01st Change Order 10/23/2003 MEMORANDUM TO: Board of County Commissioners From: James L. Roberts County Administrator Date: October 17, 2003 RE: Change Orders Attached is a proposed change order for D.L. Porter Constructors, Inc. for Renovation of the Old Mariners Hospital for approval. According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. -r/n/.L::f ~ The Administrator intends to approve this change order on.Iuc3Jav; Octobe~ 2003. ~~ James l. Roberts County Administrator MONROE COUNTY CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Renovation of the Old Mariners Hospital CHANGE ORDER NO: Total Previous Change Orders Current Change Order Original Contract Amount Revised Contract Amount Change in Contract time $0,00 $15,800.00 $2,829,600.00 $2,845.400,00 -0- Detailed description of change order and justification: [2~ c- 1t/tJ'! o!::> V Pro,Qosal Request No 3 is for site revisions because the Villaqes of Islamorada have requested that the heljpad at the Mariner's site remain. this request is for site plan revisions to include additional parkina by removinq metal buildinqs, ~ DIRECTOR OF PLANNING & CO ST.: (] ~ni COUNTY ENGINEER: d~ r Da . S. Koppel, P.E. DIRECTOR OF PUBLIC WORKS: ~ L0~ Dent Pierce COUNTY ADMINISTRATOR: = ~~ James L. Roberts CMD007-l/3/97 .'-7' . . ;, c::- c-_ -0.3 Date OI/VbJo,? Date 9'30-()~ Date /O/ls/o3 ( Date /0 - .2..tt--tl:3 Date Change Order Attachment per Ordinance No. 004-1999 · Change Order was not included in the original contract specifications. Yes X No 0 If Yes, explanation: · Change Order was included in the original specifications. Yes 0 No X If Yes, explanation of increase in price: · Change Order exceeds $25,000 or 5% of contract price (whichever is greater), Yes 0 No X If Yes, explanation as to why it is not subject for a calling for bids: · Project architect approves the change order. Yes X No 0 If no, explanation of why: · Change Order is correcting an error or omission in design document. Yes ONo X Should a claim under the applicable professional liability policy be made? Yes 0 No X Explain: HP Fax Series 900 Plain Paper Fax/Copier Fax History Report for James L Roberts Co Admin 305-292-4544 Oct 21 2003 3:23pm Last Fax Date Time ~ Identification Duration Pages Result Oct 21 3:22pm Sent RICE 0:59 3 OK Result: OK - black and white fax HP Fax Series 900 Plain Paper Fax/Copier Fax History Report for James L Roberts Co Admin 305-292-4544 Oct 21 2003 3:21pm Last Fax Date Time ~ Identification Duration Pages Result Oct 21 3:20pm Sent NELSON 1:06 3 OK Result: OK - black and white fax HP Fax Series 900 Plain Paper Fax/Copier Fax History Report for James L Roberts Co Admin 305-292-4544 Oct 21 2003 3: 14pm Last Fax Date Time ~ Identification Duration Pages Result Oct 21 3:06pm Sent McCOY 1:45 3 OK Oct 21 3:07pm Sent NELSON 0:00 0 No answer Oct 21 3:09pm Sent RICE 0:00 0 No answer Oct 21 3:11pm Sent SPEHAR 0:50 3 OK Oct 21 3:12pm Sent NEUGENT 1:29 3 OK Result: OK - black and white fax PROPOSAL REQUEST AlA Document G709 . ~M~ PROJECT: Old Mariner's j1~GfN~ (Name and address) 50 Highpoint Road Plantation Key, FL no { ,A ,0/ n""J "___ l"r vJ .fl.~".Q..i ARCHITECT CONTRACTOR FIELD f ----- c o o C':=~~ PROPOSAL REQUEST NO.: TIrree (3) OWNER: (Name and address) Momoe County 1100 Simonton Street, Key West, FL 33040 DATE OF ISSUANCE: July 18, 2003 CONTRACT FOR: Construction CONTRACT DATED; March 19,2003 Monroe County Sheriff 5525 College Road Key West, FL 3~040 ARCIDTECT'S PROJECT NO, 0102 CONTRACTOR: D.L. Porter Constructors, Inc. (Name and address) 6574 Palmer Park Circle Sarasota, FL 34238 ARCIDTECT; Bender & Associates Architects, p.a. (Name and address) 410 Angela Street Key West, FL 33040 Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein, Submit proposal within (5) Five days, or notifY the Architect in writing of the date on which you anticipate submitting your proposal. THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK ~T)ESCRIBED IN THE PROPOSED MODIFICATIONS. Description: (Insert a written description of the work) Site Plan modifications are required in order to accommodate a request from the Village of Islamorada _ Fire Chief to retain the helipad south of High Point Road. Sheet Al is revised and reissued with a date of 0718/03. Provide pricing to provide the modification s shown described in general as follows: 1. Revise all parking and landscaping shown on the revised site plan, Leave the helicopter landing pad, fencing and landscaping as it currently exists, 2. Demolish the metal building directly south of the sewage treatment plant and the metal building directly east of the current construction office building, removing foundations as required, but not less than 12" below finish grade. 3. The total nwnber of plants and other landscape materials as previously bid will remain the same, however, they will be redistributed into revised landscape areas as shown on revised site plan. 4. Landscape sprinkler system will be required to provide 100% coverage of landscape areas, including area surrounding new parking south of Highpoint Road. Attachments: (List attached documents that support description) Sheet Al Revised 07/18/03 Sheet DI Revised 07/18/03 )E~~ ~ ~ . /-,# (Si(nature) Matthew Stratton, Architect (Printed name and title) 89(11/2083 0S:44 9419299500 IL PORTER P~GE 8l./01 Scptemba 11, 2003 VIA FACSJMILE (305) 296-2727 Bert Bender Bender & Atlsociates 410 Angela St. Key West, FL 33040 RE: Old Mariner's Hospital- Plantation Key Sheriff's Substation Response to Proposal Request: Three (3) Dear Bert: Upon review of tne plans provided with the propo:ull request referenced above we offer the following; I. Revised site plan changlllS related to the modified parking lot layout, il1stalJing a new set of concrete steps leading to rear structure to remain, leaving the helicopter pad and associated fencing as indicated. Add $1,000 2. ,Demolish and remove from the site the two (2) metal bUildings towa.rds the rear of the property anowing for th,e newly proposed parking lot, Include<l would oe the removal of all a:!lsociated foundations to a maximum depth of 12" asindicatcd in the RFP.. Add $14,800 3. Landscape revision limited to the relOOlltion of prt'fiou:!lly laid out materials. No additional material considered. AddlDerluct .O~ 4. Irrigation system revised to :include 100010 coverage of all landscaped areas including revised parking lot south o(High, Point Road. AddlDcduct.o- By copy of this letter should the owner decide to implement the changes referenced in RFP Three (3) the contract Add would be $15,800. If you have any questions~ please give me a call. STRUCTORS. INC. GAUpj cc: Stephanie Coffer Don Miner Bill Sprague Kevin Groner File 6574 Palmer Park Circle · Sarasota, Florida 34238 · (941) 929-9400 . Fax (941) 929-9500 7 ,( J'3 [1 ::3 / l 10:17a Kim Sprague 3052946121 p. 1 rD'. ~ ~o<;" -gs ~.- ~ Zo os- H(O"\ '.~tL'- Sf~ 0.1.,. PORTER CONSTRUCTORS, rNC. 657<4 ,:1\LMER PARK CIRCLE. SARASOTA, FL 34238 941--!1: 9-9COO FAX 941~29-9S00 --- --- ~ '-'- Po;;~it'" F~'x Note To U- '5 C<> JOe pl. 7671 Dale la86!'S'" TO: Bert Bender Bender & Associates VIA FACIMILE @ (305) 296--2727 FRClII: Gary loer DA.TI:: June 3.2003 Phone :: RE: Old Mariners Hospilal Renovation Additional Demo/ilion il'" ':!l~ r tH'H'~";:l ~I! r ~~,~U~f~~ ~ ..~ ~'~'l ~~ "'" Fax Letter I Transmittal Bert Durin;; our initial site coordination meeting Jenny Bell- Thompson asked us to provide a price to have a coup~:. additional structures removed "om the sire. The following prices are provided for your review; To remove lhe e,;isting laundry building to the existing stab - $ 4.600 To remove the slab and foundation below the laundry buHding - $ 3.200 To remove the existing Maintenance building lo the slab - $ 4.300 To remove the slab and foundation below1he Maintenance strudtJro - $ 2,700 · We .' ave included $200 per building for demolition permils should additional fees be required those cost would be considered an extra. Further, if it is your intent fo remove tile slab and tounda1ions please add $1.00C per building for bac:kfilling and compaclfon. It asked to proceed with !he worlt wilh;n 1he next fourtel: n (14) days no additional time will be required, JeS~:~~lIVI D,L .;;~rCOnslruc:lo1'3. Inc. '1 II , leer Presuhnt cc: SII! pl1anie Coffer 1114, <i{f) . OU .---- -~1Jf 1 ~-t' (j ~ ' '.-, L ,([ JLA-.. ~, u.'1'- 2rI7/\ ~V~ .-P UfU t:C ,-- SIv-'ct6 lJUC C/t6e In 111lf}7i~' ~JhCl/1L u- jL A-M( d - 4-5~5'6~ IOO~ S:o:JJ.\'IOOSSV 'lI MHUN39 LZ l.t: 9BZ SOi: xv,,) ll: n 1:007,/1:1/90