1st Change Order 12/16/2023 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 01 Monroe County Detention Center Window Replacement INITIATION DATE: 12/12/2023 CONTRACT DATE: 02/15/2023 TO CONTRACTOR: Strong Tower Construction, LLC d1bla Koch Corporation 1901 South 7th Street Louisville, KY 40208 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)............................................$208,137.00 Net change by previously authorized Change Orders...................................................$ 0.00 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$208,137.00 The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order.......$ 0.00 The new (Contract Sum _(Guaranteed Maximum Price) including this Change Order is.......$208,137.00 The Contract Time will be (increased) (decreased) (unchanged) by.................................. 90 days The date of Substantial Completion as of the date of this Change Order is........................ 03/03/2024 Detailed description of change order and justification: Due to supply chain issues and delays from the window manufacturer, the windows were expected to arrive in September 2023 but did not arrive onsite until December 11, 2023. The Contractor is requesting a no- cost time extension of 90 days in order to complete the project. The prior substantial completion date for this project was December 4, 2023. Change Order is 0.00 %of the original contract price. Not valid until signed by Owner,Architect(if applicable), and Contractor oPuo i sA�y 'F nRg7ig5 1U ARCHITECT: I,'',')avid S III ��'srE� ....���� 1 /'1 123 Bender&Associates Arc..._ _, . .A. Date 1141a11y si,n,l by Robert Yount ON,C=US E=robert yount@7strongMr.corn Robert Yount CON=RobertYount U Protect Manager CONTRACTOR: Date 2023.12.1412 0332 0600 12/14/2 3 Strong Tower Construction LLC Date Digitally signed by Matthew R. Matthew R. Howard Howard PROJECT MANAGER Date:2023.12.15 14:18:25-05'00' Matthew Howard Date Project Management Digitally signed by Kevin G.Wilson, ,f P.E. COUNTY/ASSISTANT ADMINISTRATOR: Date:2023.12.16 12:30:55-05'00' Roman Gastesi Date Kevin Wilson Change Order Attachment per Ordinance No. 024-2015 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: No-cost time extension to project due to longer than expected lead time for manufacturing and delivery of windows. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: STRONG TOWER EXT IO IENVELOPIE WALL SYSTEMS 1901 South 7"Il' Street Louisville, KY 40208 December 12, 2023 Matthew Howard Project Manager Monroe County Project Management Department RE: Monroe County Detention Center Window Replacement Project Mr. Howard, We received a Notice to Proceed -for this 1project on March 8 2023. We subsequently immediately arrainged to imp e the windows and send 1product submittals and sI p drawings -for approval. As soon as everything was approved, we submitted the order -for the windows. At that time we were given a September delivery target date which would Ihave allowed us to complete the 1project in the allotted 270 days. However, in September we received inotice from the inn darer, "Ill olpes", Chat due to a Uass lussue the wluin u l iI aindve HU� December. We received windows on December 11, 2023. Our 270 day 1period expired on December 3, 2023. We therefore request a time extension of 90 days to complete the 1project. Thank You, Digitally signed by Robert Yount RobDN:C=US,Yount YOU E=robert.yount@strongtwr.com, Robert ntO=Strong Tower,OU=Project Strong Tower Manager,CN=Robert Yount Project Manager Date:2023.12.12 09:38:37-06'00' In G( d Akme M I rusL 1901 South Seventh Street-Louisville, Kentucky 40208-1605-(502)636-3571 Phone-www.strongtwr.com