PROJECT TITLE: MTH Chiller Replacement CHANGE ORDER NO: 3
INITIATION DATE:_July 15,2024
TO CONTRACTOR: Air Mechanical&Service CONTRACT DATE: October 19,2022
Corporation
The Contract is changed as follows:
The original (Contract Sum)(Guaranteed Maximum Price).......................................... $ 423,500.00
Net change by previously authorized Change Orders..................................................$ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$ 423,500.00
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)
(unchanged) by this Change Order...... $ 0
The new(Contract Sum)_(Guaranteied Maximum Price)including this Change Order is....... $ 423,500.00
The Contract Time will be C 1 r �'ed)(decreased)(unchanged)by............................... 160 days
The date of Substantial Completion as of the date of this Change Order is....................... June 17,2024
Detailed description of change order and justification:
This change order is for the extension of contract time to August 15,2024 (from 3/7/2024)
This change order No.3, no cost adjustments.
This change Order is 0%of the original contract price.
Not valiid until si ned by Ouwrner,Architect if applicable), and Contractor
ARCHITECT: 7/16/2 4
...� Date .._...
CONTRACTOR: 16/24
ate
7-16-24
DIRECTOR OF AIRPORTS Date
W
MONROE COUNTY: _ 07 24.2024
Asst.ICounty Administrator � Date
NPOE COUNTY ATTOInINEY
A 13111OVE7A T FORM
PEI J.
ASSISTA U A EY
Date 7/23/24
Change Order Attachment per Monroe County Code Section 2-58(b)
Change Order was not included in the original contract specifications. Yes( ) No( X)
If Yes, explanation
- Change Order was included in the original specifications. Yes ( } No ( X )
If Yes, explanation of increase in price:
Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes()No(X)
If Yes, explanation as to why it is not subject for a calling for bids..
- Project architect approves the change order. Yes(X ) No( )
If no,explanation of why:
- Change Order is correcting an error or omission in design document. Yes ( } No ( X )
- Should a claim under the applicable professional liability policy be made? Yes( ) No( X )
Explain:
O AI EC;' SERVICE CORR
2700 Avenue of the Americas
Englewood, Florida 34224
Phone 941-475-3715
Fax 941-475-3725
July 15, 2024
Florida Keys Marathon
International Airport
9400 Overseas Highway
Marathon Florida, 33050
Attn: Ryan Forney
Subject: Change Order Request#3 MTH Chiller Replacement Project (Project#
403-635110 and 403-635111) "Time Extension"
Dear Ryan,
In reference to the above subject project, Air Mechanical & Service Corp is
requesting an add change order to extend the contract time to August 15, 2024.
If further information is required, please contact me.
Sincerely,,
'1
Blaiiie Byers