2nd Change Order 04/29/2024 MONROE COUNTY/DEPARTMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECT TITLE: Relocate Runway 7-26 Phase 1 —Tree Clearing CHANGE ORDER NO: 2
INITIATION DATE: _April 18th_, 2024.
TO CONTRACTOR: A+ Environmental CONTRACT DATE: November 15, 2022
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price).......................................... $676,990.00
Net change by previously authorized Change Orders.................................................. $ 7,500.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$684,490.00
The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order.......$ 00,000.00
The new (Contract Sum _(Guaranteed Maximum Price) including this Change Order is....... $ 684,490.00
The Contract Time will be (increased) (decreased) (unchanged) by............................... 100 days
The date of Substantial Completion as of the date of this Change Order is......................._July 30th_, 2024
Detailed description of change order and justification:
This change order is to increase contract time by100days to accommodate revisions to surveyor's
and arborist's collected data within runway approaches, and enable contractor to properly complete
scope of work for the project.
This change Order is 0.0% of the original contract price.
Not valid until signed by Owner, Engineer(if applicable), and Contractor
ENGINEER: 04/18/2024
Date
CONTRACTOR: 4/18/24
Date
DIRECTOR OF AIRPORTS 04.25.2024
Date
MONROE COUNTY: m , .� 04.29.2024
Ass ./County Administrator Date
�?
NROE COUNTY TT"OFiNEY
SO4Et FOPJ
'
ASSI�rFh
J�NTY ATTORNEY
Date 4/251124
Change Order Attachment per Monroe County Code Section 2-58(b)
— Change Order was not included in the original contract specifications. Yes ( ) No (X )
If Yes, explanation:
— Change Order was included in the original specifications. Yes ( X ) No ( )
If Yes, explanation of increase in price: Not
applicable. No cost increases are
associated with this change order.
— Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X)
If Yes, explanation as to why it is not subject for a calling for bids:
— Project architect approves the change order. Yes(x) No ( )
If no,explanation of why:
— Change Order is correcting an error or omission in design document. Yes ( ) No ( X)
Should a claim underthe applicable professional liability policy be made? Yes ( ) No ( x )
Explain: