19th Change Order 04/05/2024 DocuSign Envelope ID:88808FD2-93D9-4897-87E6-D505DBDOBDBA M,CA INSM 8900.2 rage 3 MONROE COUNTY/DEPARTMENT OF AIRPORTS CONTRACT CHANGE ORDER PROTECT TITLE: KWIA Concourse A&Terminal Improvements CHANGE ORDER NO.: 019 INITIATION DATE: 2/15/2024 TO CONTRACTOR: NV2A/Gulf Keystar TV CONTRACT DATE: 8/17/2021 The Contract is changed as follows: The Original(Contract Sum)(Guaranteed Maxiurn Price.) $ Net change by previously authozied Change Order $ 8,859,16033 The(Contract Sum)(Guaranteed Mxlurn Price)prior to this Chage order was $ 1.10,320,931.33 The(Contract Surn'�(Guaranteed Mxjum price)will be(increased)by this Change,Order $ 1,512.50 The new{Contract Surn)(Guarantecd Wurn Price) Including this Change Order is $ 110,322,443.83 1 he Contract I irne will be QIncreaaedj by TED days __._ .._ The date of Substantial Completion as of the date of this Change Order is _��2016 . Detailed DescripUon of change order andjUStJflCati0M at specific locations in East and This Change Order of Unforeseen Duc ank Investigation includes exploration for underground utilities West Construction Phases for the KWIA project (20-2039-01) POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PC # Amount 'Total. 5 DO B� T 1,5�750 006 Unforeseen Ductbar�klnvestigatlan . ;= 1,512.5 This change order is M01%of the orig!nal contract price. Not valid until signed by Owner,Architect(if applicable),and Contractor 4/2/2024 I 13:06:23 PDT [1062EIE842XS V-- ARCHITECT: DATE: Dorasftoad by occusigned by: 4/2/2024 1 07:23:03 PDT CONTRACTORS: E7 Richard Strickland EXECUTIVE DIRECTOR OFAIRPORIS DATE: COIJNTY/DEPUTY ADM INIS FRATOR 04 "24 DATE NkOE COUNTY ATTonNEY( ArPI41070 Drs 0S s"6 �-E-',70 � C AS�SIS i UNTY ATTIORNEY Date----ALVjL- DocuSign Envelope ID:88808FD2-93D9-4897-87E6-D505DBDOBDBA NV' GULr gUILtuNG KEYST*R PCCO #019 Project:20-2039-01 -KWIA Concourse A and Terminal improvements NV2A/Gulf Keystar JV Program 9100 South Dadeland Blvd,Suite 600 3941 South Roosevelt Blvd. Miami,Florida 33156 Key West,Florida 33040 Phone:(786)233-5060 Prime Contract Change Order #019: FKE - Unforeseen Ductbank Investigation TO: Key West International Airport FROM: NV2A/Gulf Keystar JV 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600 Key West,Florida 33040 Miami, Florida 33156 DATE CREATED: 2/15/2024 CREATED BY: MarSOUr Sodagari(NV2A/Gulf Keystar JV) CONTRACT STATUS: Approved REVISION: 0 DESIGNATED REVIEWER: REVIEWED BY: : DUE DATE: REVIEW DATE: 02/1512024 INVOICED DATE: PAID DATE: SCHEDULE IMPACT: EXECUTED: No REVISED SUBSTANTIAL SIGNED CHANGE ORDER 02/14/2024 COMPLETION DATE: RECEIVED DATE: CONTRACT I FOR: 20-2039-01:Key West International Airport TOTAL AMOUNT, $1,512.50 Concourse A DESCRIPTION: FKE Unforeseen Ductbank Investigation This Change Order of Unforeseen Ductbank Investigation:rcludes exploration for underground utilities at specific locations in East and West Construction Phases for the KWIA project.(20-2039-01) All costs for services are included in this Change Order to perform the work as described in the attached documents. The as-builts for GPRS maps and certified payrolls are,attached, ATTACHMENTS: POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: Title Schedule Impact Amount $1,512,50 0 nforeseen Ductbank Investigation 0606 U6n $1,512.50 Total: $101,461,771,00 The original(Contract Sum) $8,859,160.33 Net change by previously authorized Change Orders $110,320,931.33 The contract sumprior to this Change Order was $1,512-50 The contract surn will be increased by this Change Order in the amount of $110,322,44183 The new contract sumincluding this Change Order will be The contract trne will riot be changed by this Change Order. DS os iDs L�Lk r Christopher Kopec(McFarland Johnson, Key West International Airport NV2A/Gulf Keystar JV Inc.) 9100 South Dadeland Blvd,Suite 600 49 Court Street,Suite.240 3491 South Roosevelt Boulevard Miami,Florida 33156 Binghamton,New York 13901 Key West,Florida 33040 D*auSigned by- -00cuftrwd by, Richard E Strickland E019D93827AF54a7— DATE SIGNATURE DATE SIGNATURE DATE SIGNATURE 4/2/2024 1 13:06:23 PDT 4/2/2024 1 07:23:03 PDT NV2A/Gulf Keystar JV Page 1 of 1 Printed On:2/15/2024 06:52 PM off TM KEYST PCO #006 NW AkGULF BUILDING R NV2A/Gulf Keystar JV Project:20-2039-01 -KWIA Concourse A and Terminal Improvements 9100 South Dadeland Blvd, Suite 600 Program Miami,Florida 33156 3941 South Roosevelt Blvd. Phone:(786)233-5060 Key West,Florida 33040 Prime Contract Potential Change Order #006: Unforeseen Ductbank Investigation TO: Key West International Airport FROM: NV2A/Gulf Keystar JV 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600 Key West, Florida 33040 Miami,Florida 33156 PCO NUMBER/REVISION: 006/1 CONTRACT: 20-2039-01-Key West International Airport Concourse A REQUEST RECEIVED FROM: CREATED BY: Mansour Sodagari(NV2AIGulf Keystar JV) STATUS: Pending-In Review CREATED DATE: 5/17/2023 REFERENCE: PRIME CONTRACT None CHANGE ORDER: FIELD CHANGE: No LOCATION: ACCOUNTING METHOD: Amount Based SCHEDULE IMPACT: PAID IN FULL: No EXECUTED: No SIGNED CHANGE ORDER RECEIVED DATE: TOTAL AMOUNT: $1,512.50 POTENTIAL CHANGE ORDER TITLE: Unforeseen Ductbank Investigation CHANGE REASON:Existing/Unforseen Condition POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows) FK lfrtlgt:g eerp,.Gu 4t��sn Inv,gst: This Change Order of Unforeseen Ductbank Investigation includes exploration for underground utilities at specific locations in East and West Construction Phases for the KWIA project.(20-20 g'-01) All costs for services are included in this Change Order to perform the work as described in the attached documents. The as-builts for GPRS maps and certified payrolls are attached. ATTACHMENTS: __. ...........-.,_ _--......_ # Budget Code Description Amount 1 26-.00.10.10.S Electrica1.Subcontractor Unforeseen Ductbank Investigation $1,375.00 2 99-99.99.66.0 Procore OH&ITP.Other 10/°mmw mITnWunn^^^ mm° Markup $137.50 ....... _....._. __ _ .... --- .._.� .. . . Grand Total: $1,512.50 Christopher Kopec, PE (McFarland Johnson,Inc.) Key West International Airport NV2A/Gulf Keystar JV 49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600 Binghamton,New York 13901 Key West,Florida 33040 Miami,Florida 33156 Kopec Date:2024.02.1408:51:37 Digitally signed b Christopher Christo her Ko ec p -05 00 „ d, 2.14.2024 SIGNATURE DATE SIGNATURE DATE SIG URE DATE NV2AIGulf Keystar JV Page 1 of 1 Printed On: 10/19/2023 03:35 PM Invoice FLORIDA HEYS r . IMEMER ELECTRICAL CONTRACTOR 905 Overseas Highway Ph (305) 296-4028 4/19/2023 11518 Key West, FL 33040 Fax (305)296-9283 W2A Group LLC Net 30 KWIA Concourse s I Early Works unforeseen ductbank investigation for ea st&west 1,375.00 1,375.00 construction zones.The existing ductbanks in question have been located and were abandoned.See accompanied gprs maps for documentation of findings. Thank you for your business.We appreciate , Payments/Credits: $100 you choosing Florida Keys Electric. If you ''�:� were satisfied with our work,please leave us a review on Google. Balance Due: $1,375.00 d tl n duc a:. v Intweo-ii d m's v nh unl id I e ( , - ,h n , rlre ,k s 1 F .wr i ru7 G impa� Y.I sis of r.dc I'a In I L ) L i F A.( tl I l Ji. .� 10 t �., dsh r not Lv i r xSa Y.6.r ixl co- N:� and 1,v n v axl C.Sts aio ell's p.oln air i. �hlcuals.u ,P;,, n �h, i,. f ➢ In t h ".,.I a:J ona I�us L.iAY a n .;r,l periianica nmic h>ui.: �ill nrn cercd SlU,�i iO � mlc�dcrc i;a :nl,�n pngr J I n,, w a,ir . d ,r e r. f�snrkmf ;ip www flkeyselectrlc com W J W j O O O In In Ln a m of in Ln C O X u Wo Y LD Z m O cu W N O 0 L V Z C U Z J O Q LLl N W d Q � H c w W z V1 O w O O Y > O O W O Ln Ln N CL r ei W o J Q ~ J u O m O H a m 5 O z .0 = u W N L w y N L H Y a+ Cid O W a 'o Ln 3 W LL � Y O W u O s U G J ' LL a z Q 0 Q zcc O w O a O U a ~ r r °a a cC GG J C G a W u W r 6 U1 Y W 1 W O Q o Q m x W m G a Q z +c Y U � G Z �me W J Y W '',1LylYyy�T�sb,, VI z W it Z G z s c z ,r, WW (7 w z J �atn W 41 LLI w O O O > O OC D z Z cr- cr- cc m o a U � J Z W Q W LL z O Lu LU N p '^ O a O Z z Z v+ z O O o o r r cis a z m z O x O ; 0 0 ? 411111 FLORIDA KEYS row ELECTRIC,INC. f*IfRV'rE11WER ELECTRICAL CONTRACTOR TIME&MATERIAL TICKET COR# UNFORSEEN DUCTBANK INVESTIGATION Work Date: 4/13/23-4/14/23 EXISTING DUCTBANK SHOWN ON GPRS REPORT THAT IS INTERFERING WITH PILE CAP Description: INSTALLATION. INVESTIGATED LOCATION,REMOVED CONCRETE,OPENED PIPE TO EXPOSE CONTENTS. IT WAS DETERMINED TO BE ABANDONDED AND OLD WIRE WAS REMOVED. Materials Cate Description Quantity NO MATERIALS REQUIRED,DEMO ONLY, Equipment Description Qty Rental Rate Rental Period Labor Name Classification Hours Straight OT MAIKEL ESCOBAR (4/14) ELECTRICIAN 2 FRANCISCO GOMEZ(4/13&4/14) ELECTRICIAN 4 DOUG HOLMES(4/13&4/14) DBW EXEMPT 4 Superintendent/Foreman Signature CM Signature for Time Verification Only Name: JORDAN COLLINS Name: Signature: Signature: Date: Date: :�EAEO E C TR I C,/N C. PREMIER ELECTRICAL CONTRACTOR LABOR RATE SCHEDULE FIDE Electrician - $125/hr Electrical Technician / Laborer - $100/hr H ech - Data/Comm & Fire Alarm Fire Alarm Technician - $125/hr Building Electronics Technician - $125/hr "Wage rates incorporate KWIA DBW specifications. "Electrical Technician / Laborer is listed as Pipe Layer/Pipe Fitter in DBW classifications. Jim o o N(n EC Q a w BLu oa € i $ �6 �. Y w � LL 3 Y , f u go 01, fffff r r r 5w„ •r / � 9 6 �r / r x i ED 0 �Pt"� 9 v M 1 w a tt1fi r 1 «W1N i �i7 n�w� ✓��' �, I IIA� 1 ' / r v rt a r ~N r � ' 2 �,'n , ■ 4J G 1 /l „ �� ;I ( �" 'U 9IIlll Jf� iD Pr/'/rl 'IU V..t.➢IU (.3� r 4; j ^.,..^— k) >�i /ail "d "°n A �AM I 1/ e ! / f � f Y it ► � �l r F � w r. �i ,�... " Aa �, r, w . b Z 2 0.. O O O o S 0 m JO d O O O C ui of Ln NO C u W Q N N N N eN-1 M 'G Of N Q ei m O rl ed' a-i rl rl 'i \ 0 ,', W_ C OW. VI',N N V! VF N N pj T L C V L V1 Q d V Z ruj W d a O W 7 ~ CQ cAIA W C "^ �^ Sd9 W o a H Ln Ln G N N V — W ~ Y OZS v Q p cn d _ W Y 10 0 W aLla ppryryyy 4Yd 4.::�, MNA Q "Ci re u W cc 0 w cc cr 44 C > Au O v� CD cu U) " 7LO CD � C z .... p p Z CD -a � LO W G > W Z N � W a s u� a , J t; o ra m Q 0 h LU W W C W J 0 s ° o z Z G W kn VI W K 0 0 O z 3 ° h ¢ Z 0 O WOZ da F- h W G O > W KWIA CONCOURSE A & LORIDA ME ELEC�" "I ,IIVC TERMINAL IMPROVEMENTS ORIGINAL SUBMISSION WAS DIRECTIVE: UNFO INCORRECT, SEE CORRECTED " WORKS LABOR DATE EMPLOYEE HOURS FLAT RATE 4/14/2023 DOUG HOLMES $ 4/14/2023NQQZA*:�" 4/14/2023 MAIKEL E�S�COB6AROriginal request had 250.00 d_ :, y-w d. 4/14/2023 JORDAN COLLINS this change? $250.00 taui.....SLJbii°nos 6ou: I 4 113/2 p wt irate its not �Z14-- WORK PERFORMED Early Works unforeseen ductb for east &west construction zones. The existing ductbanks in question have been locate doned. See accompanied gprs maps for documentation of findings. MATERIALS: QUANTITY: N/A I I i fill (9? ZLU W iEg W-" r' w Jill'g o 111.51.1 1111112 :fir � �{ �,.. .� � � ���IJ%o� �� r�� rl r�����jj// r .r a■ � � m /j / ¢uz �i M � „ g E IN/4 AP / p ~ ,,/ i ,qS�,u i � l xww«ww{ w., —mow um u�oiw�wr�wwwr w.; { Ny i P � w I � / r � " J r { m r CL co co / CJ zC.D �� �a fl� �Z Lu z w w Ui i Q - i � z c�i /y �n p o ' l fw a- K y z zi a Y I O 5 T U= u) W0WY W Z ZZ 4 r 10, /� 11 N N �, I Oil�r ai / ' 71 M S��FlFy O 0 o W� all s Iw wS w W IL z z co Z LL I 0 w 0 a w w o 2 U c �� W m 7LL K UQ 2 z 7 3 V f/J F IIY. Y m 3=f .-. W $LL Mcq rm. � C4 c N r �- prn N 8 E $E M. o "� c E 0Z. E V E E£ m m a E m m -nor =o Z � m w�-0« v'�,w� N m E Hd a° p n o' a LI m c a t Q E'o m � R ca N m_cm m m CL nLL o ° `o � @ _-5 any w Imo ° m C a LL U mm- � Em m Z p -L� c o ` ��0 m IS Z U �Q gg t�tgg z V 3r '.0 SEA 6 �m � m No 9 m �Q "° Y w s o �C OIL' m E N o w e 5 1 Ho m m1.2 w N m oav a Y nA T LU I 4 Z o TLE r �am�+mm 0a S to L� L O o0 GoLU Y `Q! N < CD C O0 3 a W SZ LLLL g 8 A �F o g 8 S Co G40 CD o o aME z QW T a m � gill .WS Iw^ C 4 Z r $ m s� UA Y c e ca v LL m �s0~ 1s e-j s � aLL GOco m L Zaom ads r m r5a o J a G n of v o °� Q v v A O r o 0 0 0 0 o 0 0 +� °�O1 g o 0 0 0 0 0 o c � $ LL1 8 $ � Q z z ry F- w0 aE U) 0 W W U O N v LL a N T (_n y �• N O NWO = g a s o2 (D _ =N= z c �,Z 'i 80'JD o m o 0 o 0 o m o... m 0... m O m D m m I- 0 � y W J V O V W $� e Y Z 2 Z _0 Z w -_ g W W W W W 1-5 IL B $ m B m 0LL " Y t O O O O a ° g .' m y � a o 2- � 5 Ai o p � � c oCP o V� G Q. e A N EV cc LL W� a g N to E_ �'= m= _ "Wd� c�� � � a� �� � � ism A S :z cmo� o 0 0ix 0 8 $ W p u a p-1 t9 W E 69 !9 fA 5 N 0cq 0 lh pLU ci ca 6s Cl) VIP cAi z a� 8 N �F4Ag p 63. t }0 LoS N $£ $ O co es O Y i T 02, to m° rL s m � o' e LD 11 Ol W J W i 6 O m <o 0 0 0 0 0 o p 9 e C o 0 0 0 0 0 0 0 o ui o 0 0 0 l c o Mr F. O O �3 H W m � (n Z U) � Q uw LLJ U o ; LL 7 Qcn � L � o NO2 W Z v N b �o LL �.9m g w J c 'la bo"10..... o m o......m o m o m o T C g � � or, Q Wce o Ell LLoS $ 3m a n ¢ m � a a w ' caKSxa waovmlw o 0 0 0 0 0 0 0 ° u. Ao'ON LL aS8 ° at J zo _ -9q $ r+ c 0 cLLCL Imo. r fl° Sg to LL NMIq Y O O o z ' C1q � TL O OQ WO O g 8 R C LL m o 9 � a 17 U 0 rn09, 00 5 s� C1 = Z V. ul (O 34$ p pp � C Z2 N R 9 8� Cui 0 0 0 0 0 0 0 0 0 0 0 o $ g o 0 0 0 0 0 $ o 0 0 0 0 o a cIn �$ .. Z A 8 w o m m � O O c COY Sr- .F. O aQ o Q << o LL c$ U) ' .1 No-1 F L C O O M O w w I O O J LL m Zw w �, _ � o o- p s € Y — &L a g n ' � � MHO Q � ga w a XwQJ � ZZ 8 H � Q t � Z w � Zpcnp eNalarex� Z J � Q U O C o cr 0o o � w � � w � Q s Qm0OwOQ G U Z U Z Z U) } E g �, w Jp — � QOO W < Z) m o o s $ Mri,l � wazzQQ W 0 '� zoc� o '�, mw — 02 ao CL m O rOn o ¢5 � Q - Iw—Lw � ww eggcU JJ z tl b0 cc V_ ..JI K C �, EV1 (n O Q 0