1st Change Order 08/14/2024 MONROE COUNTY/DEPARTMENT OF AIRPORTS CONTRACT CHANGE ORDER PROJECT TITLE: EYW Beacon Pole CHANGE ORDER NO: 1 And Relocate Existing TO CONTRACTOR: Florida Keys Electric, Inc. INITIATION DATE: April 16, 2024 CONTRACT DATE: NTP Construction: March 13, 2024 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price).......................................... $ 379,000.00 Net change by previously authorized Change Orders.................................................. $ 0 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$ 379,000.00 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order.......$0 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is....... $ 379,000.00 The Contract Time will be (increased) (decreased) (unchanged) by............................... 163 days The date of Substantial Completion as of the date of this Change Order is....................... 9/2 3/2 4 Detailed description of change order and justification: This change order is for: Time extension on project for FAA clearance, change in construction method,work conflicting with other projects. This change Order is 0.0% of the original contract price. Not valid until signed by Owner,Architect (if applicable), and Contractor �, ARCHITECT: 7/29/24 Date CONTRACTOR: 7/29/2024 Date Richard StricklandadR�abEmo o„ DIRECTOR OF AIRPORTS Date MONROE COUNTY: " �� "�� 08/14/2024 Asst./County Administrator Date 01 NR ECOUNTY ATTORNEY ArAFOI ED O J. .w ASSI ATTORNEY Elate 8/2/24 Change Order Attachment per Monroe County Code Section 2-58(b) - Change Order was not included in the original contract specifications. Yes ( ) No (X ) If Yes, explanation - Change Order was included in the original specifications. Yes ( ) No ( X ) If Yes, explanation of increase in price: - Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X) If Yes, explanation as to why it is not subject for a calling for bids: - Project architect approves the change order. Yes(X) No ( ) If no,explanation of why: - Change Order is correcting an error or omission in design document. Yes ( ) No ( X ) Should a claim under the applicable professional liability policy be made? Yes ( ) No ( X ) Explain: