HomeMy WebLinkAbout6th Change Order 06/05/2026 MONROF COUNTYANGINEERING/PRQJECT MANAGEmEmr
COWRACT CHANGE ORDER
PROJECT TITLE: Taxiway A Extension and Mitigation CHANGE ORDER NO: 6
INITIATION DATE: 06/14/2026
TO CONTRACTOR: Charley Toppino&Sons CONTRACT DATE: 11/1712021
The Contract is changed as follows:
The original Contract Sum ... ....... ......... ...... .......... ..........................$7,210,999.66
Net change by previously authorized Change Order . ........ ................. ........$914,65635
The Contract Sum prior to this Change order was......... ....... .......-$8,125,656.41
The Contract Sum is (decreased) by this Change Order 6. ......... ............ ........---.....($16,500.00)
The Revised Contract Sum including this Change Order ............... ............. ...............$8,109,156A1
Pay Item D-751-3 (Shoreline Protection Revetment - Mitigation Site 1) was billed in PA #3 (October 2025) and PA #4
(November 2025) at 75 tons each, for a total of 150 tons (100%to date). However, Pay Item D-751-3 does not appear to be
required for Mitigation Site 1 and was included as a token quantity only in the event it became necessary.
This Change Order will credit back a total of($16,500)for the amount charged to date for pay item D-751-3.
Net change to contract Change Order 6: ($16,600.00)
This Change Order 6 does not increase contract time.
Contractor agrees to accept the decrease in monetary compensation and hereby waives and releases any and all claims for
any additional compensation related to these bid items.
This Change Order 6 represents 0.0023% of the original contract price.
Not valid until approved by Owner, Architect if applicable), and Contractor
liplally sigrt B.
Robert B. Aydin,P.E.ned by Robe
DN ,=Robert B.Aydin,P.E.,
ARCHITECT/ENGIN R Aydin, P.E. -us
Date 2026.05.29 15:25:00-04'00'
11'11111'1"" I /Date
CONTRACTOR
1� bite
AIRPORTS DIRECTOR 06/03/2026
Digitally signed by Christine Date
Christine Hurley Hurley
COUNTY/ASSISTANT ADMINISTRATOR Date 2026.06.05 14 47 06-04'00'
Date
MONROE COUNTY ATTORNEY
�j ,APPROVE A RM
0
PE RD MERCADO
CHMr, TANT COUNTY ATTORNIty",-
DA, ---QaL25�
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ❑ No Z
If Yes, explanation:
• Change Order was included in the original specifications. Yes ❑ No Z
If Yes, explanation of increase in price:
• Change Order exceeds$100,000 or 5% of contract price(whichever is greater). Yes ❑ No Z
If Yes, explanation as to why it is not subject for a calling for bids:
• Project engineer/architect approves the change order. Yes 0 No ❑
If No, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No M
Should a claim under the applicable professional liability policy be made? Yes F1 No M
Explain: