Loading...
1st Change Order 03/04/2025 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 01 MCDC Stock Island Stucco Repairs INITIATION DATE: 02/28/2025 CONTRACT DATE: 07/17/2024 TO CONTRACTOR: Quick Painting Group Corp. 9867 S Orange Blossum Trail, Ste. 109 Orlando, Florida 32837 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)............................................$240,000.00 Net change by previously authorized Change Orders...................................................$ 0.00 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$240,000.00 The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order.......$ 0.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is........$240,000.00 The Contract Time will be (increased) (decreased) (unchanged) by.................................. 104 days The date of Substantial Completion as of the date of this Change Order is........................ 03/28/2025 Detailed description of change order and justification: This is a no cost time extension change order. Due to access and staffing issues, the contractor has requested 104 days be added to the contract time. The previous substantial completion date was December 14, 2024. This change Order is 0% of the original contract price. Not valid until signed by Owner, Engineer(if applicable), and Contractor ENGINEER: N/A Date CONTRACTOR: . - - 02/28/2024 C pick Painting Group Corp. Date DEPARTMENT DIRECTOR °�- 02/28/2024 Cary Vi Date Project Management Digitally signed by Christine Christine Hurley Hurley COUNTY ADMINISTRATOR: Date:2025.03.0416:31:35-05'00' Christine Hurley Date Change Order Attachment per Ordinance No. 005-2023 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: No cost time extension. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $100,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ❑ No If no, explanation of why: N/A—not needed for time extension only change order • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: MQuiclkPaintingGROUP To: Matthew R. Howard Monroe County Project Management Department 1100 Simonton Street, 2-216 Key West, Florida 33040 (305)850-8123 - howard-matthew@monroecounty-fl.gov Subject: Formal Request for Project Extension - MCDC Stock Island Stucco Repairs Dear Matthew Howard, We are writing to formally request an extension for the final completion of the MCDC Stock Island Stucco Repairs project. As per the original agreement, the project commenced on October 15, 2024, with final completion set for January 13, 2025. Despite following the schedule, additional time is needed to maintain the high quality and precision required for the project. Given that the project requires careful attention to detail and precision, we believe that an extension of 104 calendar days is necessary, moving the final completion date to April 27, 2025. Please know that our team is committed to delivering an outstanding result, and we are dedicated to upholding the highest standards of quality throughout the duration of the project. We appreciate your understanding and support as we work to ensure the successful and meticulous completion of this important work. We look forward to your approval and continued collaboration on this project. Thank you for your attention to this matter. Sincerely, Andres Sanchez President Quick Painting Group Corp 407-733-0401 quickpaintinggroup@gmail.com