4th Change Order 07/24/2024 MONROE COUNTY/DEPARTMEW OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECT TITLE: MTH Chiller Replacement CHANGE ORDER NO:4
INITIATION DATE:_July 15,2024
TO CONTRACTOR: Air Mechanical&Service CONTRACT DATE: October 19,2022
Corporation
The Contract is changed as follows:
The original(Contract Sum)(Guaranteed Maximum Price).......................................... $ 423,500.00
Net change by previously authorized Change Orders..................................................$ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$ 423,500.00
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)
(unchanged)by this Change Order...... $1926.00
The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is.......$ 423,500.00
The Contract Time will be(increased)(decreased)(unchanged)by............................... 0 days
The date of Substantial Completion as of the date of this Change Order is....................... June 17, 2024
Detailed description of change order and justification:
This change order is for spare parts for chiller to August 15, 2024
This change order No.4,for the cost of$1926.00 to be paid from Unforeseen conditions allowance.
This change Order is 0.4%of the original contract price.
Not valid until si ned bv Owner.Architect if aRplicablel, and Contractor
ARCHITECT: (Zkkoum FG/� 7/16/2 4
�_.____________________________ -w..____-w.. �_____,W...-______________Date
CONTRACTOR: " "" 7/15125
DIRECTOR OF AIRPORTS �� 7e 24
Date
MONROE COUNTY° „y A . i..:'istra,`" tor 0,7„2,4„2,024
Asst./ ou n t dmn Date
NPOF COUNTY ATTonNEY
THOVE ?T FORM
PEI� J. . .�.
I�SSIrTA O ATTORNEY
Date 7/23/24
Change Order Attachment per Monroe County Code Section 2-58(b)
Change Order was not included in the original contract specifications. Yes( ) No( X)
If Yes, explanation
- Change Order was included in the original specifications. Yes ( ) No ( X )
If Yes, explanation of increase in price;
Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes()No(X)
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes(X ) No ( )
If no,explanation of why:
• Change Order is correcting an error or omission in design document. Yes ( ) No ( X )
Should a claim under the applicable professional liability policy be made? Yes( ) No( X )
Explain
C HANICA,LRVICE CORR
2700 Avenue of the Americas
Englewood, Florida 34224
Phone 941-475-3715
lop Fax 941-475-3725
July 15, 2024
Florida Keys Marathon
International Airport
9400 Overseas Highway
Marathon Florida, 33050
Attn: Ryan Forney
Subject: Change Order Request#4 MTH Chiller Replacement Project(Project#
403-635110 and 403-635111) "Spare Chiller Parts"
Dear Ryan,
In reference to the above subject project, Air Mechanical &Service Corp is
requesting an add change order to provide (1) new flow switch and (1) new
thermistor kit.
Cost : $1605.00
AMSCO Markup: $321.00
If further information is required, please contact me.
Sinc rel
f
Blaine Dyers °""
Service Sales