Loading...
3rd Change Order 10/23/2024 MONROE COUNTY/DEPARTMENT OF AIRPORTS CONTRACT CHANGE ORDER PROJECT TITLE: Relocate Runway 7-25 Phase 1 —Tree Clearing CHANGE ORDER NO: 3 INITIATION DATE:_October 911_,2024. TO CONTRACTOR: A+Environmental CONTRACT DATE:—November 15'h_,2022. The Contract is changed as follows: The original(Contract Sur") (Guaranteed Maximum Price) $676,990.00 Net change try previously authorized previously authori ed Change Orders $ 7,500.00 ( .� ecreas s ..,� .....$684;490.00 The(Contract Sure (Guaranteed Maximum Pace) prior to this Chan e order ww The (Contract Sum) (Guaranteed Maximum Price)will be tncreaseci (d ed d' b this e Order. $ 1,230.03 (ui�change ) y Chang. The new Contract Sum)-(Guaranteed Maximum Price) including this Change Order is. $ 683,259.97 The Contract Time will be increased' (decreased (unchanged b 500 days 9 ) y......................... .. The date of Substantial Completion as of the date of this Change Order is................. ....December 121h, 2024 Detailed description of change order and justification: This change order is to increase contract time by 500 days to accommodate revisions to surveyor's and arborist's collected data within runway approaches and enable contractor to properly complete scope of work for the project. This change Order is (0.001797%of the original contract price. Not valid until si ned b Owner Eri ineer if'a licable and Contractor Ka0 Q U 1 /09124 ENGINEER: Date 10/16/2024 CONTRACTOR: L Date DIRECTOR OF AIRPORTS Date Christine Digitally signed by Christine Hurley Hurley Date 2024.10.23 18 14 36 MONROE COUNTY: -- - - ' Asst./County Administrator Date NROE COUNTY ATTOnNEYq AOVEQ FORM PED 01 CA ASSIST UNTY ATTORNEY Date 10/21/24 Change Order Attachment per Monroe County Code Section 2-58(b) — Change Order was not included in the original contract specifications. Yes ( ) No (X ) If Yes, explanation: — Change Order was included in the original specifications. Yes ( X ) No ( ) If Yes, explanation of increase in price: Not applicable. No cost increases are associated with this change order. — Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X) If Yes, explanation as to why it is not subject for a calling for bids: — Project architect approves the change order. Yes(x) No ( ) If no,explanation of why: — Change Order is correcting an error or omission in design document. Yes ( ) No ( X) Should a claim underthe applicable professional liability policy be made? Yes ( ) No ( x ) Explain: