2nd Change Order 01/17/2024 MANAGEMENT CHANGECoNTRAcr ORDER PROJECT TITLE: Card Sound Road Resurfacing Project CHANGE ORDER NO: INITIATION DATE:, 3123/23 TO CONTRACTOR: General Asphalt Co., Inc.. CONTRACT DATE: 3/22/23 The Contract is changed as follows: The original Contract Sum ......................................................................................$2,069,431.24 Net change by previously authorized Change Order ................................................... .. ....... ......$0 The Contract Sum prior to this Change order was.............. .........................................$2,069,431,24 The Contract Sum is increased by this Change Corder#2 ----...................................................$0 The Revised Contract Sum including this Change Order.....................---.....................$2,069,431.24 The Contract Tlme M1 be increased by...... ........................ ................ ......... ...................45 days The Gate of Substantial Completion as of the date of this change order is.,.................................2126124 The Contractor has requested a thane order for 45-da time extension due to Subcontractor scheduling, weather delays, and holiday schedule. The previous,.complietion date was January 12Yh, 2024. The new substantial completion date is February 26111,2024. The project commencement was June 6, 2023. Contractor agrees to accept the increase in monetary compensation and hereby Waives and releases any and all claims for any additional compensation related to these bid items. This Change Corder is(0.001/o)of the original contract price. CONTRACTOR , Date 1' Digitallysigned by Judith Clarke, ENGINE (RING SERVICES DIRECTOR Judith CI rke, P.E. Date:2024,01 A 6 09:17:51-05'00' Date Digitally signed by Kevin G.Wilson,P.E. ASSISTANT COUNTY ADMINISTRATOR � ��" Date:2024.01.1717:21:54-05'00' Date Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ❑ No If Yes, explanation: • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5% of contract price(whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project engineer/architect approves the change order. Yes ® No ❑ If no, explanation of why: NIA • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: