1st Change Order 08/14/2024 MONROE COUNTY/DEPARTMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECT TITLE: EYW Beacon Pole CHANGE ORDER NO: 1
And Relocate Existing
TO CONTRACTOR: Florida Keys Electric, Inc. INITIATION DATE: April 16, 2024
CONTRACT DATE: NTP Construction: March 13, 2024
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price).......................................... $ 379,000.00
Net change by previously authorized Change Orders.................................................. $ 0
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$ 379,000.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order.......$0
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is....... $ 379,000.00
The Contract Time will be (increased) (decreased) (unchanged) by............................... 163 days
The date of Substantial Completion as of the date of this Change Order is....................... 9/2 3/2 4
Detailed description of change order and justification:
This change order is for: Time extension on project for FAA clearance, change in construction method,work
conflicting with other projects.
This change Order is 0.0% of the original contract price.
Not valid until signed by Owner,Architect (if applicable), and Contractor
�,
ARCHITECT: 7/29/24
Date
CONTRACTOR: 7/29/2024
Date
Richard StricklandadR�abEmo o„
DIRECTOR OF AIRPORTS
Date
MONROE COUNTY: " �� "�� 08/14/2024
Asst./County Administrator Date
01 NR ECOUNTY ATTORNEY
ArAFOI
ED O J. .w
ASSI ATTORNEY
Elate 8/2/24
Change Order Attachment per Monroe County Code Section 2-58(b)
- Change Order was not included in the original contract specifications. Yes ( ) No (X )
If Yes, explanation
- Change Order was included in the original specifications. Yes ( ) No ( X )
If Yes, explanation of increase in price:
- Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X)
If Yes, explanation as to why it is not subject for a calling for bids:
- Project architect approves the change order. Yes(X) No ( )
If no,explanation of why:
- Change Order is correcting an error or omission in design document. Yes ( ) No ( X )
Should a claim under the applicable professional liability policy be made? Yes ( ) No ( X )
Explain: