09th Change Order 12/12/2023 DocuSign Envelope ID:009D958F-F81D-40FC-8A47-6A83F7EB9B34
M.C.A.INSTR.8800.2
Enclosure(1(
3/28/2017
Page 3
MONROE COUNTY/DEPARTMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECTTITLE: KWIA Concourse A&Terminal Improvements CHANGE ORDER NO.: 009
INITIATION DATE: 11/20/2023
TO CONTRACTOR: NV2A/Gulf KeystarJV CONTRACT DATE: 8/17/2022
The Contract is changed as follows:
The Original(Contract Sum)(Guaranteed Maxium Price) $ 101,461,771.00
Net change by previously authozied Change Order $ 11,739,225.92
The(Contract Sum)(Guaranteed Mxium Price)prior to this Chage order was $ 113,200,996.92
The(Contract Sum)(Guaranteed Mxium Price)will be(increased by this Change Order $ 916,960.00
The new(Contract Sum)(Guaranteed Mxium Price) including this Change Order is $ 114,117,956.92
The Contract Time will be(unchanged)by 0 days
The date of Substantial Completion as of the date of this Change Order is 3/9/2026
Detailed Description of change order and,pustificatiow
This Change Order includes the costs associated with the changes in the Scope of Work for the low voltage systems,including communication,
set:u6ty,and fire alarm,resulting from the incorporation of the revisions depicted in the 100%Conformed Design Drawings compared to the 90%
Contract Documents for the KWIA project.(20.2039-011
POTENTIAL C14AN E ORDERS IN THIS CHANGE ORDER:
PCO# Title Schedule Impact Amount
019 RF.•peMp Changes 90%CD to Conformed Set—Low vokage Sys, 0 $ 916,960.00
1"0121: $ 916,960,00
This change order is 0.90%of the original contract price.
Not valid until signed by Owner,Architect(if applicable),and Contractor DocuSLgned by,
'^^,►►,;``j6rLr Wr&2/6
ARCHITECT: r
023 1 15:58:11 PST
DATE:
,.DocuSigned by: DocuSignud by:
12/6/2023 1 15:04:31 PST
CONTRACTORS: r
019093827A75487... 61'',tt,'1+AQABT, E740r1,.. DATE:
Docu,Pgnxdby: 12/7/2023 1 07:19:44 PST
EXECUTIVE DIRECTOR OF AIRPORTS
DATE:
P3EB59'."u2F4C'2M3.. �,.°" ^°'
Ole
COUNTY/DEPUTY ADMINISTRATOR 2.1 2.2023
a
DATE:
NROE COUNTY ATTORNEY
A 43aVEg � FOfile#
PE?7 JUNTY ATTORNEY
ASSISTA UNTY ATTOI3M1IEY
i)ate 12/7/23
DocuSign Envelope ID:009D958F-F81D-40FC-8A47-6A83F7EB9B34
KIG'b4P 9411 h.b1H:b.
� YT PCCO #009
NV2A/Gulf Keystar JV Project:20-2039-01-KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key West,Florida 33040
Prime Contract Change Order #009: FKE-Design Changes 90% CD to
Conformed Set—Low Voltage Sys.
TO: Key West International Airport FROM; NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami, Florida 33156
DATE CREATED: 11/20/2023 CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar JV)
CONTRACT STATUS: Approved REVISION: 0
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE:_ REVIEW DATE: _ 12/06/2023
INVOICED DATE: PAID DATE:
SCHEDULE IMPACT 0 days EXECUTED: No
REVISED SUBSTANTIAL SIGNED CHANGE ORDER 11/20/2023
COMPLETION DATE: RECEIVED DATE:
CONTRACT FOR: 20-2039-01:Key West International Airport TOTAL AMOUNT: $916,960.00
Concourse A
DESCRIPTION:
FKE-Design Changes 90%CD to Conformed Set—Low Voltage Systems
This Change Order includes the costs associated with the changes in the Scope of Work for the low voltage systems,including communication,
security,and fire alarm,resulting from the incorporation of the revisions depicted in the 100%Conformed Design Drawings compared to the 90%
Contract Documents for the KWIA project.(20-2039-01)
This Change Order amount is a Lump Sum of$916,960.00 broken down as follows::
1 Direcl Cost—Low Voltage Systems $ 800,000.00
2 Payment and Performance Bonds included -
3 Insurance(Excluding Builders Risk)(Note 1) 1.20%
° $ 9,600.00
4 Builder's Risk Insurance(Note 1) 3.00% $ 24,000.00
5 Subtotal: $ 833,600.00
6'Markup 10.00% $ 83,360,00
7 Total $ 916,960,00
Note 1: Insurance amounts shown are allowances.Final insurance amounts shall be based on the actual insurance costs at the end of the Project.
REFERENCE:
PROCORE>Drawings>90%CD Drawing Set
PROCORE>Drawings>Conformed Set
os cs Ds os
�
ATTACHMENTS:
NV , CQ#019EKElow VQA g 91.Q6q:p f
NV2A/Gulf Keystar JV Page 1 of 2 Printed On: 12/6/2023 04:43 PM
DocuSign Envelope ID:009D958F-F81D-40FC-8A47-6A83F7EB9B34
NK KC=r sac-r*
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
FFKE
_.........
_.._
PCO# Title Schedule ImpactAmount
019 sign Changes 90%CD to Conformed Set—Low Voltage Sys. 0 days $916,960.00
Total: $916,960.00
The original(Contract Sum) $101,461,771.00
Net change by previously authorized Change Orders $11,739,225.92
The contract sum prior to this Change Order was $113,200,996.92
The contract sum will be increased by this Change Order in the amount of $916,960.00
The new contract sum including this Change Order will be $114,117,956.92
The contract time will not be changed by this Change Order.
Christopher Kopec(McFarland Johnson, Key West International Airport NV2A/Gulf Keystar JV
Inc.)
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156
DocuSigned by Dorw Sirtgnod by: Do4uSkjned by:
IC dWj � ( 3 I 07:19:44 PS r" . .-- ` g6/2023 1 15:04:31 PST
cra���saa� �s«usa / f r�5:58:11 6 ST , r
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
Ds DS DS
NV2A/Gulf Keystar JV Page 2 of 2 R
�� PirrteI :1 '3 04:43 PM
DocuSign Envelope ID:009D958F-F81 D-40FC-8A47-6A83F7EB9B34
T14 r4 v C"7 KEYST N G PCO #0'I 9
GULF BUILDING
R
NV2A/Gulf Keystar JV Project:20-2039-01-KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key West,Florida 33040
Prime Contract Potential Change Order#019: FKE-Design Changes 90% CD
to Conformed Set—Low Voltage Sys.
TO: Key West International Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
PCO NUMBER/REVISION: 019/0 CONTRACT: 20-2039-01-Key West International
Airport Concourse A
REQUEST RECEIVED FROM: CREATED BY: Mansour Sodagad(NV2A/Gulf Keystar
JV)
STATUS: Pending-In Review CREATED DATE: 10/11/2023
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: 0 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $916,960.00
POTENTIAL CHANGE ORDER TITLE:FKE-Design Changes 90%CD to Conformed Set-Low Voltage Sys.
CHANGE REASON:AlE Design Changes
POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract is Changed As follows)
FKE-Design Changes 90%CD to Conformed Set—Low Voltage Systems
This Change Order includes the costs associated with the changes in the Scope of Work for the low voltage systems,
including communication, security,and fire alarm,resulting from the Incorporation of the revisions depicted in the 100%
Conformed Design Drawings compared to the 90%Contract Documents for the KWIA project.(20-2039-01)
This Change Order amount is a Lump Sum of$916,960.00 broken down as follows:
1 Direct Cost—Low Voltage Systems $ 800.000.00
2 Payment and Performance Bonds included -
Insurance(Excluding -��3 ( g Builders Risk)(Note 1) 1.20% $ 9.600.00
4 Builder's Risk Insurance(Note 1) 3.00% $ 24,000.00
5 Subtotal: $ 833,600.00
6 Markup 10.00% $ 83,360.00
7 Total $ 916.960.00
Note 1: Insurance amounts shown are allowances. Final insurance amounts shall be based on the actual insurance costs
at the end of the Project.
REFERENCE:
PROCORE>Drawings>90%CD Drawing Set
PROCORE>Drawings> Conformed Set
AI\l7A1r:,ilF Ko,rclar 1%1 PanP 1 nr9 Printed On:10/12/2023 06:08 PM
DocuSign Envelope ID:009D958F-F81D-40FC-8A47-6A83F7EB9B34
TM Gu BUILDING PCO #019
Nw
T
ATTACHMENTS:
(A toe NV2A/Gulf Keystar JV
nd rcah Earlanson,Inc.) Key West International Airport
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156
r
e
E
/ DAT
��,, TE AT 4SIGNTl:. DATE GNAT' RE
DocuSign Envelope ID:009D958F-F81 D-40FC-8A47-6A83F7EB9B34
Low Voltage-Systems Total=$800,00 j ta 0.00
Light'Fixture InsUillation $82,500.00
1 1
Fire Alarm System $167,500.00
Low V@15g&SYRFEFs-Pathwa-ys, 7elMOTV, Security,
Access Control, CCrV,, BDA,PA,AN, etc. $132,500.00
Access Cwitrol System $136,854.38:
CCTV System $136,854.38
Complete AV System including all morfitors FIDS, BIDS,GIDS,Etc. $136,854.38
Lig�itning,Protecfion $6,936.86
Amy AecvS-f CopTKO 1_ "rt ADEN D I PK64-4 A M Al N bi j C o M M i S4 t W I IV 6
og AWq Ft5.<o(,I&W0 SortwftKe Hj1kRI)WAj2e*-
"This Change Order Includes Access Control Headend, Programming, Commissioning, as
Indicated in the Conformed Set of Contract Documents Dated May 5, 2023."