Loading...
HomeMy WebLinkAbout3rd Change Order 10/24/2025 MONROE COUNTY/ENGWEERING/ERO_MCTMANAGEMEW CONTRACT CHANGE ORDER PROJECT TITLE* Relocate Runway 7-25 CHANGE ORDER NO: 3 INITIATION DATE-. 10/17/2026 TO CONTRACTOR. General Asphalt Co. LLC CONTRACT DATE: 12/18/2024 The Contract is changed as follows: The original Contract Sum ............ ..................... .............................. ...... ...... ....$30,152,480A8 Net change by previously authorized Change Order ... ...... .............. ($11,317,04) The Contract Surn prior to thiis Change order was.......... ........... ......—.$30, 141,163.14 The Contract Sum is (decreased) by this Change Order 3...............................................$0.00 The Revised I Contract Sum including this Change Order .......... ....... ..........................$30,141,163.14 This Change Order No, 3 only includes a time extension till the end of 2025 to finish any punch list items as the 162 calendar days will be up on 10/21/2025. This is a time extension only, no cost Change Order, The total cost to complete the work as noted within this change order is$01.00 Net change to contract Change Order 3: $0.00 The construction commencement was May 13, 2025. This Change Order 3 extends the contract time to 12/31/2025. Contractor agrees to accept the increase/decrease in monetary compensation and hereby waives and releases any and all claims for any additional compensation related to these bid items. This Change Order 3 represents 0.00 % of the original contract price. Not valid until approved by Owner,Architect if applicable), and Contractor Digitally signed by Robert B. Robert B.Aydin, Aydin,P.E. DN o=Robert B.Aydin,P.E., u ARCHITECT/ENGINEER P.E. D-ate:s 2025.10.21 09 18 05-04'00' Date e CONTRACTOR �7 vp?o Pet 11/ "�'- 4�7400 'Date , 10.21.2025o AIRPORTS DIRECTOR Date y Digitally signed by Christine Hurley COUNTY/ASSISTANT ADMINISTRATOR Christine Hurle Date 2025 10.24 08 02 16-04'00' Date ', NCI OE COUNTY ATTOnNEY A P130VE FORM PED 0 J CA9G— ASSISTA�R iW'UNTY ATTORNEY Dat 10/21/25 Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ❑ No If Yes, explanation: • Change Order was included in the original specifications, Yes❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5%of contract price (whichever is greater). Yes❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project engineerlarchitect approves the change order. Yes ® No ❑ If No, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: