tts t�
nivonrr_,drue ���. iv Pane l of 1 /XPted On:10/20/2023 09:16AM
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
Tt1 GULF BUILDING PCO #003
KEVST R
NV2A/Gulf Keystar JV Project:20-2039-01-KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(785)233-5060 Key West,Florida 33040
Prime Contract Potential Change Order #003: Turnkey Intl. Revised
Ductwork and Roof Vents
TO: Key West International Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
PCO NUMBER/REVISION: 003/1 _ CONTRACT: -� 20-20
39-01-Key
West
International
Airport Concourse A
REQUEST RECEIVED FROM: CREATED BY: Mansour Sodagari(NV2A/Gulf Ke s y tar
JV)
STATUS: Approved roved....„ CREATED DATE: . ..
' /5/2023
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ,._.,. .. ,sm. ....,... . ACCOUNTING METHOD: Amount
,- .. .. _ ... ,.- w... _._._.....
Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED.
,.�. ®e...,.,,..No.,
SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $116,816.11
POTENTIAL CHANGE ORDER TITLE:Turnkey Intl.Revised Ductwork and Roof Vents
CHANGE REASON:A/E Design Changes
POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract Is Changed As Follows)
�6dF.P�99�.� �r �11]r"�. rzySl UPP��?tNr�.40�. gP)�!E�09.4
This Change Order Includes the additional cost related to mechanical scope of work to address RFI#76 for the KWtA project.(20-2039-01)
All costs for servlces are included in this Change Order to perform the work as described herein.This Change Order does not address any other costs
affected by this scope of work.
Reference:RFI#76
Revised ductwork layout as shown on drawings included in RFI 476.
Furnish and install(4)Non-Powered Roof Vents model ESO-635PD as indicated on drawing M122B.
ATTACHMENTS:
UPDATED PROPOSAL KWIA TKI COR#02.3 RFI 76 AHU Conn's.pdf
_. __.. __ _-Budget Code ... ...._„ .Description
Amount',
1 23.00.10.10.S HVAC.Subconlractor Revised Ductwork,Roof Vents,Smoke Dampers $106,196.46
2 99-,99.99.66.0 Procore OH&P.Olher 10%Markup".......... ..... . - _--.... $10,619.65
Grand Total: $116,8'16.11
McFarland Johnson,Inc. Key West International Airport NV2A/Gulf Keystar JV
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156
Dig]tally signed by Christopher
Christopher +�
pe
Date:2023.07 12 15D7:13
Kopec -"00
SIGNATURE DATE SIGN RE DATE SIGNATURE DATE
NV2A/Gulf Keystar JV Page 1 of 1 Printed On:6/19/2023 04:59 PM
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
C.O.R.Date Tuesday,June 6,2023
._
KEY WEST INTERNATIONAL AIRPORT
Project Name CONCOURSE A&TERMINAL
rinIMPROVEMENTS
i
From concept to completion
Project Number 2-23-101
Turnkey International, Inc.
Mechanical Contractors CMC 1249679
CHANGE ORDER EST' # 002 Rev. 03
TO: Ann. Mansour Sodagari City Key West
.... .
Company NV2A+Gulf Building State/Province FL Zip/Postal Code 33040
Address 5450 MacDonald Ave.,Suite 3 Country USA
Description of Change Order Request:
PCO-003-Ref.NV2A RFI 76 Response
Per the referenced RFI, please refer to the attached scope of work,exclusions,and costs breakdown.
Please refer to the attached ADD alternate if required.
NOTE:Due to the continued supply chain and material escalation cost,this COR is valid for(120)days. We reserve
the right to adjust cost if COR/Submittals are not approved within 120 days.
Items �. ,...�...._ ........�_..� ....._ -�.� .. ...�._.-.�,. �.
Amount
Refer to the attached breakdown - �
$ 6,542.24
Cost $96,542.24
OH+Profit+Bond 10 /o $9,65
a 4.22
Sub-Total $106,196.46
% $0.00
Sub-Total $106,196.46
% $0.00
Total $106,196.46
Dl,,,11lytl,,rn dtry'Leone,Son
Le o n e 15 o n U cr georveNSure,o=TumkCy Intematdonal,
In
Inc,ou,
em,Wa.'re,oanetloit igr+keymecha ical.com,c=US
Date:2023.04.26 17:07:08-000'
Accepted By: Date: Submitted by: Leonel Son Date: Jun 6,2023
Company: Turnkey International,Inc.
THIS PROPOSAL IS ONLY FOR THE COST OF PERFORMING THE CHANGE WORK ITSELF.
THIS PROPOSAL DOES NOT INCLUDE ANY ADDITIONAL COST STEMMING FROM IMPACT,DELAY OR ACCELERATION OF OUR SUBCONTRACT WORK REQUIRED
BY THIS CHANGE.OUR COMPANY RESERVES ALL RIGHTS WITH RESPECT TO SAID ADDITIONAL COSTS AND/OR TIME EXTENSIONS ARE FULLY RESERVED.
1315 NW 98th Ct Unit 15,Doral,FL 33172
P (305)591 0261 F(305)591 2676
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
us
Tunkey
,1
Turnkey International,Inc.
Mechanical Contractors
CMC 1249679
June 6, 2023
Key West International Airport
Concourse A &Terminal Improvements
TKI COR 2.3
Ref. NV2A RFI 76 AHU's Ductwork Connections Response
Per the referenced RFI response, this proposal contains the following scope of work:
➢ Revised ductwork layout as shown on drawings included in NV2A RFI 76.
➢ Furnish and install(4) Non-Powered Roof Vents model ESD-635PD as indicated
on drawing M122B. Please note that we are not including the motorized dampers
called for within the Ventilator Schedule as the AHUs have motorized dampers
on the OA inlet and EA discharge openings—Refer to RFI 140 Response.
➢ Furnish and install (1)fire damper added on Electrical room as shown on drawing
M121A& RFI 141 Response.
Exclusions:
• Any additional controls work.The OA and EA dampers on the units are already
under the BMS scope of work.
• Structural framing for new vent curbs on roof.
• Modifications to soffit structure.
• Overtime.
• This proposal does not include accelerated schedule or quick-ship of materials.
1315 NW 98T"Ct.#15,DORAL,FL 33172
PH.305.591.0261 —FAX 305.591.2676
Page I of 2
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
OW "keftaliF
I Uri I RMY
Turnkey International,Inc.
Mechanical Contractors
CMC 1249679
ALTERNATE FOR EHH-601PD ILO ESD-635PD MODEL
ADD:As a suggested alternative, note that roof vents model EHH-
601 PD have a high performance horizontal wind-driven rain style $92,000
blades for maximum protection against wind-driven rain—Refer to the
attached proposal from CorsAir
Anticipated escalation within 120 days(5%) $4,600
Deduct: ESD-635PD Roof Vent Model—Refer to the attached ($54,800)
proposal from CorsAir
$2,926
Taxes
Additional Permit $2,684
Sub-Total: $47,410
Markup (10° ) $4,741
Total ADD for using model EHH-601 PD: $52,161
1315 NW 98TH Ct.#15,DORAL,FL 33172
PH.305.591.0261 —FAX 305,591.2676
Page 2 of 2
rn o 0 0
w N O O O O O O O O O O N O 0 0 0 0 O N
O O c V1 In N
�..� N lD O O In 00 0 O O 00 m -t O w R O O rl a
W \ Q N O O tD O Op0 r Q n In Ill 00 lD 0 0 In V N
W lD 1D O h
Q0 00 00 �' m m .•i m N In N m CI
o F r
G Z
J
V} Ln
V► VPr VY VF VF VI V?VF L5 VF in
U O O O
o Ln v
rr In
cr W O
F-
O {n VT w
00 0o p,o 0 00 0 0 0 0 0 0 0
000'00 0
J N p O In Ill O ll1 01 P. 00 lD O
i o m �'rn o
H Ln t ri (n ri Iri v cri rV
O � �
r
O in V> VI
u +n ,n Vx ila v*
w o o p,o 0 0 0 0 0 0 0 0
O r o 0 0 0 0 0 0 0 0 0 0 0
m z r, n n n n n n N n 0) C) 00
g t o 00
c a
a
O V N N N'..e-I 01 'O lD
OO
Q 2 N N N Ol N d N �„4 '-I N
f0
C ~ W O V" 0 0 N 0 0 O O. ..
+' $ $ m m m m a m m m v
m
o
O p p Il� 00 p 0 0 C N
o o L6 coLr, 0 o po a II;t o v
C J m 00 000 m apo` rl m N LD co In
T En H RI. c-i. �. vi V N Imo' r4 In
In MI
N O O -. m N
3 lD �'0 r
6J Y tL {n.ill. 4^in..4A V} 4.1 VF in.V} VF V1•
Q Ln O O Ipn Iroi u
Ln LM
Ln O O VI T Ili fri
z in o m in'n i/1 VY
O
Z O N'
O
V}
lIJ e1 p
O K
rn
N �. Y Lnd N N O N ci V m
m a F o
m
LO
Q O L C p N
O N C QI N N C
CoJ u° 3 0 o: m
4 E M - n E p
C, c
n ° cl
LLI o 5 — u > er °o 0 39 0 N
rn L aL N co t W N VILLJ c
LL Q H m In v oa w 'i W In x c > _
cn o c � o ro w c x ° E
mna a c o o n d c o Ln aa) c a > f w
LU jr J i' ` Ln L O C ILO in D_
r •N y L -0W i+ N O fE
LLn O � o c m > o r X s c c o c oUC o_
rn T G u G In Q W aL Q .I VI m Q o v o Y
N W c 7 0 0 to C N N -C � I=n r N 0.. IOD..O 2a Q
Y9: +� �D a r
U N N N N O N N N N O O
m o 0 0 0 0 0 0 0 0 0 0 o m
p z F M m m m V T m M m a
0 '" 2 W p .--I N M [F In IO I� oo atLO.J
tiL,-Lim
u•I lD P
0 �--� 14 �-i e-I 'i ei •-1 '-I .--� N N N N N
0)
C
W
C
rn
(n
7
(J
O
cl
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
I
Manufacturers'Representatives
2601 S.W.32nd Avenue,Pembroke Park,FL 33023
CORS-AIR Main(954)456-4300 *FL Watts(800)678-2424
S—Lng CnWmcib %InduStryTh—JI1 E,MWI—B Intagnty Fax(954)456-4387 *Est.Fax(954)456-4387
Visit us at our website: www.cors-air.com
Q U 0"'T E
CUSTOMER: TURNKEY MECHANICAL DATE: March 14,2023
ATTENTION: LEONEL SON PAGES: 1
FAX: SALES ENGINEER: CARLOS SABATER
EMAIL: SUBMITTED BY: CARLOS SABATER
PROJECT: KWIA CONCOURSE A&TERMINAL IMPROVEMENTS
RFI# 76
(Q:T y' DESCRIPTION TOT.DELETE TOT.ADD
1 FIRE SMOKE DAMPER $463.00
4 ESD-635PD ROOF VENTS $54,840.00
4 ALTERNATE EHH-601PD ROOF VENTS $92,000.00
4 42"X42"ALUMINUM MOTORIZED DAMPERS $3,400.00
"NO ACTUATORV
SUB-TOTAL 1I $0.0011 $150,663.00
TOTAL $150,663.00
THANK YOU FOR YOUR BUSINESS!
'Exceptions.,Any items not specifically expressed in this bid/quotation.
t Unless otherwise indicated this quotation is a based on a customer take off.Purchaser has reviewed all pages for accuracy for the
materials to be ordered,especially models,accessories,sizes,quantifies,widths,heights and voltages.Louvers as quoted do not meet
Miami-Dade County product approval unless otherwise stated.Prices,specifications and conditions are accepted by Purchaser.
*The Undersigned Purchaser,as the authorized agent for the above customer has read the'Terms and Conditions'attached as the last
page of this Quote and hereby agrees to purchase and pay for the above described items.Purchaser has reviewed all pages contained and
materials to be ordered,especially sizes,quantities,widths,heights and voltages,including those of louvers and heaters and all other
products.The above prices,specifications and conditions are accepted by Purchaser.Payment must be made according to terms.This
Quote must be signed and retumed with deposit if applicable prior to Cors Air ordering product on your company's behalf.Prices are subject
to all applicable taxes.
DATE PRINTED NAME/TITLE
Page 1 of 2
DocuSign Envelope ID:C2974955-FA26-43F7-9E47-BC6D6A605BB2
SUBMI
.lob Name: KWIA - CONCOURSE A - TERMINAL - Roov
Ventilators
Engineer.' MCFARLAND JOHNSON
Contractor.• TURNKEY MECHANICAL
Elevation: (ft) 10
Date: 3/14/2023
Submitted By: Carlos Sabater
CORS-AIR
2601 SW 32 AVE
PEMBROKE PARK, FL 33023
US
Phone: (954)456-4300
Fax: (954)456-4387
Email Address: carlos@cors-air.com
Liu OEENHECOK
Building value in Air.
P.O. Box 410 Schofield,WI 54476 (715) 359-6171 FAX(715)355-2399 www.greenheck.com
G:\Wincaps\JOBS\CS\76459 KWIA-CONCOURSEA-TERMINAL.gfcj
CAPS 4.40.1103 Generated by:cados@cors-air.com Page 1 of 4