MONROE COUNTY/DEPARTMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECTTITLE: KWIA Concourse A&Terminal Improvements CHANGE ORDER NO.: 008
INITIATION DATE: 11/20/2023
TO CONTRACTOR: NV2A/Gulf Keystar JV CONTRACT DATE: 8/17/2022
The Contract is changed as follows:
The Original(Contract Sum)(Guaranteed Maxium Price) $ 101,461,771.00
Net change by previously authozied Change Order $ 8,415,245.92
The(Contract Sum)(Guaranteed Mxium Price)prior to this Chage order was $ 109,877,016.92
The(Contract Sum)(Guaranteed Mxium Price)will be('iincireased)by this Change Order $ 3,323,990.00
The new(Contract Sum)(Guaranteed Mxium Price) including this Change Order is $ 113,200,996.92
The Contract Time will be(unchairnged)by 0 days
The date of Substantial Completion as of the date of this Change Order is 3/9/2026
Detailed Description of change order and justification:
'Chas Change Order includes the costs associated with the changes in the Scope of Work for the electrical power and lighting systems resulting from
the incorporation of the revisions depicted in the 100%Conformed Design Drawings compared to the 90%Contract Documents for the KWIA project.
20.2039.01
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
p00 Title Schedule Impact Amount
018 FKE•D,&slgn Chan.90%CD to Conformed Set-Elec.ftwerMighting 0 $ 3,323,980„00
Ttntal: $ 3,323,980.00
This change order is 3.28%of the original contract price.
Not valid until signed by Owner,Architect(if applicable),and Contractor E(�J6�a,
Signed by:
S, I 6/2023 1 15:56:59 PST
ARCHITECT: ,
DocuSigned by: DocuWpned by, DATE:
I � 12/6/2023 1 15:03:25 PST
CONTRACTORS:
-- 0190p'382W—A8F..„ 613'DD4BAB$7r-'14D4 w_... DATE:
'Doctr''8lgned by: 12/7/2023 1 07:13:35 PST
EXECUTIVE DIRECTOR OF AIRPORTS
DATE:
8E66F52F4C21-4D3...„u , „
���...
COUNTY/DEPUTY ADMINISTRATOR 12.12.2023
� "' �•� �
DATE:
I+POE COUNTY ATTOnNEY DS 0s
� AO4'E
P1=D G:1,I. A -7
ASSISTA LINTY ATTORNEY
Date 12/7/23
DocuSign Envelope ID:C4A3690E-FE81-4A3A-A2CC-D95A3230FCBC
�" � GULF ruwbmar�r
" YT PCCO #008
NV2A/Gulf Keystar JV Project:20-2039-01-KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key West,Florida 33040
Prime Contract Change Order #008: FKE-Design Chan. 90%CD to
Conformed Set-Elec. Power&Lighting
TO: Key West International Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami, Florida 33156
DATE CREATED: 11/20/2023 CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar JV)
CONTRACT STATUS: Approved REVISION: 0 -
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE; REVIEW DATE;__ 12/06/2023
INVOICED DATE: PAID DATE: -
SCHEDULE IMPACT: 0 days EXECUTED: No
REVISED SUBSTANTIAL SIGNED CHANGE ORDER 11/20/2023
COMPLETION DATE: RECEIVED DATE:
CONTRACT FOR: 20-2039-01:Key West International Airport TOTAL AMOUNT: $3,323,980.00
Concourse A
DESCRIPTION:
FKE-Design Changes 90%CD to Conformed Set-Electrical Power&Lighting
This Change Order includes the costs associated with the changes in the Scope of Work for the electrical power and lighting systems resulting from the
incorporation of the revisions depicted in the 100%Conformed Design Drawings compared to the 90%Contract Documents for the KWWA project.(20-
2039.01)
This Change Order amount is a Lump Sum of$3,323,980.00 broken down as follows:
1 Direct Cost-Electrical Power and Lighting 9 9 $ 2,900,000.00
2 'Payment and Performance Bonds Included
3 Insurance(Excluding Builder's Risk)(Note 1) 1.20% $ 34,800.00
4 Builder's Risk Insurance Note 1 100%
5 Subtotal: $ 3,021,800.00
6 Markup Fo-00% $ 302,180.00
7
Total $ 3,323,980.00
Note 1:Insurance amounts shown are allowances.Final insurance amounts shall be based on the actual insurance costs at the end of the Project.
REFERENCE:
PROCORE>Drawings>90%CD Drawing Set os os os Ds
PROCORE>Drawings>Conformed Set p p
ATTACHMENTS:
NV2A/Gulf Keystar JV Page 1 of 2 Printed On: 12/6/2023 04:39 PM
DocuSign Envelope ID:C4A3690E-FE81-4A3A-A2CC-D95A3230FCBC
NV K YS't" R LICO 7T008
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
.................. ..
PCO# Title Schedule Impact Amount
018 FKE-Design n Chan.90%CD to Conformed S g et-Elec.Power&Lighting j 0 days $3,323,980.00
... .... . _.
Total: $3,323,980.00
The original(Contract Sum) $101,461,771.00
Net change by previously authorized Change Orders $8,415,245.92
The contract sum prior to this Change Order was $109,877,016.92
The contract sum will be increased by this Change Order in the amount of $3,323,980.00
The new contract sum including this Change Order will be $113,200,996.92
The contract time will not be changed by this Change Order.
Christopher Kopec(McFarland Johnson, Key West International Airport NV2A/Gulf Keystar JV
Inc.)
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156
oaaca fined by, p Dmo5igned by:: Doca«'•ftned'by:
d � f �1v1mil 12/6/2023 I 15:03:2
5 56:59 S 3 I 07:13:35 P � - 'a
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
os os
y F-`�r-*d��n,:._NV2A/Gulf Ke star JV Page 2 of 2 � 1`2 612023 04:39 PM
DocuSign Envelope ID:C4A3690E-FE81-4A3A-A2CC-D95A3230FCBC
I� = V - K wo GULF BUILDING PCO #018
IV =" KEYST R
NV2A/Gulf Keyslar JV Project:20-2039-01 -KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd, Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key West,Florida 33040
Prime Contract Potential Change Order #018: FKE-Design Chan. 90%CD to
Conformed Set-Elec. Power&Lighting
TO: Key West International Airport FROM: NV2A/Gulf Keyslar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
PCO NUMBER/REVISION: 018/0 CONTRACT: 20-2039-01-Key West International
Airport Concourse A
REQUEST RECEIVED FROM: CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar
JV)
STATUS: Pending-In Review CREATED DATE: 10/11/2023
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: 0 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $3,323,980.00
POTENTIAL CHANGE ORDER TITLE:FKE-Design Chan.90%CD to Conformed Set-Elec.Power&Llghling
CHANGE REASON:A/E Design Changes
POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract Is Changed As Follows)
FKE-Design Changes 90%CD to Conformed Set-Electrical Power&Lighting
This Change Order includes the costs associated with the changes in the Scope of Work for the electrical power and
lighting systems resulting from the incorporation of the revisions depicted in the 100% Conformed Design Drawings
compared to the 90% Contract Documents for the KWIA project. (20-2039-01)
This Change Order amount is a Lump Sum of$3,323,980.00 broken down as follows:
1 Direct Cost-Electrical Power and Lighting $ 2,900,000.00
2 Payment and Performance Bonds Included -
3 Insurance(Excluding Builder's Risk)(Note 1) 1.20% $ 34,800.00
4 Builder's Risk Insurance(Note 1) 3.00% $ 87,000.00
5 Subtotal: $ 3,021,800.00
6 Markup 10.00% $ 302,180.00
7 Total $ 3,323,980.00
Note 1: Insurance amounts shown are allowances. Final insurance amounts shall be based on the actual insurance costs
at the end of the Project.
REFERENCE:
PROCORE> Drawings> 90% CD Drawing Set
PROCORE> Drawings> Conformed Set
NWA/Gulf Kaystar JV Pape 1 of 2 Printed On:10/12/2023 05:40 PM
DocuSign Envelope ID:C4A3690E-FE81-4A3A-A2CC-D95A3230FCBC
N- 10 GULF ]BUILDING PCO #018
T
ATTACHMENTS:
I
i
1
J e7 fa c NV2AlGulf Keystar JV
McFarland Johnson,Inc.) Key West International Airport
9100 South Dadeland Blvd,Suite 600
49 Court Street,Suite 240 3491 South Roosevelt Boulevard
Binghamton,New York 13901 Key West,Florida 33040 MIamI,Florida 33156
4 .
SolE ATe st NATu
OAT GATUIRE
000uaign Envelope ID:o4AonooE-rso1