1st Change Order 12/21/2023 MONROE CO1 TT / NGtNEERtNG/PRO AwGE tEN t
CONTRACT CHANGE ORDER
PROJECT TITLE: EYW Runway 9-27 Repair CHANGE ORDER NO: 1
INITIATION DATE: 12/19/2023
TO CONTRACTOR: Ranger Construction Industries, Inc. CONTRACT DATE: 07/19/23
The Contract is changed as follows:
Theoriginal Contract Sum ............................................................................. ..........$ 1,576,088.00
Net change by previously authorized Change Order ... $ 0.00
The Contract Sum prior to this Change order was............... . ..... $ 1,576,088.00
The Contract Sum is(decreased) by this Change Order ($ 10,000.00)
The Revised 1 Contract Sum including this Change Order ... ........................................ $ 1,566,088.00
As noted in the original contract documents, and incidental to pay items P-101 and P-401„ the contractor was required to
temporarily remove and reaffix the runway edge lights each night of operation to protect them from nightly construction
activity.. The contractor submitted 1pl 03 requesting that the contractor protect the runway edge lights with barricades in
lieu of temporary removal. Jacobs approved the request with condition that a credit be made to the final close-out price.
This change order, Change Order No. 1, includes a $10,000.00 credit to the final close-out price for an alternate plan to
protect the runway edge lights.
The total cost to complete the work as noted within this change order is a decrease of$10,000.00 to the final close-out
price. See attached credit confirmation email from Ranger Construction Industries, Inc.
Net change to contract Change Order 1 ($10,000.00)
The project commencement was November 11, 2023
This Change Order 1 increases contract time by 0 calendar days.
Contractor agrees to accept the decrease in monetary compensation and hereby waives and releases any and all claims for
any additional compensation related to these bid items.
This Change Order 1 represents 0.0063% decrease of the original contract price.
Not valid until approved by Owner Architect if a licable and Contractor
ARCH ITECT/ENGINEER�m® 12.1910
23
Date
12/19/23
CONTRACTOR
Date
` 12.20.23
AIRPORTS DIRECTOR,
Date
COUNTY/ASSISTANT ADMINISTRATOR I µ 12.21.2023
Date
NFIOE COUNTY ATTOnNEY
A )LOVE T FORM
ASSt;qC&UJN'1WY'ATTORNEY
Date 12/20/23
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
1. This change-of-work credit is based on a contractor request, requested after the release of the Issued for
Construction document set.,
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price: N/A
• Change Order exceeds$25,000 or 5% of contract price(whichever is greater). Yes❑ No
If Yes, explanation as to why it is not subject for a calling for bids: N/A
• Project engineer/architect approves the change order. Yes ® No ❑
If No, explanation of why: N/A
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: