1st Change Order 02/08/2024 MoNROE CouNTyr/DEPARTAUNT OF AIRPORTS
CON" CT CHMGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 1
Relocate Automated Surface Observation System(ASOS)
INITIATION DATE: January 19,,2024
TO CONTRACTOR: CONTRACT DATE: April,20 ,2023
Pedro Falcon Contractors,Inc.
The Contract is changed as follows:
The original(Contract Sum) (Guaranteed Maximum Price).......................................... $1,270,969.65
Net change by previously authorized Change Orders.................................................. $ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$1,270,969.65
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)
(unchanned)by this Change Order—....$ 0.00
The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is....... $ 1,270,969.65
The Contract Time will be(increased)(decreased)(unchanged) by............................... 144 days
The date of Substantial Completion as of the date of this Change Order is....................... April 15, 2024
Detailed description of change order and justification:
This change order is to accommodate extended lead times encountered for electrical items being
unavailable from the manufacturer.Currently the final delivery date for the last of the electrical
items is projected to be at the end of February 2024.
This change Order is 0%of the original contract price.
Not valid until signed by Owner,Architect if applicable), and Contractor
ARCHITECT: 1/30/24
Date
CONTRACTOR: I 'AD
A
Ulgltalty by PIW rd 5WCMantlDa/ee-
1,—
ON:m=NkM1astl Sklc4land,o-Mon,oe County BOCC,
Richard Strickland ou=Manure County Plrpans,email=9tlMlantl-
DIRECTOR OF AIRPORTS D--24^�^�223a�^°N
s ..... Date
MONROE COUNTY: �
� w 02.08.2024
sst./County'Ad nist ator Date
Ar�E COUNTY ATTORMA
RNEY
ASSiSTA UNTY ATTORNEY
Date 2/2/24
Change Order Attachment per Monroe County Code Section 2-58(b)
• Change Order was not included in the original contract specifications. Yes( ) No( X)
If Yes, explanation:
- Change Order was included in the original specifications. Yes ( ) No (X )
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes()No(X)
If Yes, explanation as to why it is not subject for a calling for bids:
- Project architect approves the change order. Yes( X) No ( )
If no,explanation of why:
- Change Order is correcting an error or omission in design document. Yes O No (X )
- Should a claim under the applicable professional liability policy be made? Yes( )No( X }
Explain:
PEDRO FALCO�N
CONTRACTORS, INC.
31160 Avenuei in 1
(3 7 m Fax(g )872-2219
EC 13003416/CGC 1507617
.__. www.pedrofalcon.com
Request for Change Order
19 January 224
Project: Relocate Automated Surface Observation System(ASOSI
Change Order Request No: 001
Description:No Cost Cbp e Order
This No Cost Change Order Request is to accommodate extended lead times encountered
for electrical items being unavailable from the manufacturer.Currently the final delivery
date for the last of the electrical items is projected to be at the end of February 2024.
Recent experience for similar electrical items and projected factory delivery dates
indicates that the date provided by the manufacturer can change at any time.
PFC requests the contract end date be extended until 15 April 2024
to allow for receipt of delayed materials and installation of same after receipt.
Net Amount of Request for Change Order:...........»...............................................$0.00
Respectfully Submitted,
Ken Bygler
Project Manager
Jacobs
Change Order#1 -Acceptance
Ryan Forney, Senior Project Manager
1/26/24
11Page