Change Order No. 2 MEMORANDUM TO: Board of County Commissioners From: James L. Roberts County Administrator Date: October 17, 2003 RE: Change Orders Attached is a proposed change order for D.L. Porter Constructors, Inc. for Demolition of the Public Service Building for approval. According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. ~~ a2/ The Administrator intends to approve this change order on~, October-d;' 2003. ~D"J: .James L. Roberts County Administrator MONROE COUNTY CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Demolition of the Public Service Buildinq on Stock Island CHANGE ORDER NO: 2 Total Previous Change Orders Current Change Order Original Contract Amount Revised Contract Amount Change in Contract time $(14,000.00) $ 29,222.00 $407.700.00 $422.922.00 5 days Detailed description of change order and justification: This cost is for the unforeseen condition involvina the additional work required to remove a buried concrete diesel fuel tank which fueled the furnace that was used for the cremation of bio- waste and must be removed. cleaned out and the tank demolished. The tank weiahs 90,000 ounds and FDEP re uir ents must be followed for tank closure. CONTRACTOR: be November 20 2003 COUNTY ENGINEER: /Chani David . Koppel, P.E. . /1) DIRECTOR OF PUBLIC WORKS: !W~~ COUNTY ADMINISTRATOR: D~ James L. Roberts -- '7 .' ...)0 - J"j Date i/?c/6? Date /~- ~-co Date CMD007 -1/3/97