HomeMy WebLinkAbout#11th Amendment 10/15/2025
DATE: November 04, 2025
TO: Rhonda Haag, Chief
Resilience Officer
Janet Gunderson,
Grants Coordinator
FROM: Brynn Morey, Deputy Clerk
SUBJECT: October 15, 2025 BOCC Meeting
The following item has been executed and added to the record:
P3 Approval to enter into Amendment No. 11 for $65,752.82 for professional engineering
services, for the design, permitting and preparation of contract plans for the milling and
resurfacing of roads in the Stillwright Point community, under the contract with HDR,
Inc. for the Roads Vulnerability Analysis and Capital Plan for County-maintained roads.
.
Should you have any questions please feel free to contact me at (305) 292-3550.
cc: County Attorney
Finance
File
KEY WEST MARATHON PLANTATION KEY
500 Whitehead Street 3117 Overseas Highway 88770 Overseas Highway
Key West, Florida 33040 Marathon, Florida 33050 Plantation Key, Florida 33070
AMENDMENT NO. 11
TO THE AGREEMENT
FOR
SEA LEVEL RISE VULNERABILITY ANALYSIS AND PLANNING
FOR COUNTY MAINTAINED ROADS INFRASTRUCTURE ADAPTATION
BETWEEN
MONROE COUNTY BOARD OF COUNTY COMMISSIONERS
AND
HDR ENGINEERING INC.
th
This AMENDMENT NO. 11 (“Amendment”) is made and entered into this15 day of October, 2025
to that Agreement dated May 22, 2019 as amended November 17, 2020 under Amendment No. 1,
April 21, 2021 under Amendment No. 2, November 17, 2021 under Amendment No. 3, June 15, 2022
under Amendment No. 4, October 19, 2022 under Amendment No. 5, June 21, 2023 under
Amendment No. 5A/5B, June 21, 2023 under Amendment No. 6, November 8, 2023 under
Amendment No. 7, January 31, 2024 under Amendment No. 8, October 16, 2024 under Amendment
No. 8A, January 31, 2024 under Amendment No. 9, and June 17, 2025 under Amendment No. 10
(cumulatively, "Agreement"), by and between Monroe County "COUNTY," and HDR Engineering,
Inc. "CONSULTANT".
WITNESSETH:
WHEREAS, the COUNTY recognized the need for immediate, coordinated, and visionary action to
address the impacts of a changing climate and ensure the COUNTY provides for resilience for its
more than 300 miles of roads infrastructure; and
WHEREAS, the recommendation for a Roads Adaptation Plan is contained in Green Keys Item 2-
14, which specifies that the County shall conduct a County-wide roads analysis to identify near-term
roads subject to inundation risk, including nuisance flooding, and to include related green
infrastructure, where appropriate; and
WHEREAS, on May 22, 2019, the parties entered into the Agreement, so that the CONSULTANT
could provide professional services for vulnerability analysis on roadways in the unincorporated
Monroe County; and
WHEREAS, the parties wish to amend the Agreement in order to design, permit, and prepare
contract plans for milling and resurfacing the roads in the Stillwright Point Community; and
WHEREAS, under the terms of this Amendment No. 11, the Consultant shall conduct the roadway
milling and resurfacing design assessment; and
NOW, THEREFORE, in consideration of the mutual promises, covenants and agreements stated
herein, and for other good and valuable consideration, the sufficiency of which is hereby
acknowledged, COUNTY and CONSULTANT agree as follows:
1. Articles 2.1, 7.1, and 7.2.1 in the AGREEMENT are amended as follows:
-1-
ARTICLE II SCOPE OF BASIC SERVICES
2.1DEFINITION
CONSULTANT’S revised Scope of Basic Services shall consist of that described in attached Exhibit
A-11. The CONSULTANT shall commence work on the services provided for in this Amendment
promptly upon his receipt of a written notice to proceed from the COUNTY.
ARTICLE VII COMPENSATION
7.1 PAYMENT SUM
The COUNTY shall pay the CONSULTANT for the CONSULTANT’S performance of this
Amendment No. 11 an amount not to exceed Sixty-Five Thousand, Seven Hundred, Fifty-Two
Dollars and Eighty-Two Cents ($65,752.82). Thetotal Agreement is not to exceed $3,196,218.78,
which includes the lump sum amount and time and materials amount of $3,007,051.60 for Required
Services and an amount not to exceed $189,167.18 for Optional Services. The Contract Sum shall
not exceed this amount unless amended by formal approval of the Monroe County Board of County
Commissioners (BOCC). No charges shall be incurred by the COUNTY other than products or
services that were ordered, provided and agreed upon by the COUNTY.
7.2 PAYMENTS
7.2.1 For its assumption and performances of the duties, obligations and responsibilities set forth
herein, the CONSULTANT shall be paid according to the revised Deliverable Schedule attached as
Exhibit B-11, and according to the Florida Local Government Prompt Payment Act (Section 218.70,
Florida Statutes). Payments will be lump sum or time and materials, as indicated in Exhibit B-11.
Partial payments of tasks and deliverables shall be allowed for any item over $5,000. The
CONSULTANT shall submit to the COUNTY an invoice with supporting documentation in a form
acceptable to the Office of Monroe County Clerk and Comptroller (County Clerk). Acceptability to
the County Clerk is based on generally accepted accounting principles and such laws, rules and
regulations as may govern the County Clerk’s disbursal of funds. The Sustainability Director will
review the request, note her approval of the request and forward it to the County Clerk for payment.
7.2.2 Exhibits A-11 and B-11 attached to this Amendment are added to the Agreement.
nd
7.2.3 All other provisions of the AGREEMENT dated the 22 day of May 2019 and amended
November 17, 2020, April 21, 2021, November 17, 2021, June 15, 2022, October 19, 2022, June 21,
2023, November 8, 2023, January 31, 2024, October 16, 2024, and June 17, 2025,not inconsistent
herewith, shall remain in full force and effect.
THE REMAINDER OF THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK.
-2-
EXHIBIT A-11
Monroe County Roadway Vulnerability Analysis and Capital Plan
Stillwright Point Design, Permitting, and Contract Plans for
Milling and Resurfacing Project
Scope of Services
REVISED: September 15, 2025
The following tasks are added through this Amendment. All other tasks from Exhibit A in the original
Agreement as well as Exhibits A-1, A-2, A-3, A-4, A-5, A5A/A5B, A-6, A-7, A-8, and A-10 in prior
amendments remain unchanged.
The scope of Amendment No. 11 and this Exhibit A-11 is for the provision of professional services
provided by HDR Engineering, Inc. (HDR) for the Stillwright Point Community milling and
resurfacing project. Milling and resurfacing includes North Blackwater Lane, South Blackwater Lane,
Sexton Way, Stillwright Way, Center Lane, North Drive, and South Drive limits. A roadway milling
and resurfacing design will be conducted.The design will also include conducting the corresponding
permitting process with State Agencies. Construction Contract documents will be prepared for the
implementation of the milling and resurfacing project.
Proposal does not include bidding or construction services.
1. Task 1: Project Set Up and Data Collection
1.1. Surveying and Mapping: Using mobile LiDAR survey data to map out the present-day
roadway elevation and assort the roadway segments in order of roadway elevation. Review
and set up Survey CAD files that depict the ground surface information as well as the existing
Right-of-Way compatible with AutoCAD.
1.1 Deliverables:
Obtain the Survey CAD Filesconducted under the Stillwright Point Adaptation
Project. 1. Ground Surface depicting the existing surface features such as utilities,
buildings, and fences. 2. Right-of-Way depicting private property limits and
existing easements.3. Roadway elevations and existing Right of Wayelevations
and elevations 15 feet from the pavement edge.
1.2.Site Assessment and Condition Survey: Includes available pavement condition reports,
geotechnical, and other pertaining design information.
-4-
1.2 Deliverables:
Obtain pertaining data from the Geotechnical Report (Pavement Condition Report)
and information conducted under theStillwright Point Adaptation Project.
1.3. Environmental Assessment: Includes available environmental assessment conducted within
the project limits.
1.3 Deliverables:
Obtain pertinent data from the Environmental Site Assessment conducted under the
Stillwright Point Adaptation Project.
2. Task 2: Construction Contract Plan Development
Develop construction contract plans for the implementation of short-term roadway improvements.
Plan sheets should have a minimum scale of 1” = 40’.
2.1. Design
2.1.1. Roadway Design:
2.1.1.1. Typical Section Design
The CONSULTANT shall prepare the Typical Sections based on the corresponding
design criteria. Coordination will be conducted with the COUNTY for review and
approval of Typical Sections.
2.1.1.2. Pavement Design
The CONSULTANT shall produce and provide a milling and resurfacing Pavement
Design in the Contract Plans. The pavement design shall conform to the FDOT
Flexible Pavement Design Package requirements and the Stillwright Point
Geotechnical Investigation report. .
2.1.1.3.Horizontal/Vertical Master Design Files
The CONSULTANT shall design the geometrics using the Standard Plans that are
most appropriate with proper consideration given to the design traffic volumes, design
speed, capacity and levels of service, functional classification, adjacent land use,
adjacent flooding impacts to ROW or property, design consistency and driver
expectancy, aesthetics, existing vegetation to be preserved, pedestrian and bicycle
concerns, ADA requirements and scope of work.
2.1.1.4.Cross Section Design Files
The CONSULTANT shall establish and develop cross section design files in
accordance with the COUNTY’s CADD standards. Cross sections will be provided for
specific locations to validate any connection or grading impacts.
-5-
2.1.1.5.Traffic Control Analysis
The CONSULTANT shall design a safe and effective Traffic Control Plan to move
vehicular and pedestrian traffic during all phases of construction. The design shall
include construction phasing of roadways ingress and egress to existing property
owners and businesses, routing, signing and pavement markings, and detour quantity
tabulations, roadway pavement, front slopes, back slopes, anddrop offs within clear
zone. Positive drainage must be maintained at all times. The design shall include
construction phasing of roadways to accommodate the construction, adjustment, or
relocation of utilities.
The Traffic Control Plan shall be prepared by a certified designer who has completed
training as required by FDOT and the COUNTY. Before proceeding with the Traffic
Control Plan, the CONSULTANT shall meet with the appropriate COUNTY
personnel. The purpose of this meeting is to provide information to the
CONSULTANT that will better coordinate the Preliminary and Final Traffic Control
Plan efforts.
The CONSULTANT shall consider the local impact of any lane closures. When the
need to close a road is identified during this analysis, the CONSULTANT shall notify
the COUNTY's Project Manager as soon as possible. Proposed road closings must be
reviewed and approved by the COUNTY. Diligence shall be used to minimize negative
impacts by appropriate specifications, recommendations or plans development. Local
impacts to consider will be local events, holidays, peak seasons, detour route
deterioration and other eventualities.
2.1.1.6. Design Report
The CONSULTANT shall prepare a Design Report to document decisions and
establish design criteria.
2.1.1.7. Quantities
The CONSULTANT shall develop accurate quantities and the supporting
documentation, including construction days when required.
2.1.1.8. Cost Estimate - To be developed at 60%, 90%, and 100% design submittals.
2.1.1.9. Field Reviews
-6-
2.1.1.10.Quality Assurance/Quality Control
The CONSULTANT shall prepare Roadway plans, notes, and details. For review by
the COUNTYat 60% and 90%. The plans shall include the following sheets necessary
to convey the intent and scope of the project for the purposes of construction.
i. Key Sheet with street names and page numbers
ii. Summary of Pay Items Including Quantity Input
iii. Typical Section Sheets
iv. General Notes/Pay Item Notes
v. Summary of Quantities Sheets
vi. Project Layout
vii. Plan Sheet
viii. Special Details
ix. Cross Sections
x. Temporary Traffic Control Plans
xi. Temporary Traffic Control Details
xii. Project Control Sheets
The CONSULTANT shall analyze and document Signing and Pavement Markings
Tasks in accordance with all applicable manuals, guidelines, standards, handbooks,
procedures, and current design memorandums. The CONSULTANT shall prepare
Signing & Pavement Marking plans, notes, and details for review by COUNTY at 60%
and 90%. The plans shall include the following sheets necessary to convey the intent
and scope of the project for the purposes of construction.
2.1 Deliverables:
Electronic copy of plans, technical specifications, and engineer cost estimate
2.2. Utilities
The CONSULTANT shall identify utility facilities and plans from the Utility Agency Owners
(UAO) ensuring all conflicts that exist between utility facilities and the COUNTY’s construction
project are addressed.
2.2 Deliverables:
Documentation of the coordination and decision making with Utility Agency Owners.
Utility Work schedules for any adjustment or relocation of utilities.
2.3.Environmental and Permitting: Coordination with Permitting Agencies to implement
raising of the roadway with no drainage infrastructure while in compliance with allowable
requirements and criteria.
2.3 Deliverables:
Documentation of the coordination and decision making with Permitting Agencies.
-7-
Exhibit B-
Monroe County Roadway Vulnerability Analysis and Capital Plan
Stillwright Point Design, Permitting, and Contract Plans for
Milling and Resurfacing Project Delivery Schedule
Revised – September 15, 2025
The following tasks with associated delivery schedules are added through this Amendment. All other
tasks from Exhibit B in the original Agreement as well as Exhibits B-1, B-2, B-3, B-4, B-5, B-5A, B-
6, B-7, B-8, B-9, and B-10 in prior amendments, remain unchanged.
Required Services
Scope of Work (Deliverables) Amount Due Date
(Lump Sum)
Task 1: Project Set Up and Data Collection $6,136.40 October 31,
2025
Survey CAD Files. 1. Ground Surface depicting the
existing surface features such as utilities, buildings, and
fences. 2. Right-of-way depicting private property
limits and existing easements. 3. Roadway elevations
and existing right of way elevations and elevations 15
feet from the pavement edge.
Pavement Condition Report and information conducted
under the MC Vulnerability Study. Latest Geotechnical
Report depicting pavement coring information.
The Environmental Site Assessment conducted under
the Resiliency Long term project.
Task 2: Construction Contract Plan Development$59,616.42 April 20,
2026
Electronic copy of plans, technical specifications, and
engineer cost estimate.
-NT
P – Assumed for October 2025
-60% Submittal – December 22, 2025
-90% Submittal – February 16, 2026
-100% Submittal – April 20, 2026
D
ocumentation of the coordination and decision making
with Utility Agency Owners.
Documentation of the coordination and decision making
with Permitting Agencies.
-8-