HomeMy WebLinkAboutNotice to Proceed Construction Key 'West A Intermationa l Airport / a May 7, 2025 Mr. Robert Lopez General Asphalt 4850 NW 72nd Avenue Miami, FL 33166 Subject: Notice to Proceed Construction Relocate Runway 7-25 The Florida Keys Marathon International Airport Mr. Lopez: Please consider this letter as a Notice to Proceed (NTP) Construction effective on May 13, 2025, per the requirements of the above contract dated December 11th, 2024. The Contract time of 162 Calendar Days will begin on May 13, 2025, with a completion date of October 21, 2025. Please note that within this time it is imperative that Phase 5 work must be completed between August 18, 2025, and October 7, 2025 as noted in Special Provision No. 3 of the Project Manual. If you have any questions, please do not hesitate to contact this office. Sincerely, �1 Richard Strickland, CM Executive Director of Airports 305.393.7742