Release of Contingency Funds #090 BOARD OF COUNTY COMMISSIONERS County of Monroe . Mayor Holly Merrill Raschein,District 5 The Florida Keys Mayor Pro Tem James K. Scholl,District 3 h Craig Cates,District 1 Michelle Lincoln,District 2 David Rice,District 4 Memorandum DATE: 12/22/2023 TO: BOCC Digitally signed by Kevin FROM: Kevin G. Wilson P.E. Wilson,P.E. Date:2023.12.22 10:40:28-05'00' SUBJECT: Release of Contingency Funds Included with this memo is the proposed Release of Contingency Funds 490 for the Fl Keys Marathon Airport Non-Aeronautical Use Building (EOC)project. This does not affect the contract amount, but releases contingency funds already included in the Guaranteed Maximum Price for work that was either not foreseen or for which a price could not be determined at the time of contract execution. The amount requested is $1,626.00. The attached Release of Owner Contingency Request provides the details. This is being provided to ensure the BOCC is aware of this change. Please contact me with any questions. If there are none with the normal 24-hour window, I will approve the request. COUrit Of MOrirOe °� � ,�` BOA F UNTY C w � Iss�I 1� s Y Mayor Holly Xlenill Rmchem,District The Florida Keys ��, Mayor " games K. clwh,District Craig Fates,District t Michelle L urcoln,Distict 2 David Ride,District 4 MEMORANDUM DATE: 12/19/2023 TO: County Administrator FROM: Cary Vick SUBJECT: Release of Contingency for: FL KEYS MARATHON AIRPORT NON- AERONAUTICAL USE BUILDING (EOC) Action Requested: Approval for RELEASE of contingency funds in the amount of $ 1,626.00 as outlined below. Basis for Recommended Action: 1. The requested release does not increase the total cost of the project as approved by the BOCC, and it will have no impact to contract time. 2. The scope for which the release is requested is within the intended project scope. 3. The release is not based upon an error or omission by the designer or the general contractor. Background: This is a cost change to the Contingency related to RFI 289, dated 11/28/2023, to furnishing and installing 208V 1-phase power for the fire alarm power supplies in lieu of 120V originally shown, including changing the circuit breaker size in panel ESP. ........................ w .......................................................................................................................................................................... 4' Approved by IMarshallll Quarles 12-20-2023 12/19/"2023 5:03:30 IFINA Ajax Building Company Architects Design Group Cary Digitally signed Digitally signed by Kevin G. I/ by Cary Vicki / _._.._ Wilson,P.E. Vick Date:2023.12.21 B Date:2024.01.08 12:48:24-05'00' 10:07:16-05'00' On behalf of the Kevin Wilson,Assistant County Administrator Director of Project Management Project: FL Keys Marathon Airport Non-Aeronautical Use Building (EOS) (202011 Subcontractor: PEDRO FALCON ELECTRICAL CONTRACTORS, INC. Subcontractor tracking#: Change (RFI #,ASI #, etc): COR-051 Based on RFI 289 FA Power Supply Circuit Breaker Requirements Date: 12/19/2023 Request for Additional Time 1 day. Monday-Friday 7AM-3.30PM LABOR oggntity Units Description unit Cost of labor 2 Hour Forman $ 45.00 $ 90.00 8 Hour Electrical $ 35.00 $ 280.00 8 Hour Electrical Helper $ 25.00 $ 200.00 Labor Subtotal $ 570.00 Labor Burden Percentagel 38% $ 216.60 Labor Total $ 786.60 MATERIAL (SUPPLIER BACK-UP REQUIRED) 0 Units Description unit Cost of Material 0 Feet Fire wall penetration $35.00 $0.00 6 Each 2G J-Box $10.00 $60.00 460 Feet #12 Wire solid $0.26 $119.60 30 Feet 3/4"EMT CONDUIT $1.02 $30.60 3 Each 3/4"EMT Compression COUPLINGS $3.70 $11.10 1 Each 3/4"EMT Compression CONNECTORS $3.00 $3.00 3 Each 3/4 EMT SUPPORTS $5.80 $17.40 1 L.E. Misc.material $25.00 $25.00 0 Each Fire caulk $35.00 $0.00 Material subtotal $266.70 Material Sales Tax 7.50% $ 20.00 Material Total $ 286.70 uantit Units Description Vunit Cost of E/S/U 1 L.E. 21 20A CB $ 355.00 $ 355.00 1 L.E. Freight cost $ 50.00 $ 50.00 Labor Total $ 786.60 Material total' $ 286.70 Subtotal $ 1,478.30 Allowable OH&P 10% $ 147.83 GRAND TOTAL(no pennies) $ 1,626 AjdxAjax Building Company, LLC Project:202011 Monroe County FL Keys Marathon 109 Commerce Blvd Airport NAUB EOC Oldsmar, Florida 34677 7280 Overseas Highway P: +1.1379239.. Marathon, Florida 33050 RFI #Con-289: FA Power Supply Circuit Breaker Requirements Status Closed on 11/28/23 To Mickey Pruitt(Architects Design Group) From Jeffrey Whipple(Ajax Building Company, LLC) Devon Ayers(K2M Design) 424 SW 7th Terrace Gainesville, Florida 32601 Date Initiated Nov 8,2023 Due Date Nov 13,2023 Location Project Stage Course of Construction Cost Impact TBD Schedule Impact TBD Spec Section Cost Code Drawing Number Reference Linked Drawings Received From Ihor Rymaruk(Pedro Falcon Electrical Contractors, Inc.) Copies To Giselle Albisu(TLC Engineering Solutions(Jax)),Victor Carrasco(TLC Engineering Solutions(Jax)), Donald Harcrow(Ajax Building Company, LLC),Cary Knight(Monroe County),Travis Mauldin(Ajax Building Company, LLC),Juan Perez(TLC Engineering Solutions(Jax)), Marshall Quarles(Ajax Building Company, LLC), Banistka Rodriguez(Architects Design Group), Jordan Salinger(Monroe County), Denise Saltzman(TLC Engineering Solutions(Jax)),Steven Sanders(Monroe County), Daniel Taylor(Architects Design Group), Cary Vick(Monroe County) Activity Question Question from Jeffrey Whipple Ajax Building Company,LLC on Wednesday, Nov 8,2023 at 11:28 AM EST There are currently 2 power supplies needed for the Fire alarm.One dedicated 2-pole 20Amp circuit breaker can feed both of these power supplies.After meeting with our FA subcontractor,we confirmed that these power supplies will correctly function on 208V as opposed to the 240V shown on the cut sheet. Based on this information,we recommend making the following changes to Panel ESP: 1. Move the ATS annunciator panel from CK#70 to CK#11.This will free up CK#'s 70 and 72 for the 2-pole 20Amp Circuit breaker. 2. Use CK#9 for FA panel and amplifier. See attached RFI-289 Sketch and advise if moving the ATS annunciator panel to CK#11 and utilizing CK#70 and 72 for the FA power supply is acceptable. Attachments RR-289 Sketclh.pdf Official Response Response from Devon Ayers K2M Design on Tuesday, Nov 28, 2023 at 08:47 AM EST See attached. Attachments 120825,._.Response,._.RFV Coin-289 FA Poweir Supply Circuit Bireakeir Requiiremeints.pdf Ajax Building Company, LLC Page 1 of 1 Printed On: Nov 28,2023 09:36 AM EST I�1110��VlWlii�� �pIJ}�N!IIII�Nyc E N G I N II ih R 1 l 4 G �Wr 0 1- L,I r I o I`I s,,, RFI Response Con-289 RFI# Con-289 Reviewer: Victor Carrasco Project: 120825 - MONROE COUNTY EOC Received: 11/08/2023 Name: FA Power Supply Circuit Breaker Requirements Returned: 11/28/2023 Please Note: The following RFI response is not intended to authorize any deviation or modification to the design documents except as specifically clarified below for this specific application and circumstance. Furthermore, this response is not intended to authorize any increase in construction cost, schedule or time extension, or construction in conflict with any applicable codes or specified design standards. It is the responsibility of the Contractor to notify the design team immediately of any perceived scope, schedule, or cost impacts or adjustments. Attachments 1 RFII Con.289 FA Power SD I. Circuit Bir lker uiiiremei�ts II D.pdfl a ..... Questions Attached is RFI Con-289 FA Power Supply Circuit Breaker Requirements for your review. Comments TLC takes no exception to the proposed 2-pole, 20A circuit breaker at ESP-70,72 based on the fire alarm power supplies' electrical characteristics confirmed by the Contractor. Page 1 of 1 Saltzman, Denise From: Carrasco,Victor Sent: Monday, November 27, 2023 2:16 PM To: Saltzman, Denise Cc: Perez,Juan Subject: FW: Monroe EOC RFI 289 Update (TLC 120825) Attachments: RFI-289 Sketch.pdf Hi Denise, Hope you had a nice Thanksgiving weekend. Would you please replace RFI 289 in our Procore with the attached updated RFI per the Contractor's email below? Please let me know once it's updated for me to provide a response and close the RFI on our side. Thank you, Denise. Victor E. Carrasco Associate I Project Manager I Electrical C.`ailo°m„�a t: 305.263.3892 Cidk 305.439.6782 iirlaii:.;victor.carrasco@tic-eng.com E011 r I r4I E R Dl Je. 5757 Blue Lagoon Dr.,Ste 400 Miami,FL 33126 From:Jeffrey Whipple<Jeffrey.Whipple@ajaxbuilding.com> Sent:Wednesday, November 22, 2023 11:54 AM To: Mickey Pruitt<mickeyp@adgusa.org>; Devon Ayers <DAyers@k2mdesign.com>; Carrasco,Victor<victor.carrasco@tic- eng.com>; Perez,Juan <juan.perez@tic-eng.com>; Vick-Cary<Vick-Cary@monroecounty-fl.gov> Cc: Marshall Quarles<Marshall.Quarles@ajaxbuilding.com>;Travis Mauldin <Travis.Mauldin @ajaxbuilding.com>; Donald Harcrow<Donald.Harcrow@Ajaxbuilding.com> Subject: Monroe EOC RFI 289 Update This Message Is From an External Sender This message came from outside your organization. Please remember to never enter your TLC credentials into any links from outside the organization. Team, we have recently updated RFI 289 with the following changes: 1. The previous version requested 2x 2pole breakers to feed the two FA power supplies but in reality we only need 1 which was updated on the most recent version. 2. The new version contains a suggested solution to fitting the new 2-pole breaker in panel ESP by relocating the generator annunciator circuit.This is where all the other FA equipment is fed from. (see attached sketch for clarity) Please replace the old version of RFI-289 that is currently under review with the new version. Call me with any questions or concerns and have a great Thanksgiving. Respectfully, Jeffrey Whipple Assistant Project Manager Ajax O: 850-224-9571 C: 813-455-4697 E: ..................................ir .... J�.i..I .I II. .. .. .U. 11 uiHdi'ir�. .. purr.. 5901 College Rd. Key West, FI. 33040 AjdxAjax Building Company, LLC Project:202011 Monroe County FL Keys Marathon 109 Commerce Blvd Airport NAUB EOC Oldsmar, Florida 34677 7280 Overseas Highway P: +1.1379239.. Marathon, Florida 33050 RFI #Con-289: FA Power Supply Circuit Breaker Requirements Status Open To Mickey Pruitt(Architects Design Group) From Jeffrey Whipple(Ajax Building Company, LLC) Devon Ayers(K2M Design) 424 SW 7th Terrace Gainesville, Florida 32601 Date Initiated Nov 8,2023 Due Date Nov 13,2023 Location Project Stage Course of Construction Cost Impact TBD Schedule Impact TBD Spec Section Cost Code Drawing Number Reference Linked Drawings Received From Ihor Rymaruk(Pedro Falcon Electrical Contractors, Inc.) Copies To Giselle Albisu(TLC Engineering Solutions(Jax)),Victor Carrasco(TLC Engineering Solutions(Jax)), Donald Harcrow(Ajax Building Company, LLC),Cary Knight(Monroe County),Travis Mauldin(Ajax Building Company, LLC),Juan Perez(TLC Engineering Solutions(Jax)), Marshall Quarles(Ajax Building Company, LLC), Banistka Rodriguez(Architects Design Group), Jordan Salinger(Monroe County), Denise Saltzman(TLC Engineering Solutions(Jax)),Steven Sanders(Monroe County), Daniel Taylor(Architects Design Group), Cary Vick(Monroe County) Activity Question Question from Jeffrey Whipple Ajax Building Company,LLC on Wednesday, Nov 8,2023 at 11:28 AM EST There are currently 2 power supplies needed for the Fire alarm.One dedicated 2-pole 20Amp circuit breaker can feed both of these power supplies.After meeting with our FA subcontractor,we confirmed that these power supplies will correctly function on 208V as opposed to the 240V shown on the cut sheet. Based on this information,we recommend making the following changes to Panel ESP: 1. Move the ATS annunciator panel from CK#70 to CK#11.This will free up CK#'s 70 and 72 for the 2-pole 20Amp Circuit breaker. 2. Use CK#9 for FA panel and amplifier. See attached RFI-289 Sketch and advise if moving the ATS annunciator panel to CK#11 and utilizing CK#70 and 72 for the FA power supply is acceptable. Attachments RR-289 Sketclh.pdf Awaiting an Official Response Ajax Building Company, LLC Page 1 of 1 Printed On: Nov 27,2023 04:02 PM EST • ®1111111111®111111111111111111111 a0000000000m00000000000000000000000a II�II�II�II�II�11�11�11�11�11�11�11� �I�11�11�11�11�11�11�11�11�11�11�11�1� �����IIIIII ��I1�11�11�11�11�11�11�11�11�11�11�11 �II �I1�11�11�11�11�11�11�11�11�11 . m®omm mmmmmmmmmmmmmmmmmmmmmmmmmmmmmm mmte• ®mmm®mmmmmm®®mmmmeee®®m00000 = tN h �y �• a ,. k�� llr���✓a J f �' i a � i mUw�wiNmort rc��a' � jai miowwwam r��.uuewww� � t � �i� „ fig ,�Y n3 w w m�w�a um nm xm�q w.un °rvuircxm a�rvevnsa ms n°e wwuw u/¢/ Nva� a�aobe occ ceroolosaa � ^�*°��"°��^""a��,x,ud""�° /A69 O6O 116O1�3xOxd _ xivavw °3wmx°«.°.ur°°,nm:a°s�" .—� �s `°°'°`"^""°"'°"""'°`"` ZOM Ii'xO1x1Otlx9 .o- inns .—� nn a xaa.ntao'UHAVS Dl'lana asaan000as ��/� aom Noarapscesv� 07 NV'Id YS2IV1V d2IL3 W sxou.vxao aoNaDxaysa wav,v saNave V on'oxulnsxooa 2I00'I3.LSiIL3 ONIx33NI0x3 OtN , w a'os0El 0 4 11, a m b b 0 -T 3 m s w a I R3�•�j R R6 j 6 RI "! 3 aIN R IN R 1 m a 'N IN IN Z ,i! 2L Q. - a CL ,R W In R i — a, 3 w 0 ® ry Q- d3 3 _1, R / - I m >� y � m W o 3 ,, i