Resolution 087-1984
. '
Art Skelly, Airport Director
RESOLUTION NO. 087-1984
RESOLUTION AUTHORIZING THE CHAIRMAN OF THE
BOARD OF COUNTY COMMISSIONERS OF MONROE
COUNTY, FLORIDA, TO EXECUTE AN ENGINEER'S
AGREEMENT BY AND BETWEEN THE BOARD OF COUNTY
COMMISSIONERS OF MONROE COUNTY. FLORIDA, AND
POST, BUCKLEY, SCHUH & JERNIGAN, INC.
RE: MARATHON AIRPORT A.I.P. PROJECT -02 FOR
$44,444.00 TO PREPARE AN UPDATED AIRPORT
MASTER PLAN FOR MARATHON AIRPORT.
BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF
MONROE COUNTY, FLORIDA, as follows:
That the Mayor and Chairman of the Board of County Commis-
sioners of Monroe County, Florida, is hereby authorized to
execute an Engineer's Agreement by and between the Board of
County Commissioners of Monroe County, Florida, and Post.
Buckley, Schuh & Jernigan, Inc., a copy of same being attached
hereto, in re: Marathon Airport A.I.P. Project -02 for
$44,444.00 to prepare an updated Airport Master Plan for Marathon
Airport.
PASSED AND ADOPTED by the Board of County Commissioners of
Monroe County, Florida, at a regular meeting of said Board held
on the 23rd day of March, A.D. 1984.
I
BOARD OF COUNTY COMMISSIONERS
OF MON~OE/C()UNTY, F~lIDA
\.t/ /\
.A~~/1..-- ~>\'/)~
By r \ ,--,_ r'----/
Chairman
(Seal)
At t est: DANNY L. KOLHAGE, Clerk
~'\~~ ~p~
~clerk
VED AS TO F~~~ LJ
GALSU~~
Attorney's Office
t '
•
•
. .
•
•
This document has important legal consequences: consultation with an attorney is encouraged with respect to its
completion or modification.
. - STANDARD FORM OF AGREEMENT •
BETWEEN
•
OWNER AND ENGINEER
• FOR
•
PROFESSIONAL SERVICES
•
•THIS IS AN AGREEMENT made as of January 19 84
between The' Board of County Commissioners of Monroe County, Florida
•
• ' (OWNER) and
. Post,. Buckley, Schuh & Jernigan, Inc.
•
•
•
(ENGINEER).
OWNER intends to prepare an Updated. Airport Master Plan for .
Marathon Airport •
•
•
•
(hereinafter called the Project).
OWNER and ENGINEER in consideration of their mutual covenants herein agree in respect of the performance
of professional engineering services by ENGINEER and the payment for those services by OWNER as set forth
below. •
ENGINEER shall provide professional engineering services for OWNER in all phases of the Project to which this
Agreement applies, serve as OWNER's professional engineering representative for the Project as set forth below
• and shall give professional engineering consultation and advice to OWNER during the performance of services
hereunder.
•
•
SECTION 1—BASIC SERVICES OF ENGINEER 1.2. Study and Report Phase.
After written authorization to proceed, ENGINEER
shall: - . -
1.1. General. •
1.2.1. Consult with OWNER to clarify and define
1.1.1. ENGINEER shall perform professional ser- OWNER's requirements for the Project and review
vices as hereinafter stated which include*.e4►sr er y- available data.
civil, atructura c,al g..
services.and customary architectural services inciden- 1.2.2. Advise OWNER as to the necessity of
tal thereto. • V OWNER's providing or obtaining from others data or
* planning
•
Page 1 of_1.4_pages •
8.2.3
EXHIBIT C
AIRPORT MASTER PLAN UPDATE
MARATHON AIRPORT
PROJECT BUDGET
AIRPORT MASTER PLAN UPDATE
MARATHON AIRPORT
PROJECT BUDGET (Continued)
EMPLOYEE(I) MAN-
WORK ELEMENT CLASSIFICATION RATE HOURS TOTAL COST
PHASE II -
AIRPORT PLANS
Element 6 - Airport Layout Plan 1 $43.00 10 $ 430.00
2 $39.00 20 780.00
3 $29.00 40 1,160.00
4 $22.00 10 220.00
Sub-total $ 2,590.00
Element 7 - Approach and Vicinity
Plan 1 $43.00 5 $ 215.00
2 $39.00 20 780.00
3 $29.00 40 1,160.00
4 $22.00 5 11 0 . 00
Sub-total 2,265.00
Element 8 - Terminal Area Plan 1 $43.00 10 $ 430.00
2 $39.00 20 780.00
3 $29.00 40 1,160.00
4 $22.00 5 110.00
Sub-tota 1 $ 2,480.00
Element 9 - Land Use Plan 1 $43.00 10 $ 430.00
2 $39.00 20 780.00
3 $29.00 40 1,160.00
4 $22.00 5 11 0 . 00
Sub-tota 1 $ 2,480.00
Element 10- Airport Access Plan 1 $43.00 5 $ 215.00
2 $39.00 16 624.00
3 $29.00 40 1,160.00
4 $22.00 5 110.00
Sub-total $ 2,109.00
(1)1 - Project Manager
2 - Planner/Engineer
3 - Technician/Draftsperson
4 - Administrative/Clerical
521/8C022784
EXHIBIT C
Page 2 of 4 Pages
(1)1 - Project Manager
2 - Planner/Engineer
3 - Technician/Draftsperson
4 - Administrative/Clerical
521/BC022784
AIRPORT MASTER PLAN UPDATE
MARATHON AIRPORT
PROJECT BUDGET (Continued)
EXHIBIT C
Page 3 of 4 Pages
AIRPORT MASTER PLAN UPDATE
MARATHON AIRPORT
PROJECT BUDGET (Continued)
EMPLOYEE(l) MAN-
WORK ELEMENT CLASS IFI CATION RATE HOURS TOTAL COST
PHASE V -
OTHER
Element 16- Printing(2) Lump Sum $ 3,000.00
Element 17- Public Hearings 1 $43.00 8 $ 344.00
2 $39.00 12 468.00
3 $29.00 12 348.00
4 $22.00 5 11 0 . 00
Sub-Total $ 1,270.00
'Element 18- Coordination 1 $43.00 10 $ 410 . 00
2 $39.00 15 585.00
3 $29.00 30 870.00
4 $22.00 10 220.00
Sub-total $ 2,105.00
Element 19- Study Design Development
1
2
3
4
$43.00
$39.00
$29.00
$22.00
5
20
20
10
$ 215.00
780.00
580.00
220.00
$ 1,795.00
Sub-total
Element 20- Administration 1 $43.00 5 $ 215.00
2 $39.00 20 780.00
3 $29.00 20 580.00
4 $22.00 10 220.00
Sub-total $ 1,795.00
Element 21- Travel Lump Sum $ 2,000.00
TOTAL $44,444.00
(1) 1 - Project Manager
2 - Planner/Engineer
3 - Technician/Draftsperson
4 - Administrative/Clerical EXHIBIT C
521/BC022784 Page 4 of 4 Pages