HomeMy WebLinkAboutNotice to Proceed Construction Key Nest IW auPrnad Nep.11 3491 South Roosevelt Blvd. Key West, FL 33040 August 15, 2025 Mr. Richard Toppino Charley Toppino & Sons, Inc. PO Box 787 Key West, FL 33041 Subject: Notice to Proceed Construction Taxiway A Extension and Mitigation Key West International Airport Dear Mr. Toppino: Please consider this letter as a Notice to Proceed (NTP) for Construction effective on August 25th, 2025, per the requirements of the above subject contract dated November 17th, 2021. The Contract time of 365 Calendar Days will begin on August 25th, 2025, with a completion date of August 25th, 2026. If you have any questions, please do not hesitate to contact this office. Sincerely, Richard Digitally signed by Richard Strickland Strickland Date:2025.08.15 13:10:34-04'00' Richard Strickland Executive Director of Airports 305.393.7742