Item C15 C15
BOARD OF COUNTY COMMISSIONERS
COUNTY of MONROE i Mayor Holly Merrill Raschein,District 5
The Florida Keys Mayor Pro Tern James K.Scholl,District 3
Craig Cates,District 1
Michelle Lincoln,District 2
' David Rice,District 4
Board of County Commissioners Meeting
April 17, 2024
Agenda Item Number: C 15
2023-2349
BULK ITEM: Yes DEPARTMENT: Project Management
TIME APPROXIMATE: STAFF CONTACT: Kevin Wilson
n/a
AGENDA ITEM WORDING: Report of monthly change orders for the month of March 2024,
reviewed by the County Administrator/Assistant County Administrator.
ITEM BACKGROUND:
There were eight(8) change orders considered and approved by the County Administrator/Assistant
Administrator for the period beginning 03/01/2024 and ending 03/31/2024 for a total of$48,219.42.
There were no change order requests denied.
PREVIOUS RELEVANT BOCC ACTION:
On September 9, 1998, Ordinance No 027-1998 was adopted in order to provide that the County
Administrator may approve separate, non-cumulative change orders for construction projects and
professional service contracts in amounts not to exceed $50,000 (as amended per Ordinance No. 024-
2015), or 5% of the original contract price, whichever is greater. The BOCC requested a monthly report
of all change orders considered by the County Administrator.
INSURANCE REQUIRED:
No
CONTRACT/AGREEMENT CHANGES:
N/A
STAFF RECOMMENDATION: N/A
DOCUMENTATION:
Change Order Rpt_Apr 202 .pdf
906
FINANCIAL IMPACT:
N/A
907
O m
3 0) N O
C Ln N
V api 01
Ou C
C
O_ m Ln O- i OV .Q
V m 0) 0) a
3 O 0 +� E u E
w oo aa) o a) .0) U o
Vo w (n LL J (n
3 � o W to N N ko
7 0 a a a a a
a) a) �' a a a a a
a M O a) O O O O O O
p C C _
T O 2 O O O O O O
a) O a-
-
C C C C C C
E v a) O O O O O O O O
C fa 3 O f0 f0 f0 f0 f0 f0
a'' VVVVV f0V
U a) o C C C C c: 3 C
a) O O O O O -p O
W V Q N Q N
W W
LLIQ Ln� LL O
N � WO LL QN N N N N N
LU Q C) C) C) C) C) Q
(' N � Zo M O � Zo 0 0 0 0 0
Z LU
OC N U C7 U
_ 74 Z
V a c+n a
VM V V V V V V u V Ni
O
O Z Z 7 7 7 7 7 C 7 V
W W O a � a a
I H a) o � m a a a a a $ a G1
O H M 0 P C) o � o 0 0 0 �
O
66 a 0 a o � ou o 0 0 0 � N
IL c x � � 0a o2 0 0 0 �; 0Q
Q a) Q C fu C vim' c � c o) c C 'n
Z N co
U a) QU O O oc oc o o
Oa V) a) E Ln � E � � -2 E
rl W +� W W o L) o o` o C o o .. o o`
+� — — — 2)
~ 0 -0 0 Q Q C - C C LL— C zz. C 3 C
Z E v V W 00 00 0ko $ N $ o $ �o t
Ma) O O N
O O � w
ZW D Z oo O ~ r, Ln
'� w/ 0 Z W o 0) C) N
O W ko o > > o 0 0 o rn ni P; O
U m W M ' M
Z H 4 m ko � O J
yr
WH a LU O
013� �
W G LL
O v OC O 0)
W U O
Z �+
Z O U U U U U U U U 3
OV J J O J J J J J J
C J J J J J J
(� O E = O C C C C C C
C: f0 f0 f0 f0 f0 f0 f0
a) �
J a) O O O O O O
U U U U U U
Q 0) 0) 0) 0) 0) 0)o
Z cOa Z o 0 0 0 0 0
V O W V Co m m m m m
C x x x x x x
� n3 n3 n3 n3 n3 n3 n3
0 Q Q Q Q Q Q
c C c c c c
C O O .Y .. O .Y .. O Y .. O Y O Y .. O u ..
a) a) O o OU OU OU O � OU OU
n30 n30 n30 n30 n30
w n30
c C w C w C C w C w C w
a — V N Ln Q Ln Q Ln Q Ln Q Ln Q m Q
7 p
a = S 0 m d QI Y 0 .5 Y 0 .5 Y 0 .5 Y 0 .5 Y 0 .5 Y 0 .5
N a) OZCO OZCO OZCO OZCO OZCO OZCO
0) M a a) a tf a) -a tf a) -a tf a) a a) a a)
.n L`L .n ` ` n ` n ` nU D D D D D
LL
Q Q Q Q Q Q
908
MONROE COUNTY FACILITIES MAINTENANCE
CONTRACTL ORDER
PROJECT TITLE INITIATION DATE: February 26, 2024
Harry Harris Ballfield Lighting Upgrade CHANGE ORDER NO: 1
CONTRACT HATE: October,18, 2023
TO CONTRACTOR:
Musco Sports Lighting, LLC
100 First Avenue (Nest
Oskaloosa, Iowa 52577
The Contract is changed as follows:
The original (Contract Surma) (Guaranteed Maximum Price).-.............--................ $372,500.00
Net change by previously authorized Change Orders.. ................. . 0.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$372,500.00
The (Contract Sum) (Guaranteed Maximum Price)will be increased by this Change Order.,$3„666.00
The new(Contract.Sum)_(Guaranteed Maximum Price) including this Change Order is.......$376,166,00
The Contract Time will be unchanged................. ........................................ ............ 0 Gays
The date of Substantial Completion as of the date of this Change Order is... ...................N'JA
Detailed description of change order and justifiication:
Contractor applied for and paid the permitting fees. This change.order is for rei m bursernent of the
yermittina fees without ark-up.
This change order is 1% of the original contract price.
Not valid until sicined bv Owwner.Architect if a liicable and Contractor
ENGINEER: N/A
Date
CONTRACTOR; "
Digitally signed by John Da,e
#.Jlnhn'Allen Dlate 2024.02.28
DIRECTOR PARKS AND BEACHES _ J53255-05'00'
Digitally signed by Kevin Date
G.Wilson,P.E.
Date:2024.03.01
COUNTY/ASSISTANTADMINISTRATOR: 13:48:41-05'00'
Kevin Wilson Date
909
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in,the original contract specifications. Yes& No E]
If Yes, explanation: A permit was required for the electrical work. The contractor applied for the
permit and paid the permitting fees.
• Change Order was included in:the original specifications. Yes El No
If Yes, explanation of increase in, price:
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes El No0
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes 0 No&
If no, explanation of why: Architect was not required for this project.
• Change Order is correcting an error or omission in design document, Yes E—]No(@
Should a claim under the applicable professional liability policy be made? Yes n No K9
Explain:
910
Corporate; 100 1st Ave West PO Box 808 Oskaloosa, IA 52577 641/671-1411 . 800/8 5-6020 Fax:866/9;0-6190
Web:WWWAIUSCOXO �xr it ti t�tirt r���r ccw.r:c�rr�
C ,�. u
MUS
CHANGE ORDER REQUEST
Cate: February 26, 2024
Change Order#: 1
Contract Fate: October 18,2023
Project: hurry Harris Park Baseball Relight.
To: Monroe County
The contract is changed as followers:
- Permit fees
Original Contract Sum: $372,666,
Net Change by Previous Change Orders: $6.60
Contract Price Prior to This Change Order: $872,660
Change Order amount: $3,666
New Contract Sum Including This Change Order: $876,166.00
Monroe County Musco Sports Lighting, LLC
Signed: Signed:
awL
Monroe County ,losie Sanger
500 Whitehead Street P.O. Box 808
Key West, FL 88040 100 1 st Ave West
Oskaloosa, IA 52577
66 -999-419C
Lighting . . . 'fie Make it Happen.
M-4037-enus-4
911
(7
d�
U 1-h Rd
w
Permit _ < . ....
-ELEC-202 -008
Commercial Electric Permit
50 E BEACH ROAD
TAVERNIER, Florida 33070
Flood Zane All
Conditions- 1
Fees and Payments
Overview
Total Fees 3,666.24 US
Property Information
Total. Payable 3,665. 4 USIA
Workflow Total Paid 3,666,24 USf
Balance Date 0.00 UST
Kermit Information
inspections `parc r 0
No items to display..
Communication
Related Transactions
912
;. MONROE COUNTY BUILDINGDEPARTMENT
PAYMENT RECEIPT
�o ou�yNt �giur tll,G iiW"" ,;� r far ����u 1ptWfTrans,Id:
7q p—Histm Key OW378
ftof fd EPA '2p7.�U 206TI9431f30"f92
Dra wor; Ceohlor.
Payment Received By. Charles Floyd
Payment Amount: $2530.10
Sawles Fee Amount: $«73.30 0368711630e5 VISA
APPLICATION DETAIL
p11 'onr IC1. - ) -2i 4 9 Applicant,"RLE FLOYf3
Sfto Address,City, 60 E MACH ROAD,TAVERMER PmvW JD-0008942 0
Owner Name SOARO OF COUNTY CCI@Alh4flSall7N£R$
City,% KEY WEST,FL
1 ANOW
Witting Code Admin 8 Inop FL ftroberge Retained $3.42
Planning Permit Fee $900.00
Oulldfng Education Fee $440
Florida BuAding CornmWon FL Surcharge Retained $2,20
Building Pomwn t Fee Selanoe $1,1 6.06
Fire Permit Fee $422.20
Contrsctor tmrestoodon Fee $11.00
SulHfing Code Admin&,lnsp FL 6ur7ohergo $30.7
Florida Building Commission FL Surclwarge $20A
�a
1q
February 6.2024
913
vayment l ec ipt ' ,
Fron'ia donotreply@srappaYrgb'obal.com (dono reply sna;ppayglob l.coirn) ° ,` ,fir,-�3
1b: ecsinc25@aoLcom
Late: Wednesday, Decermber 27, 2023 at 09:32 AM F T
ll „�
Payment Receipt
Merchant Monroe County Building Department, Monroe County Building Department Online,
305453876
Account 1000519896 - Monroe County
Customer 3606000 3730761' - Charles Floyd
Transaction 1,136. E
Amount
Fee Amount 32.9E
Total Amount 1,169,01
Paid an 1 / 7/ 6 3 8:31:08 Al l
p'aym nt Su ma
'VISA 5133 361453°734 691 1,136.06 03289 Transaction successful.
Service tee has been charged as a separate transaction.
Click here to Sign In to `-n,apPay.
Contact Information
Te1:(888)888-8888
Emai1:��
.........__._._. 914
MONROE CouNTY/ENGiNEERiNG/ PROJECT MANAGEMENT
CONTRACT CHANCE ORDER
PROJECT TITLE: CHANGE ORDER NO: #002
Marathon Professional,Center Building INITIATION DATE: 3/13/2024
Roof Replacement CONTRACT DATE: 06/1712023
TO CONTRACTOR.
Dan Enterphses Tearn, LLC
1'8501 Pine Boulevard, Suite 357
Pembroke Pines, FL 33029
The Contract is changed as follows:
The original(Contract Sum) (Guaranteed Maximum Price) .--.......----............ $ 188,80731
Net change by previously authorized Change Orders............... ....... ..... ........ ....... $ 23,165.27
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was ....... $ 211,972.98
The(Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order..—,.....--- $ 0.00'
The new(Contract Sum) (Guaranteed Maximum Price)including this Change Order is $ 211,972.98
The Contract Time will be (ingrggsed (decreased) (unchanged) by................. ....... 145 Days
The date of Substantial Completion as of the date of this Change Order is.... 03/01/2024
Detailed description,of change order and justification:
This chan-ge order is a no-cost time extension of 145 days. The contractor had a delay in securing the
manufacturer warranf on the new roof. The prior substantial completion date was 10/8/2023.
Change order is 0.0%of oL6Linal contract i2fice.
Not valid until signed by Owner, Engineer if applicablell,and Contractor
ENGINEER NIA—not needed for time extension
Perez Engineering& Development, Inc. Date
CONTRACTOR:
Dan Enterprises Team, LLC Date
DIRECTOR PROJECT MANAGEMENT.'. 03/14/24
Gary Vkk, Interim Director Date
Digitally signed by Kevin G.Wilson,
P.E.
COUNTY/ASSISTANT ADMINISTRATOR: Date 2024.03.15 09 45 54-04'00'
Kevin Wilson Date
915
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: No cost time extension due to delays in securing manufacturer warranty.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ❑ No
If no, explanation of why: Engineer approval not needed for time extension.
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
916
Dan Enterprises Team LLC
March Ist 2024
Monroe County
2955 Overseas Hwy Marathon, FL 33050
Att. Mr. Derrick Lazzara �T .....................
Ref: Request an extension of time
We hereby submit this request of extension of time to our contract for Marathon Professional'Center Building Roof
Replacement from Wovernbef 8"' 2023 to March Est 2024 in connection:with the need for a warranty inspection..
The project was completed on time and we requested for the warranty from mainufa:cturer.
Please contact me if you have additional questions.Thank you for working with us on this.
Best Regards,
Heidi Perez
917
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
FL Keys Marathon Airport Non-Aeronautical Use Building (EOC) CHANGE ORDER NO: 039
INITIATION DATE: 02/28/2024
CONTRACT DATE: 11/03/2021
TO CONTRACTOR:
Ajax Building Company, LLC
109 Commerce Boulevard
Oldsmar, FL 34677
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)..................................... $31,856,275.00
Net change by previously authorized Change Orders................................................... ($5,227,317.13)
The (Contract Suml(Guaranteed Maximum Price) prior to this Change order was....... $26,628,957.87
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order................... $4,370.81
The new (Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $26,633,328.68
The Contract Time will be (increased) (decreased) (unchanged) by........................... 0 days
The date of Substantial Completion as of the date of this Change Order is ................. 04/02/2024
Detailed description of change order and justification:
Reconcile the$4,370.81 unused balance of Owner Direct Purchase (ODP) B-PO-1122-00002638 with
City Electric Supply.
The net change is a credit to the GMP of$4,370.81.
Change order is .0014% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
Approved by Mickey Pruitt
ARCHITECT: 1 02/28/2024 3:16:13 PM
Architects Design Group, Inc. Date
Approved by�44
uarles
CONTRACTOR: 02/28/202M
Ajax Building Company, LLC Date
APPROVED
DEPARTMENT DIRECTOR: By Cary Vick at 3:20 pm,Feb28 2024
.........................................................................::.::.......................................::::................................::
Date
Cary Vick, Acting Project Management Director
Digitally signed by Kevin
Wilson
COUNTY/ASSISTANT ADMINISTRATOR: Kevin Wilson Date:2024.03.0416:21:53
-0e'00' Date
Kevin Wilson, Acting County Administrator
918
CHANGE ORDER LEDGER �qa"
FL Keys Marathon Airport Non-Aeronautical Use Building (E0Q
,l �E
--.
2/28/2024
I� mICII 0 il C I Illiip i�B- E
C lip
01 CDP#01 L&W Supply CDP Framing and Drywall 0 ( 308, 9,7 )
02 CDP#02 Seaman Corporation CDP Membrane Roofing 0 ( 386,66"),0!))
03 CDP#03 Seaman Corporation CDP Temporary Roofing 0 ($38 811 00)
ODP#04 DH Pace Company, CDP Doors, Frames,
04 Inc Hardware 0 ($ 93,!)88 00)
CDP#05 Polymershapes
Holding, Inc. dba Insulgard
05 Security Products CDP Strorefronts 0 ($!)'ply 787 00)
CDP#06 Commercial Air
06 Management, Inc. CDP HVAC Equipment 0 ($8! 420,00)
07 CDP#07 Trane U.S. Inc. CDP HVAC Equipment 0 'pEmm E'dw l"0)
08 CDP#08 Tex-Cote LLC CDP Paint 0 ($3!),7 p 7,00)
09 CDP#09 White Cap, LP CDP Rebar 0 ( 368 3 p 38)
10 CDP#10 City Electric Supply CDP Electrical 0 ($73,466,0 )
11 CDP#11 Electrical Supplies, CDP Gear Package 0 ($44 1.„620,00)
CDP#12 Monroe Concrete
12 Products CDP Concrete 0 ($!)02,068 l"0)
13 CDP#13 Barnes Alarm CDP Alarm Equipment 0 ( 4,1,11 7A )
CDP#14 Stewart& Stevenson
14 LLC CDP Generators I 0 ($699,!) 7 l"0)
Add back the cost of freight
CDP#05 and #08 Freight Cost inadvertently included in
15 Correction CDP request 0 $30,935.00
CDP#15 Bonded Lightning
16 Protection Systems, Inc. CDP Electrical 0 ($2l,897 10)
17 CDP#16 Ferguson CDP Storm Piping 0 ( p p4,!) 4 p )
18 CDP#17 Technical Sales CDP Lift Station 0 ($ 0 70,00)
CDP#18 Concrete Products of
19 the Palm Beaches CDP Storm Structures 0 ($ 9,03:p.,00)
CANCELLED CDP#19 -Sesco Lighting CDP Lighting $0.00
CDP #20 - Foundation
20 Building Materials CDP ACT Grid &Tile 0 ($ Il ,96! 9 )
919
CHANGE ORDER LEDGER �qa"
r
--.
ODP Cable, Connectors,
21 ODP#21 AVI Hardware, etc. 0 ( 29:1.„7 7,A )
22 ODP#22 Rexel ODP Lighting 0 ($3 p.„000,00)
23 ODP#23 TK Elevator ODP Elevator Components 0 ( A 03,9 i3,00)
24 ODP#24 Patterson Pope ODP Lockers and Shelving 0 ($ 2,878 ") )
25 ODP#25 Rexel ODP Cable Connectors 0 ( !) i") p 0)
26 ODP#26 Stephens Pipe ODP Fencing ($4 0 p")439)
ODP#12 Monroe Concrete Increased current PO by
27 Products $190,600.00 0 ($p.9 0,600,00)
28 ODP#23 TK Elevator Cancel ODP and PO 0 $103,943.00
29 ODP#05 Insulgard Cancel ODP and PO 0 $263,302.33
Additional cost spent on
ODP#8 Texcote over the PO
30 ODP #08 Tex-Cote value 0 ($J ") i p A3)
Additional quote for
material over the original
31 ODP#01 L&W ODP#1 L&W PO value 0 ($98 00 80)
Correction to OCO 29
32 ODP#5 Insulgard reconciliation value 0 ( 7,9 3"),00)
Reconcile B-PO-1122-
33 ODP#3 Seaman Corp 00002659 Seaman Corp 0 $259.99
Reconcile B-PO-1122-
34 ODP#36 Commercial Air 00002659 Seaman Corp 0 $8,465.00
Reconcile and Close B-PO-B-
ODP 12 & 27 Monroe PO-1122-00002731 Monroe
35 Concrete Concrete 0 ($4.26
36 N/A Time extension 60 $0.00
Reconcile and Close B-PO-
37 ODP Package#1 - L&W Supply 1122-00002656 L&W Supply 0 $444.89
Reconcile and Close B-PO-
38 ODP Package#9 -Whitecap 1122-00002664 Whitecap 0 $70,285.50
Reconcile and Close B-PO-
39 ODP Package#10 -CES 1122-00002638 0 $4,370.81
920
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
FL Keys Marathon Airport Non-Aeronautical Use Building (EOC) CHANGE ORDER NO: 040
INITIATION DATE: 02/28/2024
CONTRACT DATE: 11/03/2021
TO CONTRACTOR:
Ajax Building Company, LLC
109 Commerce Boulevard
Oldsmar, FL 34677
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)..................................... $31,856,275.00
Net change by previously authorized Change Orders................................................... ($5,222,946.32)
The (Contract Suml(Guaranteed Maximum Price) prior to this Change order was....... $26,633,328.68
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order................... $375.00
The new (Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $26,633,703.68
The Contract Time will be (increased) (decreased) (unchanged) by........................... 0 days
The date of Substantial Completion as of the date of this Change Order is ................. 04/02/2024
Detailed description of change order and justification:
Reconcile the$375.00 unused balance of Owner Direct Purchase (ODP) B-PO-0123-00000270 with
Concrete products of Palm Beaches.
Change order is .0012% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
Approved by Mickey Pruitt
ARCHITECT: 02/28/2024 3:19:27 PM
Architects Design Grou Inc. Date
Approved by Marshall Quarles
CONTRACTOR: 02 26 2o2a 3 3r 33._PM............
Ajax Building Company, LLC Date
DEPARTMENT DIRECTOR: A#-ki'R? yEi
................................................................................................................................... Date
Cary Vick, Acting Project Management Director
Digitally signed by Kevin
COUNTY/ASSISTANT ADMINISTRATOR: Kevin WIISOII Wilson
Data:2ma n3 na
16:23:14-0500 Date
Kevin Wilson, Acting County Administrator
921
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
FL Keys Marathon Airport Non-Aeronautical Use Building (EOC) CHANGE ORDER NO: 041
INITIATION DATE: 02/28/2024
CONTRACT DATE: 11/03/2021
TO CONTRACTOR:
Ajax Building Company, LLC
109 Commerce Boulevard
Oldsmar, FL 34677
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)..................................... $31,856,275.00
Net change by previously authorized Change Orders................................................... ($5,222,571.32)
The (Contract Suml(Guaranteed Maximum Price) prior to this Change order was....... $26,633,703.68
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order................... $342.89
The new (Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $26,634,046.57
The Contract Time will be (increased) (decreased) (unchanged) by........................... 0 days
The date of Substantial Completion as of the date of this Change Order is ................. 04/02/2024
Detailed description of change order and justification:
Reconcile the$342.89 unused balance of Owner Direct Purchase (ODP) B-PO-0423-00001037 with
Stephens Pipe & Steel, LLC.
Change order is .0011% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
Approved by Mickey Pruitt
ARCHITECT: 02/28/2024 4:00:00 PM
Architects Design Group, Inc. Date
.. a
CONTRACTOR: rp;.r2lv P
Ajax Building Company, LLC Date
APPROVED
DEPARTMENT DIRECTOR: �Ely C..ag Vick at412pm,Feb 28,202d
Date
Cary Vick, Acting Project Management Director
Digitally signed by Kevin
COUNTY/ASSISTANT ADMINISTRATOR: KeVln Wilson Wilson
"44244
16:24:02-05'00' Date
Kevin Wilson, Acting County Administrator
922
CHANGE ORDER LEDGER �qa"
,l �E
FL Keys Marathon Airport Non-Aeronautical Use Building (E0Q
--.
2/28/2024
II RgppNlll'u yh ul �WI'�ilikld,
I1Y Ili
60 Days $5,222,2" ..
01 CDP#01 L&W Supply CDP Framing and Drywall 0 ( 308,749,r )
02 CDP#02 Seaman CDP Membrane Roofing 0 ( 386,66"),0!))
Corporation
03 CDP#03 Seaman CDP Temporary Roofing 0 ($38 811 00)
Corporation
04 ODP#04 DH Pace Company, CDP Doors, Frames, 0 ($ 93,!)88 00)
Inc Hardware
05 CDP#05 Polymershapes CDP Strorefronts 0 ($!)'l0,787,00)
Holding, Inc. dba Insulgard
Security Products
06 CDP#06 Commercial Air CDP HVAC Equipment 0 ($8! 420,00)
Management, Inc.
07 CDP#07 Trane U.S. Inc. CDP HVAC Equipment 0 ($'m E+an 00)
08 CDP#08 Tex-Cote LLC CDP Paint 0 ( !),74 7,00)
09 CDP#09 White Cap, LP CDP Rebar 0 ( 368 3e'I 38)
10 CDP#10 City Electric Supply CDP Electrical 0 ($73„4 66,0 )
11 CDP#11 Electrical Supplies, CDP Gear Package 0 ($4,1 1.„620,00)
12 CDP#12 Monroe Concrete CDP Concrete 0 ($!)0 2 068 00)
Products
13 CDP#13 Barnes Alarm CDP Alarm Equipment 0 ( "4,J J 7A )
14 CDP#14 Stewart& CDP Generators 0 ($699 !)3 7,00)
Stevenson LLC
15 CDP#05 and#08 Freight Add back the cost of freight 0 $30,935.00
Cost Correction inadvertently included in CDP
request
16 CDP#15 Bonded Lightning CDP Electrical 0 ($2 0,89 7,J0)
Protection Systems, Inc.
17 CDP#16 Ferguson CDP Storm Piping 0 ( A A°i ") 4,A
18 CDP#17 Technical Sales CDP Lift Station 0 ($3,3 ''0,00)
19 CDP#18 Concrete Products CDP Storm Structures 0 ($ 9,03.p...,00)
of the Palm Beaches
CANCELLED CDP#19 -Sesco Lighting CDP Lighting $0.00
923
CHANGE ORDER LEDGER �qa"
r
--.
20 ODP #20 - Foundation ODP ACT Grid &Tile 0 ($86,96" 9 )
Building Materials
21 ODP#21 AVI ODP Cable, Connectors, 0 ( 9 A 7!)7,A )
Hardware, etc.
22 ODP#22 Rexel ODP Lighting 0 ($30 p.„000,00)
23 ODP#23 TK Elevator ODP Elevator Components 0 ( A 0 ,94 3,00)
24 ODP#24 Patterson Pope ODP Lockers and Shelving 0 ($6 2,878 ") )
25 ODP#25 Rexel ODP Cable Connectors 0 ( 2" 4!)9 A 0)
26 ODP#26 Stephens Pipe ODP Fencing ( 0 p"` i 9)
27 ODP#12 Monroe Concrete Increased current PO by 0 ($p. 0,600,00)
Products $190,600.00
28 ODP#23 TK Elevator Cancel ODP and PO 0 $103,943.00
29 ODP#05 Insulgard Cancel ODP and PO 0 $263,302.33
30 ODP #08 Tex-Cote Additional cost spent on ODP 0 ($ A !)4 AA3)
#8 Texcote over the PO value
31 ODP#01 L&W Additional quote for material 0 ($98 00 80)
over the original CDP#1 L&W
PO value
32 ODP#5 Insulgard Correction to OCO 29 0 ( 27,93") 00)
reconciliation value
33 ODP#3 Seaman Corp Reconcile B-PO-1122- 0 $259.99
00002659 Seaman Corp
34 ODP#36 Commercial Air Reconcile B-PO-1122- 0 $8,465.00
00002659 Seaman Corp
35 ODP 12 & 27 Monroe Reconcile and Close B-PO-B- 0 ($4.4. 15J)
Concrete PO-1122-00002731 Monroe
Concrete
36 N/A Time extension 60 $0.00
37 ODP Package#1 - L&W Reconcile and Close B-PO- 0 $444.89
Supply 1122-00002656 L&W Supply
38 ODP Package#9 -Whitecap Reconcile and Close B-PO- 0 $70,285.50
1122-00002664 Whitecap
39 ODP Package#10 -CES Reconcile and Close B-PO- 0 $4,370.81
1122-00002638
40 ODP Package#19 -Concrete Reconcile and Close B-PO- 0 $375.00
Products of the Palm Beaches 0123-00000270
41 ODP Package#26 -Stephens Reconcile and Close B-PO- 0 $342.89
Pipe 0423-00001037
924
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
FL Keys Marathon Airport Non-Aeronautical Use Building (EOC) CHANGE ORDER NO: 042
INITIATION DATE: 02/28/2024
CONTRACT DATE: 11/03/2021
TO CONTRACTOR:
Ajax Building Company, LLC
109 Commerce Boulevard
Oldsmar, FL 34677
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)..................................... $31,856,275.00
Net change by previously authorized Change Orders................................................... ($5,222,228.43)
The (Contract Suml(Guaranteed Maximum Price) prior to this Change order was....... $26,634,046.57
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order................... $747.00
The new (Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $26,634,793.57
The Contract Time will be (increased) (decreased) (unchanged) by........................... 0 days
The date of Substantial Completion as of the date of this Change Order is ................. 04/02/2024
Detailed description of change order and justification:
Reconcile the$747.00 unused balance of Owner Direct Purchase (ODP) B-PO-0323-00000587 with
Rexel.
Change order is .0023% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
Approved by Mickey Pruitt
ARCHITECT: 02/29/2024 7:22:18 AM
Architects Des i n Group. Inc. Date
Ap"proveei by Marshall U'kuarles
CONTRACTOR: 02/28/2024 4 01 33 PM
Ajax Building Company, LLC Date
DEPARTMENT DIRECTOR: BY C yry B mh at 6,20—Feb 24 2�`��................................................................................................................................
Date
Cary Vick, Acting Project Management Director
Digitally signed by Kevin
COUNTY/ASSISTANT ADMINISTRATOR: Kevin Wilsonn �.
1624:36-05'00' Date
Kevin Wilson, Acting County Administrator
925
CHANGE ORDER LEDGER �qa"
,l �E
FL Keys Marathon Airport Non-Aeronautical Use Building (E0Q
--.
2/28/2024
II RgppNlll'u yh ul �WI'�ilikld,
I1Y Ili
60 Days $5,221.,,4.81.. 3)
01 CDP#01 L&W Supply CDP Framing and Drywall 0 ( 308,749,r )
02 CDP#02 Seaman CDP Membrane Roofing 0 ( 386,66"),0!))
Corporation
03 CDP#03 Seaman CDP Temporary Roofing 0 ($38 811 00)
Corporation
04 ODP#04 DH Pace Company, CDP Doors, Frames, 0 ($ 93,!)88 00)
Inc Hardware
05 CDP#05 Polymershapes CDP Strorefronts 0 ($!)'l0,787,00)
Holding, Inc. dba Insulgard
Security Products
06 CDP#06 Commercial Air CDP HVAC Equipment 0 ($8! 420,00)
Management, Inc.
07 CDP#07 Trane U.S. Inc. CDP HVAC Equipment 0 ($'m E+an 00)
08 CDP#08 Tex-Cote LLC CDP Paint 0 ( !),74 7,00)
09 CDP#09 White Cap, LP CDP Rebar 0 ( 368 3e'I 38)
10 CDP#10 City Electric Supply CDP Electrical 0 ($73„4 66,0 )
11 CDP#11 Electrical Supplies, CDP Gear Package 0 ($4,1 1.„620,00)
12 CDP#12 Monroe Concrete CDP Concrete 0 ($!)0 2 068 00)
Products
13 CDP#13 Barnes Alarm CDP Alarm Equipment 0 ( "4,J J 7A )
14 CDP#14 Stewart& CDP Generators 0 ($699 !)3 7,00)
Stevenson LLC
15 CDP#05 and#08 Freight Add back the cost of freight 0 $30,935.00
Cost Correction inadvertently included in CDP
request
16 CDP#15 Bonded Lightning CDP Electrical 0 ($2 0,89 7,J0)
Protection Systems, Inc.
17 CDP#16 Ferguson CDP Storm Piping 0 ( A A°i ") 4,A
18 CDP#17 Technical Sales CDP Lift Station 0 ($3,3 ''0,00)
19 CDP#18 Concrete Products CDP Storm Structures 0 ($ 9,03.p...,00)
of the Palm Beaches
CANCELLED CDP#19 -Sesco Lighting CDP Lighting $0.00
926
CHANGE ORDER LEDGER �qa"
r
--.
20 ODP #20 - Foundation ODP ACT Grid &Tile 0 ($86,96" 9 )
Building Materials
21 ODP#21 AVI ODP Cable, Connectors, 0 ( 9 A 7!)7,A )
Hardware, etc.
22 ODP#22 Rexel ODP Lighting 0 ($30 p.„000,00)
23 ODP#23 TK Elevator ODP Elevator Components 0 ( A 0 ,94 3,00)
24 ODP#24 Patterson Pope ODP Lockers and Shelving 0 ($6 2,878 ") )
25 ODP#25 Rexel ODP Cable Connectors 0 ( 2" 4!)9 A 0)
26 ODP#26 Stephens Pipe ODP Fencing ( 0 p"` i 9)
27 ODP#12 Monroe Concrete Increased current PO by 0 ($p. 0,600,00)
Products $190,600.00
28 ODP#23 TK Elevator Cancel ODP and PO 0 $103,943.00
29 ODP#05 Insulgard Cancel ODP and PO 0 $263,302.33
30 ODP #08 Tex-Cote Additional cost spent on ODP 0 ($ A !)4 AA3)
#8 Texcote over the PO value
31 ODP#01 L&W Additional quote for material 0 ($98 00 80)
over the original CDP#1 L&W
PO value
32 ODP#5 Insulgard Correction to OCO 29 0 ( 27,93") 00)
reconciliation value
33 ODP#3 Seaman Corp Reconcile B-PO-1122- 0 $259.99
00002659 Seaman Corp
34 ODP#36 Commercial Air Reconcile B-PO-1122- 0 $8,465.00
00002659 Seaman Corp
35 ODP 12 & 27 Monroe Reconcile and Close B-PO-B- 0 ($4.4. 15J)
Concrete PO-1122-00002731 Monroe
Concrete
36 N/A Time extension 60 $0.00
37 ODP Package#1 - L&W Reconcile and Close B-PO- 0 $444.89
Supply 1122-00002656 L&W Supply
38 ODP Package#9 -Whitecap Reconcile and Close B-PO- 0 $70,285.50
1122-00002664 Whitecap
39 ODP Package#10 -CES Reconcile and Close B-PO- 0 $4,370.81
1122-00002638
40 ODP Package#19 -Concrete Reconcile and Close B-PO- 0 $375.00
Products of the Palm Beaches 0123-00000270
41 ODP Package#26 -Stephens Reconcile and Close B-PO- 0 $342.89
Pipe 0423-00001037
ODP#22 Rexel Reconcile and Close B-PO-
42 0323-00000587 0 $747.00
927
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
FL Keys Marathon Airport Non-Aeronautical Use Building (EOC) CHANGE ORDER NO: 043
INITIATION DATE: 02/28/2024
CONTRACT DATE: 11/03/2021
TO CONTRACTOR:
Ajax Building Company, LLC
109 Commerce Boulevard
Oldsmar, FL 34677
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)..................................... $31,856,275.00
Net change by previously authorized Change Orders................................................... ($5,221,481.43)
The (Contract Suml(Guaranteed Maximum Price) prior to this Change order was....... $26,634,793.57
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order................... $16,639.47
The new (Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $26,651,433.04
The Contract Time will be (increased) (decreased) (unchanged) by........................... 0 days
The date of Substantial Completion as of the date of this Change Order is ................. 04/02/2024
Detailed description of change order and justification:
Reconcile the$16,639.47 unused balance of Owner Direct Purchase (ODP) B-PO-0723-00001655 with
AVI-SPL International.
Change order is .0522% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
Approved by Mickey Pruitt
ARCHITECT: 02/29/2024 7:29:14 AM
Architects Design Group, Inc. Date
[fOr2/]28,202.
d by Marshall Quarles
CONTRACTOR: 06 Ply
Ajax Building Company, LLC Date
imwoPJib
DEPARTMENT DIRECTOR: ByCary Vick at823 am,Feb 29„2Q2t
Date
Cary Vick, Acting Project Management Director
Digitally signed by Kevin
Wilson
COUNTY/ASSISTANT ADMINISTRATOR: Kevin Wilson at._.: 02.04
�ate:.�f�
16:25:09-05'00' Date
Kevin Wilson, Acting County Administrator
928
CHANGE ORDER LEDGER �qa"
,l �E
FL Keys Marathon Airport Non-Aeronautical Use Building (E0Q
--.
2/28/2024
II RgppNlll'u yh ul �WI'�ilikld,
I1Y Ili
60 Days $5,20 .,8 '1_9(i
01 CDP#01 L&W Supply CDP Framing and Drywall 0 ( 308,749,r )
02 CDP#02 Seaman CDP Membrane Roofing 0 ( 386,66"),0!))
Corporation
03 CDP#03 Seaman CDP Temporary Roofing 0 ($38 811 00)
Corporation
04 ODP#04 DH Pace Company, CDP Doors, Frames, 0 ($ 93,!)88 00)
Inc Hardware
05 CDP#05 Polymershapes CDP Strorefronts 0 ($!)'l0,787,00)
Holding, Inc. dba Insulgard
Security Products
06 CDP#06 Commercial Air CDP HVAC Equipment 0 ($8! 4 20.00)
Management, Inc.
07 CDP#07 Trane U.S. Inc. CDP HVAC Equipment 0 ($'m E+an 00)
08 CDP#08 Tex-Cote LLC CDP Paint 0 ( !),74 7,00)
09 CDP#09 White Cap, LP CDP Rebar 0 ( 368 3e'I 38)
10 CDP#10 City Electric Supply CDP Electrical 0 ($73„4 66,0 )
11 CDP#11 Electrical Supplies, CDP Gear Package 0 ($4,1 1.„620,00)
12 CDP#12 Monroe Concrete CDP Concrete 0 ($!)0 2 068 00)
Products
13 CDP#13 Barnes Alarm CDP Alarm Equipment 0 ( "4,J J 7A )
14 CDP#14 Stewart& CDP Generators 0 ($699 !)3 7,00)
Stevenson LLC
15 CDP#05 and#08 Freight Add back the cost of freight 0 $30,935.00
Cost Correction inadvertently included in CDP
request
16 CDP#15 Bonded Lightning CDP Electrical 0 ($2 0,89 7,J0)
Protection Systems, Inc.
17 CDP#16 Ferguson CDP Storm Piping 0 ( A A°i ") 4,A
18 CDP#17 Technical Sales CDP Lift Station 0 ($3,3 ''0,00)
19 CDP#18 Concrete Products CDP Storm Structures 0 ($ 9,03.p....00)
of the Palm Beaches
CANCELLED CDP#19 -Sesco Lighting CDP Lighting $0.00
929
CHANGE ORDER LEDGER �qa"
r
--.
20 ODP #20 - Foundation ODP ACT Grid &Tile 0 ($86,96" 9 )
Building Materials
21 ODP#21 AVI ODP Cable, Connectors, 0 ( 9 A 7!)7,A )
Hardware, etc.
22 ODP#22 Rexel ODP Lighting 0 ($30 p.„000,00)
23 ODP#23 TK Elevator ODP Elevator Components 0 ( A 0 ,94 3,00)
24 ODP#24 Patterson Pope ODP Lockers and Shelving 0 ($6 2,878 ") )
25 ODP#25 Rexel ODP Cable Connectors 0 ( 2" 4!)9 A 0)
26 ODP#26 Stephens Pipe ODP Fencing ( 0 p"` i 9)
27 ODP#12 Monroe Concrete Increased current PO by 0 ($p. 0,600,00)
Products $190,600.00
28 ODP#23 TK Elevator Cancel ODP and PO 0 $103,943.00
29 ODP#05 Insulgard Cancel ODP and PO 0 $263,302.33
30 ODP #08 Tex-Cote Additional cost spent on ODP 0 ($ A !)4 AA3)
#8 Texcote over the PO value
31 ODP#01 L&W Additional quote for material 0 ($98 00 80)
over the original CDP#1 L&W
PO value
32 ODP#5 Insulgard Correction to OCO 29 0 ( 27,93") 00)
reconciliation value
33 ODP#3 Seaman Corp Reconcile B-PO-1122- 0 $259.99
00002659 Seaman Corp
34 ODP#36 Commercial Air Reconcile B-PO-1122- 0 $8,465.00
00002659 Seaman Corp
35 ODP 12 & 27 Monroe Reconcile and Close B-PO-B- 0 ($4.4. 15J)
Concrete PO-1122-00002731 Monroe
Concrete
36 N/A Time extension 60 $0.00
37 ODP Package#1 - L&W Reconcile and Close B-PO- 0 $444.89
Supply 1122-00002656 L&W Supply
38 ODP Package#9 -Whitecap Reconcile and Close B-PO- 0 $70,285.50
1122-00002664 Whitecap
39 ODP Package#10 -CES Reconcile and Close B-PO- 0 $4,370.81
1122-00002638
40 ODP Package#19 -Concrete Reconcile and Close B-PO- 0 $375.00
Products of the Palm Beaches 0123-00000270
41 ODP Package#26 -Stephens Reconcile and Close B-PO- 0 $342.89
Pipe 0423-00001037
42 ODP#22 Rexel Reconcile and Close B-PO- 0 $747.00
0323-00000587
930
CHANGE ORDER LEDGER �qa"
r
--.
43 ODP#21 AVI Reconcile and Close B-PO- $16,639.47
0323-00000587
931
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
FL Keys Marathon Airport Non-Aeronautical Use Building (EOC) CHANGE ORDER NO: 044
INITIATION DATE: 02/28/2024
CONTRACT DATE: 11/03/2021
TO CONTRACTOR:
Ajax Building Company, LLC
109 Commerce Boulevard
Oldsmar, FL 34677
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)..................................... $31,856,275.00
Net change by previously authorized Change Orders................................................... ($5,204,841.96)
The (Contract Suml(Guaranteed Maximum Price) prior to this Change order was....... $26,651,433.04
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order................... $18,412.25
The new (Contract Sum)(Guaranteed Maximum Price) including this Change Order is. $26,669,845.29
The Contract Time will be (increased) (decreased) (unchanged) by........................... 0 days
The date of Substantial Completion as of the date of this Change Order is ................. 04/02/2024
Detailed description of change order and justification:
Reconcile the$18,412.25 unused balance of Owner Direct Purchase (ODP) B-PO-0223-00000292 with
Ferguson.
Change order is .0578% of original contract price.
Not valid until signed by Owner,Architect(if applicable), and Contractor
Approved by Mickey Pruitt
ARCHITECT: 1 02/29/2024 7:34:04 AM
Architects Design Group, Inc. Date
C Approved by Marshall UWarles
CONTRACTOR: I 02/28/2024423 34PM
Ajax Building Company, LLC Date
DEPARTMENT DIRECTOR: APPROVED
�By Cara Ifick at&2'5 any,Fehr 2.9,.26�:�& Date
Cary Vick, Acting Project Management Director
Digitally signed by Kevin
COUNTY/ASSISTANT ADMINISTRATOR: Kevin WIISOII Wilson
ate:2024.03.04
16:25:39-05'00' Date
Kevin Wilson, Acting County Administrator
932
CHANGE ORDER LEDGER �qa"
,l �E
FL Keys Marathon Airport Non-Aeronautical Use Building (E0Q
--.
2/28/2024
II RgppNlll'u yh ul �WI'�ilikld,
I1Y Ili
60 Days " ,:or"�,,�18��6,..29. .1.)
01 CDP#01 L&W Supply CDP Framing and Drywall 0 ( 308,749,r )
02 CDP#02 Seaman CDP Membrane Roofing 0 ( 386,66"),0!))
Corporation
03 CDP#03 Seaman CDP Temporary Roofing 0 ($38 811 00)
Corporation
04 ODP#04 DH Pace Company, CDP Doors, Frames, 0 ($ 93,!)88 00)
Inc Hardware
05 CDP#05 Polymershapes CDP Strorefronts 0 ($!)'l0,787,00)
Holding, Inc. dba Insulgard
Security Products
06 CDP#06 Commercial Air CDP HVAC Equipment 0 ($8! 420,00)
Management, Inc.
07 CDP#07 Trane U.S. Inc. CDP HVAC Equipment 0 ($'m E+an 00)
08 CDP#08 Tex-Cote LLC CDP Paint 0 ( !),74 7,00)
09 CDP#09 White Cap, LP CDP Rebar 0 ( 368 3e'I 38)
10 CDP#10 City Electric Supply CDP Electrical 0 ($73„4 66,0 )
11 CDP#11 Electrical Supplies, CDP Gear Package 0 ($4,1 1.„620,00)
12 CDP#12 Monroe Concrete CDP Concrete 0 ($!)0 2 068 00)
Products
13 CDP#13 Barnes Alarm CDP Alarm Equipment 0 ( "4,J J 7A )
14 CDP#14 Stewart& CDP Generators 0 ($699 !)3 7,00)
Stevenson LLC
15 CDP#05 and#08 Freight Add back the cost of freight 0 $30,935.00
Cost Correction inadvertently included in CDP
request
16 CDP#15 Bonded Lightning CDP Electrical 0 ($2 0,89 7,J0)
Protection Systems, Inc.
17 CDP#16 Ferguson CDP Storm Piping 0 ( A A°i ") 4,A
18 CDP#17 Technical Sales CDP Lift Station 0 ($3,3 ''0,00)
19 CDP#18 Concrete Products CDP Storm Structures 0 ($ 9,03.p...,00)
of the Palm Beaches
CANCELLED CDP#19 -Sesco Lighting CDP Lighting $0.00
933
CHANGE ORDER LEDGER �qa"
r
--.
20 ODP #20 - Foundation ODP ACT Grid &Tile 0 ($86,96" 9 )
Building Materials
21 ODP#21 AVI ODP Cable, Connectors, 0 ( 9 A 7!)7,A )
Hardware, etc.
22 ODP#22 Rexel ODP Lighting 0 ($30 p.„000,00)
23 ODP#23 TK Elevator ODP Elevator Components 0 ( A 0 ,94 3,00)
24 ODP#24 Patterson Pope ODP Lockers and Shelving 0 ($6 2,878 ") )
25 ODP#25 Rexel ODP Cable Connectors 0 ( 2" 4!)9 A 0)
26 ODP#26 Stephens Pipe ODP Fencing ( 0 p"` i 9)
27 ODP#12 Monroe Concrete Increased current PO by 0 ($p. 0,600,00)
Products $190,600.00
28 ODP#23 TK Elevator Cancel ODP and PO 0 $103,943.00
29 ODP#05 Insulgard Cancel ODP and PO 0 $263,302.33
30 ODP #08 Tex-Cote Additional cost spent on ODP 0 ($ A !)4 AA3)
#8 Texcote over the PO value
31 ODP#01 L&W Additional quote for material 0 ($98 00 80)
over the original CDP#1 L&W
PO value
32 ODP#5 Insulgard Correction to OCO 29 0 ( 27,93") 00)
reconciliation value
33 ODP#3 Seaman Corp Reconcile B-PO-1122- 0 $259.99
00002659 Seaman Corp
34 ODP#36 Commercial Air Reconcile B-PO-1122- 0 $8,465.00
00002659 Seaman Corp
35 ODP 12 & 27 Monroe Reconcile and Close B-PO-B- 0 ($4.4. 15J)
Concrete PO-1122-00002731 Monroe
Concrete
36 N/A Time extension 60 $0.00
37 ODP Package#1 - L&W Reconcile and Close B-PO- 0 $444.89
Supply 1122-00002656 L&W Supply
38 ODP Package#9 -Whitecap Reconcile and Close B-PO- 0 $70,285.50
1122-00002664 Whitecap
39 ODP Package#10 -CES Reconcile and Close B-PO- 0 $4,370.81
1122-00002638
40 ODP Package#19 -Concrete Reconcile and Close B-PO- 0 $375.00
Products of the Palm Beaches 0123-00000270
41 ODP Package#26 -Stephens Reconcile and Close B-PO- 0 $342.89
Pipe 0423-00001037
42 ODP#22 Rexel Reconcile and Close B-PO- 0 $747.00
0323-00000587
934
CHANGE ORDER LEDGER �qa"
r
--.
43 ODP#21 AVI Reconcile and Close B-PO- $16,639.47
0723-00001655
44 CDP#16 Ferguson Reconcile and Close B-PO- $18,412.25
0223-00000292
935