Loading...
HomeMy WebLinkAbout1st Change Order 08/18/2025 Cowmcr gAt G.� F PROJECT TITLE: Relocate Runway 7-25 CHANGE ORDER NO: 1 INITIATION DATE: 05/19/2025 TO CONTRACTOR: General Asphalt Co. LLC CONTRACT DATE: 12/18/2024 The Contract is changed as follows: The original Contract Sum .......................................................m..._............... .............$30,152,480.18 Net change by previously authorized Change Order.....................3.,,,...,,..........,w..........$0.00 The Contract Sum prior to this Change order was....................................w.....................$30,152,480.18 The Contract Sum is (decreased) by this Change Order 1..............................,..............$0.00 The Revised 1 Contract Sum including this Change Order.......n,,,,,,,,,,,,,,,_..,,,.,..........--.$30,152,480.18 This Change Order No.1 only includes revisions to unit prices and quantities to the contract bid items as noted in Attachment 1. This is a net zero Change Order. The total cost to complete the work as noted within this change order is $0.00. See Attachment 2 for the updated Summary of Quantities sheet G-004. Net change to contract Change Order 1: $0.00 The construction commencement was May 13, 2025. This Change Order 1 does not increase contract time. Contractor agrees to accept the increase/decrease in monetary compensation and hereby waives and releases any and all claims for any additional compensation related to these bid items. This Change Order 1 represents 0.00 % of the original contract price. Not valid !until a raved by Owner Architect jif applicable).and Contractor ARCHITECT/ENGINEER 8/12/2025 Date p� Digitally±,tt�n�. b ,6rrse Semprun Jose �� pl Date 202508 61 ,10:35-04'00' CONTRACTOR Date 08. AIRPORTS DIRE CTOR TOR CChristine Rally signed by Date L 'Christine Hurley COUNTY/ASSISTANT ADMINISTRATOR Hurley Date:2025.'0 12:1300-04'00' Date NF30E COUNTY C "E FOPRJA NI M PFD O J, ~ A G ASS[ NTY AMRNEY Oat 8/14/25 Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: 1. The negotiations and exact scope reduction would only be finalized once the Contractor's Bid was received. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5% of contract price (whichever is greater). Yes❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project engineer/architect approves the change order. Yes ® No ❑ If No, explanation of why: • Change Order is correcting an error or omission in design document. Yes❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Attachment 1: Revisions to Project Bid Items 8 d 8� � a o d V L C OC 1 W ry N 1 10 �q NO � o ON, Ln W LL u F3 _ a � z o u w z g z a il� F � F o S OO z u u Z a Z z w o G Z 4i OC / LD l� a Z, ¢o z a o z w $ 03a � O- � � " FRG � w � I: Cf w o ¢ uEd 1" o 0 o a my v g R $ o u u 'L � � � � o00 a as � � v� � � Attachment 2: Revised Summary of Quantities Sheet G-004 .... ..... ...� ._____.. _,�. ....._..._.",..�. .... .... ........ ,.. mwa�acrva�ainraaoi asnssi . ..... .................. ..........� si — — . .......�. o e, OA21 WW S $E 9 a' "� � •••••• • .•.. Nnx w�wd+�.Wl 'W.: wmnHrN IXAv:YSATaX........ .... ..........,..�.. .... �......... ,�....._... n............ � ...w....�: n �r f e �wy�rw..xgww"+wr�w�y�^r I"ail v 5��s m. � .. _ r a R.Ht s 3 _s, I� '� � � � � wY �'3'3 _�r ,�G w� � �5 q I� � m'�3 S ��'�,�� w � �,I �•y � tt awe ... � 0 0 .� _ e _. _, e e L LSOSZOL 3109101d�SMA NO1VInBtl olk`Fltl ."kaY�"n.".tl AtlM1WntlW1M61HOdtlN590.']��3�MO3xOYll3tlOIYV�.tl35111�