22nd Change Order 05/02/2024 DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
M.C.A.INSTR.8800.2
Enclosure(1)
3/28/2017
Page 3
MONROE COUNTY/DEPARTMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECTTITLE: KWIA Concourse A&Terminal Improvements CHANGE ORDER NO.: 022
INITIATION DATE: 1/26/2024
TO CONTRACTOR: NV2A/Gulf Keystar JV CONTRACT DATE: 8/17/2022
The Contract is changed as follows:
The Original(Contract Sum)(Guaranteed Maxium Price) $ 101,461,771.00
Net change by previously authozied Change Order $ 9,085,129.74
The(Contract Sum)(Guaranteed Mxium Price)prior to this Chage order was $ 110,546,900.74
The(Contract Sum)(Guaranteed Mxium Price)will be by this Change Order $ 115,918.00
The new(Contract Sum)(Guaranteed Mxium Price) including this Change Order is $ 110,662,818.74
The Contract Time will be(uni:haagad by 0 days
The date of Substantial Completion as of the date of this Change Order is 3/9/2026
Detailed Description of change order and justification:
This Change Order includes costs associated with steel material escalation for the KWIA project(20-2039-01).
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO p I Title Schedule Impact Amount
046 iSteel Fab-Material Escalation 0 $ 115,918.00
Total: $ 115,918.00
This change order is 0.11%of the original contract price.
DocuSigned by:
Not valid until signed by Owner,Architect(if applicable),and Contractor sfaplu,v� �op�c 4/26/2024 1 05:04:46 PDT
E�,vi S.
ARCHITECT: 062E1E642336487...
DocuSigned by: DocuSigned by: DATE:
.�Fb 4/18/2024 1 06:53:29 PDT
CONTRACTORS: '--"e DocuSigned b487... - DATE:
DocuSigned by:
4/30/2024 1 06:56:32 PDT
EXECUTIVE DIRECTOR OF AIRPORTS Fri&'&L SM1('L&—L
8E65F52F4C2F4D3... DATE:
COUNTY/DEPUTY ADMINISTRATOR - 05.01.2024
DATE:
f�JNROE COUNTY ATfOF9NE°!
A "ROV7E S FOd DS DS
C. ./ s AD�ec,. (�
J, A
ASSBSTA LINTY ATTORNEY"
Dnte 4/30/24
DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
NV K � GULF ST
PCCO #022
NV2A/Gulf Keystar JV Project:20-2039-01 -KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami, Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key West, Florida 33040
Prime Contract Change Order #022: Steel Fab - Material Escalation
TO: Key West International Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West, Florida 33040 Miami, Florida 33156
DATE CREATED: 4/02/2024 CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar JV)
CONTRACT STATUS: Approved REVISION: 0
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE: REVIEW DATE: 04/02/2024
INVOICED DATE: PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
REVISED SUBSTANTIAL SIGNED CHANGE ORDER 04/02/2024
COMPLETION DATE: RECEIVED DATE:
CONTRACT FOR: 20-2039-01:Key West International Airport TOTAL AMOUNT: $115,918.00
Concourse A
DESCRIPTION:
Steel Fabricators-Material Escalation
This Change Order includes costs associated with steel material escalation for the KWIA project.Cost breakdown is as attached.
ATTACHMENTS:
NV2A PCO#046($115,918.00 Steel Fab Material Escalationh.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
046 1 Steel Fab-Material Escalation $115,918.00
Total: $115,918.00
The original(Contract Sum) $101,461,771.00
Net change by previously authorized Change Orders $9,085,129.74
The contract sum prior to this Change Order was $110,546,900.74
The contract sum will be increased by this Change Order in the amount of $115,913.00
The new contract sum including this Change Order will be $110,662,813.74
The contract time will not be changed by this Change Order.
DS DS
Christopher Kopec(McFarland Johnson, Key West International Airport NV2A/Gulf Keystar JV
Inc.)
49 Court Street, Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton, New York 13901 Key West, Florida 33040 Miami, Florida 33156
EDocuSigned by: DocuSigned by: DocuSigned by: DocuSigned by:
062F1 RR4233R4A7... AFaSFS�Fdr�FdnZ �eF�,zA�G48, aFsa�+�n�aFznvs
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
4/26/2024 1 05:04:46 PDT 4/30/2024 1 06:56:32 PDT 4/18/2024 1 06:53:29 PDT
NV2A/Gulf Keystar JV Page 1 of 1 Printed On:4/2/2024 03:18 PM
DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
TM NV GULF BUILDING PCO #046 k ==" KE=-YST*"R
NV2A/Gulf Keystar JV Project:20-2039-01 -KWIA Concourse A and Terminal Improvements
9100 South Dadeland Blvd,Suite 600 Program
Miami,Florida 33156 3941 South Roosevelt Blvd.
Phone:(786)233-5060 Key West,Florida 33040
Prime Contract Potential Change Order 0Steel Fab ® Material
Escalation
TO: Key West International Airport FROM: NV2A/Gulf Keystar JV
3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Key West,Florida 33040 Miami,Florida 33156
PCO NUMBER/REVISION: 046/0 CONTRACT- 20-2039-01 -Key West International
Airport Concourse A
REQUEST RECEIVED FROM: CREATED BY: Mansour Sodagari(NV2A/Gulf Keystar
JV)
STATUS: Pending-In Review CREATED DATE: 1/25/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: _ PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $115,918.00
POTENTIAL CHANGE ORDER TITLE:Steel Fab-Material Escalation
CHANGE REASON: No Change Reason
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
Steel Fab-Material Escalation
This Change Order includes costs associated with steel material escalation for the KWIA project.
Cost breakdown is as attached.
ATTACHMENTS:
22596 RCO Oat Rev 1-Material_Escalatio€l.pdf
# Budget Code Description Amount
1 05-.12.10.00.S Structural Steel Framing( Material Escalation $105,380.00
Joist.Subcontractor
2 99-.99.99.66.0 Procore OH&P.Other Prime Contract 10%Markup $10,538.00
Grand Total: $115,918.00
Christopher Kopec(McFarland Johnson, Key West International Airport NV2A/Gulf Keystar JV
Inc.)
49 Court Street,Suite 240 3491 South Roosevelt Boulevard 9100 South Dadeland Blvd,Suite 600
Binghamton,New York 13901 Key West, Florida 33040 Miami, Florida 33156
Christopher Digita11ysig—dbyCh,istapher
Kopec Richard Strickland
Kopec Date:2024.03.261737:50-04'00' d
SIGNATURE DATE SIGNATURE DATE G ATUR DATE
NV2A/Gulf Keystar JV Page 1 of 1 Printed On: 1/25/2024 06:42 PM
DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
oon%guru REQUEST FOR CHANGE ORDER
( �, 721 N.E.44th Street NUMBER: 002.1
�E:i �� Fort Lauderdale, FL 33334 Phone: 954-772-0440
mr � Fax: 954-938-7527
TITLE: RCO#002.1 Material escalation DATE: 4/14/2023
PROJECT: 22596 Key West IACA&Terminal JOB: 22596
TO: Antonio Pinto
NV2A REASON: Price Only
CIC REFERENCE:
Phone: (954)599-0009
Fax:
DESCRIPTION OF CHANGE
Cost associated with material escalation, as per attached back up
Item Description Quantity Units Unit Price Net Amount
063 Material Escalation 1.00 /Lot 95,800.00 95,800.00
069 Overhead at 0.05 4,790.00 4,790.00
070 Profit at 0.05 4,790.00 4,790.00
By my signature below, I attest that I am authorized by my firm to enter into an agreement to purchase goods and/or services.As the Buyer,
hereby authorize Steel Fabricators, L.L.C.to proceed with the additional work described herein and do guarantee compensation on the basis
noted above. If schedule impact listed below is zero or not listed, additional contract time required will be determined by Steel Fabricators at the
time of implementation due to changes described above.
The Contract Sum Will be Increased 105,380.00
The Contract Time Will Not be Changed TBD
ACCEPTED:
NV2A
BY: Antonio Pinto BY:
DATE: DATE:
PAGE 1 OF 1
FORM:F CO 01 RFT SF
DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
Cost per Total net
Item Tons/SQ escalation OH&P 10%
ton increase
V���:r:;lh 620 $ 49,000 $ 4,900 O,
Raw Materials 468 $ 100 $ 46,800 $ 4,680 5 q ^180
ut aII gin.
DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
CLIFFS
Imoo....
CLF E::L.AND-CLIFFS INC.
NEWS RELEASE
Cleveland-Cliffs Announces Price Increase for Hot Rolled, Cold Rolled and
Coated Steel Products
CLEVELAND — February 27, 2023 — Cleveland-Cliffs Inc. (NYSE: CLF) today announced that it is
increasing current spot market base prices for all carbon hot rolled, cold rolled and coated steel products
by a minimum of$100 per net ton, effective immediately with all new orders. Cliffs' minimum base price for
hot rolled steel is now$1,100 per net ton.
About Cleveland-Cliffs Inc.
Cleveland-Cliffs is the largest flat-rolled steel producer in North America. Founded in 1847 as a mine operator, Cliffs
also is the largest manufacturer of iron ore pellets in North America. The Company is vertically integrated from mined
raw materials, direct reduced iron, and ferrous scrap to primary steelmaking and downstream finishing, stamping,
tooling, and tubing. Cleveland-Cliffs is the largest supplier of steel to the automotive industry in North America and
serves a diverse range of other markets due to its comprehensive offering of flat-rolled steel products. Headquartered
in Cleveland, Ohio, Cleveland-Cliffs employs approximately 27,000 people across its operations in the United States
and Canada.
Source: Cleveland-Cliffs Inc.
MEDIA CONTACT: INVESTOR CONTACT:
Patricia Persico James Kerr
Senior Director, Corporate Communications Manager, Investor Relations
(216) 694-5316 (216) 694-7719
CII_IE-:VIE-:II_AINE).-CI._IIFIE=S IINC„ « 200 IaUBUIC SQUARE . SMITE 3300 « CI._IE VEII_AND,OH 44114-2544
DocuSign Envelope ID:531552D0-DC32-4F11-A544-BA02CDD28384
Eduardo Dominguez
From: Frank Ladisa
Sent: Wednesday, April 12, 2023 2:36 PM
To: Eduardo Dominguez
Cc: Shane Russell
Subject: Key West International Airport Concourse A I #22596 I Material increase
Attachments: CLF_20230227_Cleveland-Cliffs Announces Price Increase for Hot Rolled, Cold Rolled
and Coated Steel Products.pdf; KWIA escalation .xlsx
Eduardo see attached summary with back up on escalation,
I..hanks
Frank Lad'isa
Celli 91.54 21.4 9048 III Fax'9!!:4 938 71.52.7
steel' II :l uu u�.�!!!utruu d 4 11 C
.........................................................................................
721 N.E 44TH ST
FT Lauderdale, FL, 33334
AISC Certified Fabricator/Erector
int
�ru�r���r��r:,,, l,�lla rra°1onu }�P;,iu�aiuu�IlUs�,�a°uirn:, I uuull a"�Itl.„..
From: Bagley, Robert (VSC) <rbagley@vulcraft-sc.com>
Date: March 20, 2023 at 5:46:50 AM CST
To:<II:::.II. .::j..... . ... s ,ll.::..p..!M>; Eduardo Dominguez<.[:J�.g!.I"0..!!.!n.,gl:i.'.z..
Subject: 03-20-23; 014-22-0678 1 Key West International Airport Concourse A #22596 Re. Schedule/
cost
Eduardo,
Good morning,
Got notice last week that we are back on for getting this job underway (confirmed Vulcraft contract with
Steel Fabricator LLC). We will shoot for the below schedule, unless you have some modifications needed
to it. Please let me know if you should need anything from me. Thanks.
OFA= (9'�T04-14-23)
BFA= (02 2 2; 04-28-23)
Delivery= (End of June—further out than price protection date)
September Delayed delivery increase adds$49,000.
II ladle
Vulcraft Illlro,pect Manager
1