05th Change Order 12/04/2023 DocuSign Envelope ID:B07EA9C6-AA4A-4D4F-B206-25E1BE77OF9E
M.C.A.INSTR,8800,2
Enclosure(1)
3/28/2017
Page 3
MONROE COUNTY/ENGINEERING/PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECTTITLE: KWIA Concourse A&Terminal Improvements CHANGE ORDER NO.: 005
INITIATION DATE: 9/5/2023
TO CONTRACTOR: NVZA/Gulf Keystar JV CONTRACT DATE; 8/17/2022
The Contract is changed as follows:
The Original(Contract Sum)(Guaranteed Maxium Price) $ 101,461,771.00
Net change by previously authozied Change Order $ 8,415,245.92
The(Contract Sum)(Guaranteed Mxium Price)prior to this Chage order was $ 109,877,016.92
The(Contract Sum)(Guaranteed Mxium Price)will be f,uunchaangecll)by this Change Order 0
The new(Contract Sum)(Guaranteed Mxium Price) including this Change Order is $ 109,877,016.92
The Contract Time will be 1 ii.unahreaau&Iio:,'Il by 0 days
The date of Substantial Completion as of the date of this Change Order is 3/9/2026
Detailed Descdptlon.of change order and)usWicat'low
As per the attached approved PCO#009,JV is proposing to self-perform the temporary construction partitions work in a lump sum amount of
118,802,64.The cost breakdown,work phases,and locations are provided in the backup documents.
POTENTIAL CHANGE ORDER'S IN THIS CHANGE ORDER:
Pco# Title Schedule Impact Amount
009 '.Temporary Construction Partitions Inside Existing Terminal 0 0
Total: 0
This change order is 0.00%of the original contract price.
Not valid until signed by Owner,Architect(if applicable),and Contractor 177—
usigned by:
11/30/2023 N 10:45:41 PST
ARCHITECT: aY'
I}ocuSigned by: IgiG0:, 10487 DATE:
�7 2023 20:37:26 PST
CONTRACTORS:
m.�
01;�85k.9fk2TA'TdP7.... �aa'3IJfJtlA817Er"%L7�',. DATE: ....
DIRECTOR ENGINEERING'. N/A
DATE:
DIRECTOR PROJECT MANAGEMENT: N/A
DATE: la3
Executive Director of Airports
� � 7ATE:
DEPUTY ADMINISTRATOR µm
a ^
COUNTY/DEPUTY „���' °.°�... 12�4�2023
DATE:
47S RM El
A NRC7 OI.II�ITY AT� NAY
ITE;CI d,L A
A 'SI5, d,lNTY ATTORNEY
Date 1211/23
DocuSign Envelope ID:B07EA9C6-AA4A-4D4F-B206-25E1 BE770F9E
GOLF BUILGaNG
KEYST R PCCO #005
NV2A/Gulf Keystar JV Project:20-2039-01-KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key Wesl,Florida 33040
Prime Contract Change Order #005: Temporary Construction Partitions
Inside Existing Terminal
TO: Key West International Airport FROM: NV2AIGulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
DATE CREATED: 9/05/2023 CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar JV)
CONTRACT STATUS: Approved REVISION: 0
DESIGNATED REVIEWER: REVIEWED BY.
DUE DATE: REVIEW DATE:: 10/2012023
INVOICED DATE: PAID DATE:
SCHEDULE IMPACT: EXECUTED, NO
REVISED SUBSTANTIAL SIGNED CHANGE ORDER
COMPLETION DATE: RECEIVED DATE:
CONTRACT FOR: 20-2039-01:Key West International Airport TOTAL AMOUNT: $0.00
Concourse A
DESCRIPTION:
As per the attached approved PCO#009,JV is proposing to self-perform the temporary construction partitions work in a lump sum amount of
$118,8 2A4,The cast breakdown,work phases,and locations are provided in the backup documents.
-Phase A-Arrival Terminal:t+Iew Elevator,Passenger Bridge,East Carrousel,Airline Offices $34,772.59
Phase B-Arrival Terminal,New West!Baggage Ctalm Carrousel,and the New'Vestibules $41,236.54
Phase C-Departure Terminal:New T'SA Security Checkpoint,TSA Offices $42,793.51
TOTAL: $118,802.64
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: __—•••
Schedule Impact Amount
PCO#
009 Temporary Construction Partitions Inside E�xistingrminal $0,00
_- Tote I:
$0,00
The original(Contract Sum) $101,461.771.00
Net change by previously authorized Change Orders $8,415,245.92
The contract sum prior to this Change Order was $109,877,016.92
The contract sum will not be changed by this Change Order in the amount of $0.00
The new contract sum including this Change Order will be $109,877,016.92
The contract time will not be changed by this Change Order.
O'"r � +P C
Iatrt ra McFarland Johnson,Inc.) Key West International Airport NV2A/Gulf Keystar JV
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156
SIGNA E DATE .IGNATURE', DA E S ATURE DATE.
DS
NV2A/Gulf Keystar JV Page 1 of 1 ;*ted On:10/20/2023 09:33 AM
DocuSign Envelope ID:B07EA9C6-AA4A-4D4F-B206-25E1BE770F9E
GULF BUILDING PCO #009
NVI" I KEYST R
NV2A/Gulf Keystar JV Project:20-2039-01-KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Key West,Florida 33040
Phone:(786)233.5060
Prime Contract Potential Change Order #009: Temporary Construction
Partitions Inside Existing Terminal
TO: Key West Internalkinal Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
PCO NUMBERIREVISION: 009/0 CONTRACT., 20-2039-01-Key West International
Airport Concourse A
REQUEST RE.
CEIVED FROM: CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar
JV)
STATUS: Approved CREATED DATE: 6/712023
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: 3'a $0A,
.,ii,.i
POTENTIAL CHANGE ORDER TITLE:Temporary Construction Partitions Inside Existing Terminal
CHANGE REASON:Client Request
POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract/s Changed As Follows)
of '_ray rsi uc'ia n "artttla its Iros6d i ,iin -Ter 'ta
Description
The JV is proposing to self-perform the temporary construction partitions work in a lump sum amount of$118,802.64.The
cost breakdown,work phases,and locations are provided in the backup documents.
-Phase A-Arrival Terminal: New Elevator, Passenger Bridge,East Carrousel, Airline Offices $34,772.59
-Phase B-Arrival Terminal: New West Baggage Claim Carrousel, and the New Vestibules $41,236.54
-Phase C-Departure Terminal: New TSA Security Checkpoint,TSA Offices $42,793.51
TOTAL: $118,802.64
ATTACHMENTS:
Emall.odf
Description Amount
# Budget Code p i p i.VV,.
1 .4" '30 O'Te 3 "`Gheel"" i � Temporary Construction Partitions at Existing Terminal 1 "8
1 Allowance-Other W, 6,"R W Vu af�ti�rt�„yq" urrnMm
Grand Total: 0 00
McFarland Johnson,Inc. Key West International Airport NV2A/Gulf Keystar JV
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Lin harntotl,,New York 13901 Key West,Florida 33040 Miami,Florida 33156
7/27/2023
SIGNATURE DATE SIGNAL RE' DATE ATU DATE
NV2A/Gulf Keystar JV Page 1 of 1 Printed On:611512023 08:48 AM
DocuSign Envelope ID:B07EA9C6-AA4A-4D4F-B206-25E1BE770F9E
From:Antonio Pinto
Sent:Wednesday, May 24,2023 4:42 PM
To: Leto-Beth<Leto-Beth@ M onroeCou nty-FL.G ov>; Bethel-Tyler<Bethel-Tyler@MonroeCounty-FL.Gov>; Mercado-
Pedro<Mercado-Pedro@MonroeCounty-FL.Gov>; Emie Simeone(simeone-emie@monroecounty-fl.gov)<simeone-
emie@monroecounty-fl.gov>;MansourS@gulf build ing.com
Cc:Saenz-Stephanie<Saenz-Stephanie@MonroeCounty-FL.Gov>;Oscar Benito<obenito@nv2agroup.com>
Subject:KWIA Temporary Construction Partitions
Good afternoon Beth,Tyler and Pedro,
Following up on this morning's meeting, please find below a description on the approach the JV would like
your concurrence to move forward.
The JV included Modern Containment System (MCS) in GMP 2 to perform the temporary construction
partitions for the project. GMP Amendment 2, Section 05 Bid Leveling Sheets page 2 of 60 shows total
$118,802.64 for the temporary construction partitions.
The JV is unable to execute an agreement with MCS, and in order not to jeopardize the project, is proposing to
self-perform the temporary construction partitions work in a lump sum amount of$118,802.64 broken down
as follows:
• Phase A-Arrival Terminal:New Elevator, Passenger Bridge,East Carrousel,Airline Offices
o Temporary construction partitions at the Baggage Claim Room and Hold Room at the Arrivals
Terminal First Floor for$34,772.59 including the new elevator construction, new passenger
bridge construction, new east baggage claim carrousel, and Airline's offices. Please see pages 4
and 5 of 8 of the Terminal Improvements Phasing Plan Revision 8 dated 10/28/2022.
• Phase B-Arrival Terminal: New West Baggage Claim Carrousel,and the New Vestibules
o Temporary construction partitions at the Baggage Claim Room at the Arrivals Terminal First
Floor for$41,236.54 including the new west baggage claim carrousel, and the new vestibules.
Please see page 7 of 8 of the Terminal Improvements Phasing Plan Revision 8 dated
10/28/2022.
• Phase C- Departure Terminal: New TSA Security Checkpoint,TSA Offices
o Temporary construction partitions at the Departure Terminal Second Floor for$42,793.51
including the new TSA Security Checkpoint,and the new TSA offices. Please see page 8 of 8 of
the Terminal Improvements Phasing Plan Revision 8 dated 10/28/2022.
The temporary construction partitions work in the current Schedule of Values (SOV) are included in line-item
MOT/Movement of Passengers for GMP 2(Phase A and B-Terminal Improvements First Floor), and GMP 4
(Phase C-Terminal Improvements Second Floor).
Please review this issue and let us know if you have questions or require additional information.
Regards,
Antonio Pinto
5450 MacDonald Ave., Suite 3
Key West, FL 33040
C 305.202.0610
E alginto nv2a rou .c m
N 0 Ar �"� GULF HIIILONN'G
KEYST