HomeMy WebLinkAbout2022-97 EYW Bird Control Services 2026 Phase 1 MASTER AGREEMENT FOR PROFESSIONAL SERVICES
TASK ORDER FORM
Effective Date Task Order No. 2022 - 97
Client Project No.404-630230-530310-SC 00038 G3G04 Engineer Project No. _EGXM7931
This Task Order is entered into on the effective date noted above pursuant to the "Master
Agreement for Professional Services" between Monroe County, Florida ("Client") and JACOBS
PROJECT MANAGEMENT CO. ("Consultant"), dated February 16, 2022 ("Agreement"). The
Agreement is incorporated herein and forms an integral part of this Task Order.
Services Authorized—Bird Control Services —2026 Phase 1
Client authorizes Consultant to perform the Services described in Exhibit A attached hereto and
incorporated herein, which Exhibit A is marked with the above noted Task Order No. and
consists of 1 page(s).
Pricing
N/A Time and Expense per Agreement and Appendix B to the Agreement.
X Firm Fixed Price of$ 45,820.00
N/A Other(Describe): tD C
ScheduleµwcH, w+w ,-
Services may commence on Execution [ p U
Services will cease by 547 Days Date 12/1/25
Recommended by: Approved by:
Christine Digitally signed by
Ile r Christine Hurley
DateHurley07:4 39-052A3
C 07:45:39-05'00'
Director of Airports Date: 11.19.2025 Asst./County Adminstrator Date:
CONSULTANT: JACOBS PROJECT MANAGEMENT CO
Jacqueline �19��'lysl9� IIIIe�4Sel eRoss
By
oN:��=s,g,,eby Ross�=us.o=de�obs
labq-1 emss&—bs.—
_S.,. agreeto the terms--d by the
Witness Ross °la`e��totmy�9�et�reo�thl b�`���t Title Director of Operations
LocaOo¢PI lm Beach
Page 1 of 1
File: MSTR APES Monroe County
Exhibit A—(2022 - 97)
Scope of Services
Monroe County Airports
Key West International Airport
Bird Control Services—2026 Phase 1
SCOPE OF WORK
Jacobs Project Management Company will provide the services as outlined in the Fee schedule
and in Michael Baker International, Inc's. Exhibit A- Scope of Services and Fee Schedule.
Assumptions/Design Parameters
1. All work will be performed pursuant to the Master Agreement for Professional Services
between Project Management Co. and Monroe County, FL agreement signed between the
parties on February 16, 2022.
Page 1 of 1
JACOBS ENGINEERING GROUP JOB HOUR AND FEE ESTIMATE
Monroe County
Airport:
Key West International Airport
Project:
Bird Control Services- 2026 Phase 1
FEE SUMMARY
BASIC SERVICES
Hours Fee DBE AMOUNT
Article A: Bird Control Services 36 $ 5,792
Total Basic Services Lump Sum Fee $ 5,792 $
SPECIAL SERVICES Hours Fee DBE AMOUNT
Article A: Bird Control Services
Michael Baker International $ 40,028
Total Special Services Lump Sum Fee $ 40,028 $ -
TOTAL LUMP SUM PROJECT FEE 36 $ 45,820 $
DBE Percentage 0.00%
EXHIBIT
SCOPE OF SERVICES AND FEE ESTIMATE
MONROE COUNTY
KEY WEST, FLORIDA
KEY WEST INTERNATIONAL AIRPORT
2026 PHASE i - BIRD CONTROL SERVICES
Michael Baker International, Inc. (CONSULTANT), a Pennsylvania Corporation agrees to perform and
complete the following services(hereinafter"Services")for JACOBS('CLIENT').
TASK DESCRIPTION
This task provides for authorized "airport bird control" consulting services that is required by the
CLIENT to provide wildlife hazard management services to Monroe County, specifically at Key West
International Airport(EYW).These"airport bird control"services include the following tasks:
1) Falconry;
2) Depredation;
3) Wildlife harassment;and
4) Wildlife activities event report submitted via e-mail
The CONSULTANT's subconsultant Predator Bird Services, Inc. will provide bird control services at
EYW (Exhibit B ). The CONSULTANT will review bird control activities recommended by
the subconsultant for EYW to ensure compliance with EYW's United States Fish and Wildlife
Service Depredation Permit. The CONSULTANT will coordinate bird control activities with EYW.
SCHEDULE
The CONSULTANT will coordinate with the CLIENT and EYW and initiate bird control activities upon
receipt of authorization to proceed. Bird control services will be provided for 18 half-days, which is
divided into 2-day events fora total of 10 events.The breakdown of events is listed below:
Month No.of Events No.of Half-Days
April 1 2
May 1 2
June 1 2
July 2 4
August 3 6
September 2 4
TOTAL 10 20
2026 Phase i EYW Bird Control Services Michael Baker International
Page 1of2 September 23,2025
For the months of April through June, one 2-day event will be conducted per month. For July and
September, two 2-day events and for August three 2-day events will be conducted as these are when
there is an increase in bird population in the Florida Keys. EYW will provide access and an escort for
each event.
DELIVERABLES:
• Bird Control Event Summary Email
• Monthly Progress Report
COMPENSATION
Exhibit B provides for the manpower and expenses necessary to complete the outlined scope of work.
Actual billing will be based on percent completion of the project in accordance with the standard hourly
rates detailed in the Master Agreement between the CONSULTANT and the CLIENT.The CLIENT shall
compensate the CONSULTANT, a lump sum fee of FORTY THOUSAND TWENTY-EIGHT DOLLARS
AND FORTY-FOUR CENTS(540,028-44).
END OF SCOPE OF WORK DOCUMENT
2026 Phase i EYW Bird Control Services Michael Baker International
Page 2 of 2 September 23,2025
PREDAT ' :,R,
BIRD SERVICES, I I V C. IIYI'fA�7%t!%YY4�S iPo rP�dYp71161 Y'4tl r,—"x 5�rk.l"I
EXHIBIT B
Mariben Andersen
Associate Vice President
Michael Baker International
m,��de:-- _()mbakerit ll.com
C. (727) 560-6757
September 22,2025
Dear Mariben,
Thank you for contacting us regarding your bird control program. As discussed, below
are quotes for control services at EYW for 2026, focusing more heavily during Florida Keys
migration months. The program will be divided into two phases. Phase 1 will take place during
the months of January—September. Based on previous data and following migration patterns,
visits will occur 1-3x per month accordingly. These visits will be divided into 2-day stints to
disperse the effect of our program and track results. After the scheduled events in September,
the program and results will be evaluated to make any necessary adjustments for Phase 2.
Daily Bird Control Program:
2025 Half-day airport rate: $1,375.00
Price for Phase 1 —18 half-days of service: $27,500
Phase 1
Month No. of Events No. of Days on Site
April 1 2
May 1 2
June 1 2
July 2 4
August 3 6
September 2 2
Total 10 20
All work includes but not limited to: falconry, trapping, wildlife harassment. Pricing
includes any and all bird or wildlife removal requested each day. When necessary, we will shift
work time to after dark to eliminate roosts or nocturnal species.
PREDAT ' :,R,
BIRD SERVICES, I I V C. IIYI'o-A�7%t!%YY4�S iPo rP�dYp71161 Y'4tl r,—"x 5�rk.l"I
While mainly using falconry to supplement the current program in place, we use a
variety of different control methods as listed below, which can be used as necessary. All PBSI
staff will work from EYW operations vehicles when on-site, creating a fear of vehicles on the
airfield.
Additionally, we will work with EYW operations to determine the most effective
techniques to use when we are off site. All captured birds will be humanely euthanized and
buried in a designated area as determined by operations staff. Any listed species that are
captured will be reported with Airport Operations immediately.
All of our work is documented on a daily basis and reported via email at the end of each
period. Additionally, we submit weekly formal reports summarizing all of the daily work we
complete at Key West International Airport.
Thank you.
Robin Churchill
Vice-President
Predator Bird Services Inc.
lQhi.n_(a), redatorbirdservices.corn