Loading...
HomeMy WebLinkAbout3rd Change Order 09/10/2025 MONROE COUNTY/ DEPARTMENT OF AIRPORTS CONTRACT CHANGE ORDER PROJECT TITLE- CHANGE ORDER NO: 003 Key West International Airport INITIATION DATE: September 5, 2025 Noise Insulation Program Construction of NIP Group 1 CONTRACT DATE: October 16, 2024 TO CONTRACTOR: Marino Construction Group, Inc. The Contract is changed as follows: The original Contract Sum ........... ............. ...................................... .........$1�473'006'00 Net change by previously authorized Change Orders........ ......... .................... .........<$,11,809.00> The Contract Sum prior to this Change order was............. .............................. .......$1,461,197.00 The Contract Sum will be unchanged by this Change Order.......-.......-.... ...... ....... ...... WOO The new Contract Sum including this Change Order is ....---...... ................ .......$1,461,197.00 The Contract Time will be increased by.....,........... ....... ....................... .....................--56 days The date of Substantial Completion as of the date of this Change Order is...... October 31, 2025 Detailed description of change order and justification: The original contract time was 235 calendar days. Change Order 002, dated July 10, 2025, added 68 calendar days to the original contract time. Total contract time (including Change Order 002) prio to this Change Order(Number 003) was 303 calendar days, which extended the contract time until Friday, September 5, 2025, See the attached request for additional time from Marino Construction Group that describes the circumstances that prevented them from completing construction tasks on schedule. This Change Order(Number 003) is for additional time(56 calendar days), with no change in the Contract Sum. With the addition of 56 calendar days, contract time is extended until Friday, October 31, 2025, Not valid until signed by Owner, Architect(if a2plicable),and Contractor ARCHITECT: 9/12/25 Date CONTRACTOR: Date AIRPORTS DIRECTOR 09.16.2025 Digitally sipn%tchy Christine COUNTY/ASSISTANT ADMINISTRATOR Christine Hurl Fjtale� Date:20250131113)16:17:56-04'00' NROE COUNTY ATTOnN79 AOVEQ FORM PED 40 J, ERCAGG--� ASSISTIMOUNTY ATTORNEY Date e 9/16/25 Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes❑ No If Yes, explanation: • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5%of contract price (whichever is greater). Yes❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes[]No Should a claim under the applicable professional liability policy be made? Yes❑ No Explain: M R I N 0 C b ICJ S T R U C T 1 0 N to R, 0 U P Ivey West International Airport Noise Insulation Program Construction of NIP Group I Change Order NO: 003 Due to incorrect measures in the Pre-Constructiongobsite walk, "Door A." sidelight is the wrong, size with the door at 2916 Rivera Drive, It is wider than the CMIJ wall opening. The opening for the door and sidelight is 54"'amide X 83 1/2"I"Iigh, The existing received door is 38" Wide with a 1" mullion, which leaves 15". We are in need. I" buck (1/?" ea. side) so the total width of the sidelight would be 1.4" wide.. We inquired with Ilan Hamilton at H. Prairie to order these products for correct material installation.. Which would include a 14" wide sidelight and niullion caps. Per the supplier it will take 5-6 weeks to receive the product and an additional 2 weeks to schedule the installation. Marino is requesting 56 additional calendar days from September 5,2025 to complete construction at the location of 2916 Riviera:Dr. Sincerely, John White, Project Manager CGCO21647 1305-359-5269 1 3100 overseas HWY Key West, FL 330140 1 www,marino-constructlon.cc ,