Resolution 091-1987
Jeff Fisher, Director
Extension Services
RESOLUTION NO. 091 -1987
A RESOLUTION OF THE BOARD OF COUNTY COMMIS-
SIONERS OF MONROE COUNTY, FLORIDA,
AUTHORIZING THE MAYOR/CHAIRMAN OF THE BOARD
TO EXECUTE AN AGREEMENT BY AND BETWEEN
ADVANCED MARINE CONSTRUCTION (A/K/A PETER
JONES) AND THE BOARD OF COUNTY COMMISSIONERS
CONCERNING THE ARTIFICAL REEF PROJECT LOCATED
NEAR MARATHON, MONROE COUNTY, FLORIDA.
BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF
MONROE COUNTY, FLORIDA, that said Board hereby authorizes the
Mayor/Chairman of the Board to execute an Agreement by and
between Advanced Marine Construction (a/k/a Peter Jones) and the
Board of County Commissioners, a copy of same being attached
hereto, concerning the Artifical Reef Project located near
Marathon, Monroe County, Florida.
PASSED AND ADOPTED by the Board of County Commissioners of
Monroe County, Florida, at a regular meeting of said Board held
on the 3rd day of February, A.D. 1987.
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
o r-...... g;
u~ .---::--
BY: -r::~~,...-/
MAY HAIRMAN
(SEAL)
ATTEST:
..a~,t?~1~~
" E K
IIPPROVED AS TO FORM
AND L ,4L SUFFICIENCY.
f /
/~tf{Jm'?v's Office
r~\_1'
_____......L_._____..._____..___ ______~~.___ ___
AGREEMENT
THIS AGREEMENT made this 3rd day of February, 1987, by and
between ADVANCED MARINE CONSTRUCTION (a/k/a PETER JONES),
hereinafter called the "CONTRACTOR" and the BOARD OF COUNTY
COMMISSIONERS OF MONROE COUNTY, FLORIDA, of the County of Monroe,
State of Florida, hereinafter called the "OWNER."
WIT N E SSE T H:
That the CONTRACTOR and the OWNER for the consideration
hereinafter named agree as follows:
1. The CONTRACTOR shall furnish all the materials and
perform all the work as required by the Specifications for the
Artificial Reef Proj ect, located near Marathon, Monroe County,
Florida, a copy of which is attached hereto and made a part
hereof.
2. The work to be performed under the contract shall be
commenced within thirty (30) days from date OWNER provides Notice
to Proceed and to be completed within sixty (60) days of that
date. However, regardless of days in question, all work shall be
completed by the 1st day of June, 1987.
3. Further, the parties agree that if the Notice to
Proceed has not been given by OWNER to CONTRACTOR on or before
April 30, 1987, that this Agreement shall be null and void.
4. Further, the work to be performed under the contract is
contingent upon receipt of appropriate grant monies from the
State Department of Natural Resources, Artificial Reef Program.
In the event grant monies are revoked, this Agreement is null and
void. It is also agreed that the CONTRACTOR understands the
rules of the Department of Natural Resources, Artificial Reef
Program and will comply with said rules along with the rules and
procedures instituted by the OWNER to insure an orderly progress
to the project.
5. The OWNER shall pay to the CONTRACTOR for the perfor-
mance of the contract the sum of Fourteen Thousand, Eight Hundred
and Fifty ($14,850.00) Dollars upon completion by CONTRACTOR and
acceptance by OWNER, subject to terms and conditions of para-
graphs one through four above.
6. The attached Specifications and Plans together with
this Agreement, form the contract and they are as fully a part of
this contract as if herein repeated.
IN WITNESS WHEREOF the parties hereto have executed this
Agreement the day and year first written above.
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
By
Mayor/Chairman
(SEAL)
Attest:
Clerk
ADVANCED MARINE CONSTRUCTION
By
Peter Jones
Witnesses
APPROVED AS TO FORM /1
AND LEGAl.. SUr-FICIEPJc,Y. /__~~) /
. . I / ..... '-..I>-J'-<..I( ,
'. _...........'- (,. _.......----. V 1
'1'{ Attorney's Office .
2