Loading...
Resolution 331-1983 Mr. Edward L. Stickney Director of Public Works RESOLUTION NO. 331 -1983 RESOLUTION APPROVING CHANGE ORDER NO. 2 AND CHANGE ORDER NO.4 AMENDING THE CONTRACT BY AND BETWEEN UPPER KEYS MARINE CONSTRUCTION, INC. AND MONROE COUNTY, FLORIDA, COVERING DELETIONS AND ADDITIONS TO SAID CONTRACT DUE TO THE DELAY OF THE FLORIDA KEYS AQUEDUCT AUTHORITY IN AWARDING A WATER LINE CONTRACT FOR THE INSTALLATION OF A NEW WATER LINE ON THE PERMANENT COPA D'ORO BRIDGE. WHEREAS, Monroe County, Florida, previously entered into a contract with Upper Keys Marine Construction, Inc. for the permanent replacement of Copa D'Oro Bridge, Monroe County, Florida, and WHEREAS, after the contract letting and during construction it has been brought to the attention of the County Engineers, Post, Buckley, Schuh & Jernigan, Inc., that said Contractor is unable, through no fault of his, to complete said contract with respect to pavement, pavement marking, installation of said cement rip-rap, nor can he remove the Temporary Bridge (which has the temporary water line on it), which is a necessity prior to the restoration of private property due to a delay by the Florida Keys Aqueduct Authority in authorizing the work necessary to remove the water line from the Temporary Bridge, and to install a new water line on the new Permanent Bridge, and WHEREAS, Upper Keys Marine Construction, Inc. has issued Change Order No. 2 and Change Order No.4 to cover the necessary deletions and additions in order to complete said project and submitted said Change Orders to the Board of County Commissioners of Monroe County, Florida, for its approval, now, therefore, BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF MONROE COUNTY, FLORIDA, as follows: 1. That said Board of County Commissioners hereby approves Change Order No.2 and Change Order No.4 to that certain con- tract entered into by and between Monroe County, Florida, and Upper Keys Marine Construction, Inc. for the permanent replace- ment of Copa DIOro Bridge in Monroe County, Florida. 2. That said Board also approves and authorizes the adjustment to be made in the Contract Price and Time as contained in said Change Order No. 2 and Change Order 4. Passed and adopted by the Board of County Commissioners of Monroe County, Florida, at a regular meeting of said Board held on the 23rd day of November, A.D. 1983. BOARD OF COUNTY COMMISSIONERS OF MONROE COUNTY, FLORIDA By ~.. ~...- ... . "'-- t..v U ~ - Mayor/Chairman ~ ,-- (Seal) Attest: D~ L. KOLHAG~ C~erk ,~ "~M. ~,D.e o Clerk 'fl.."'t APPROVED AS TO FORM AN. AL SUFFICIENCY. BY 2 t 1 B Po ckley, ;huh & Jernigan, Inc.• _ • s j CONSULTING ENGINEERS and PLANNERS 10 PALMS PLAZA,HOMESTEAD,FLORIDA 33030-6094 • 305/248-4750 • TELEX 808435 November 15, 1983 • Mr. Edward L. Stickney, Director • Monroe County Public Works Department P. O. Box 1029 . Key West, Florida 33040 RE: Change Requests #2 and #4 for the Copa D'Oro Bridge Projects • Dear Mr. Stickney:• • Enclosed for your further processing is Change Order #2 (Project Number 401-002.14K, Copa D'Oro Permanent Bridge) and Change Order #4 (Project Number 401-002.14J, Copa D'Oro Temporary Bridge). These change orders are submitted together as a package, and represent a no cost Transfer of Funds and work requirement from one contract to another contract. In general, the contractor is unable to complete Copa D'Oro Permanent Bridge on schedule due to the delay in awarding a water line contract (for installation of a new water line on the permanent Copa D'Oro Bridge) by the Florida Keys Aqueduct Authority. We have therefore recommended that those items in contract #401-002.14K, Copa D'Oro Permanent Bridge, that are contingent upon the Aqueduct Authority Contract be deleted from the Permanent Bridge Contract and added to the removal portion of the Temporary Bridge Contract (#401-002.14J), and that. the Permanent Bridge Contract be recorded as completed on schedule. We have discussed the legality of this proposal for change of funding with Mr. Proby and he is inclined to agree that it can be accomplished. We therefore recommend that the Commission approve these changes as being in the best interest of Monroe County. Very truly yours, POST, BUCKLEY, SCHUH & JERNIGAN, INC. as MONROE COUNTY CONSULTING ENGINEERS By: H. L Swanson, •.E. Project Manager ' HLS/lvc 401-002.14J a'.1 i � q 401-002.14K e ,.. �.,f 1.1 Enclosures NOV 17 1983 cc: 1 Lucien Proby w/encl: Kermit Lewin w/encl• COUNTY A 1Y• CH, 3E ORDER NO. 2 • Project Title: Job No. Bridge Replacement Permanent 401 -002 . 14K Copa D ' Oro Bridge Contractor: " Contract Date: Upper .Keys Marine Construction , Inc . " April 2,9 , 1983 To: Upper Keys Marine Construction , Inc . P . O . Box 18AAA , Key Largo , Florida 33037 You are directed to make the changes noted below in the sub' co a t: z , Attest: By: war is ey Date: Title: Di •ector , 'P blic Works Dept . Approved As To Correctness and - Form U.) .. - , /l By: ,,�c,c _ �.,�; _ / t 4 Attorney for Monroe County' / VNI Nature of the Change:- SEE ATTACHMENT - • The changes result in the following adjustment of Contract Price and Time: Contract Price Prior to this Change Order: $2 3 4 , 0 8 5 . 6 0 Net ( H6) (Decrease) Resulting from this Change Order: • 7 , 627 . 60 Current Contract Price Including this Change Order: 226 ,458 . 00 Contract Time Prior to this Change 'Order: 180 d a s Net'(Increase) (Decrease) Resulting from this Change Order: -0- Current Contract Time Including this Change Order: 180 days Prepared by: Richard C . P e p e r Post,'Buckley, Schuh 8c Jernigan, Inc. as Monr .S onsulting Engineers Date: November 15 , 1983 . By: H . Lee Swa son , P . t . , Project Tgr . The boy h es a •ted: Attes • di/,l 'au7 0-e.4.(xl--- Date: n ag/4./,,,: Title: "'� _., G_C/#18 Cli,' "3E ORDER NO. 4 . • an- • Project Title: Job No. Bridge Replacement (By- Pass ) 401-002 . 14J Copa D' Oro Bridge Contractor: Contract Date: Upper Keys Marine Construction, Inc . May 3 , 1982 To: Upper Keys Marine Construction , Inc . . P . O . Box 18AAA , Key Largo , Florida 33037 You are directed to make the changes noted below in the subj ct contrac Attest: By: war L . Stic ey Date: Title: Director , P bl is Works Dept . Approve- .As To Correct ess and Form By: Attorney for Monroe County Nature of the Change: SEE ATTACHMENT The changes result in the following adjustment of Contract Price and Time: • Contract Price Prior to this Change Order: $13 9 0 2 5 . 0 0 Net (Increase) (I/d(cli.?4KM Resulting from this Change Order: 7 ,627 . 60 Current Contract Price.Including this Change Order: 146 , 652 . 60 Contract Time Prior to this Change Order: 150 d a s - Net (Increase) (Decrease) Resulting from this Change Order: -0- Current Contract Time Including this Change Order: 150 days Prepared by: Richard C .. P e p e r Post, Buckley, Schuh & Jernigan, Inc. as Monro o ty nsulting Engineers Date: November .15 , 1983 By: . Le wanson , P . E . , Project Mgr . The Above C es ar ted: Attest• A�. Date: l ', / ^/ �3 Title: GC/#18. • • ATTACHMENT REFERENCES AND BACKGROUND Job Number 401-002.14J is a Monroe County Contract with Upper Keys Marine, for the installation and subsequent removal (after completion of the Permanent Bridge) of the Copa D'Oro (By-Pass) Bridge. Under this contract the FKAA installed a temporary •• water line on the Temporary Bridge. Job. Number 401-002.14K is a Monroe County Contract with Upper Keys Marine for the construction of a Copa D'Oro Permanent Bridge, and the restoration of private property after removal and return of the Temporary Bridge. Job Number (unknown) is a contract awarded November 9, 1983, between the Florida Keys Aqueduct Authority, and Upper Keys Marine Construction for the removal of the temporary water line from the Temporary Copa D'Oro Bridge, and the installation of a permanent water line on the Permanent Copa D'Oro Bridge. NATURE OF THE CHANGE Because of the delay by the Florida Keys Aqueduct Authority, in authorizing the work necessary to remove the water line from the Temporary Bridge, and to install a new water line on the new Permanent Bridge, the contractor is not able to complete his contract in full for the construction of the Copa D'Oro Permanent Bridge by November • 14, 1983. The Permanent Bridge structure is complete. Until, however, the installation of the new permanent water line on the new bridge is complete the contractor cannot complete the contract with respect to pavement, pavement marking, installation of sand cement rip-rap, nor can he remove the Temporary Bridge (which has the temporary water line on it), .which is a necessity prior to the restoration of private property. To correct this situation, which is no fault of the contractor, Upper Keys Marine, the contractor has recommended that the following items be deleted from Job #401- 002.14K, Contract for Construction of the Copa D'Oro Permanent Bridge, and added to Job #401-002.14J, Contract for Construction and Removal of Copa D'Oro Temporary (By-Pass) Bridge. Item #1.1 1367.SY of Type S-1 Asphaltic Concrete Surface.Course at $2.80/SY $3,827.60 Item.#13 65 SY of Sand Cement Rip-Rap at $50.0.0/SY $2,800.00 Item #14 Restoration of Private Property $ 500.00 Item #15 Pavement Marking $ 500.00 $7,627.60 • This proposal would allow the contractor to essentially complete his contract on the permanent bridge which is now being held up by the late contract award by the Florida Keys Aqueduct Authority and in addition would: (A) Allow for the pavement of the new approach roadways after completion of a portion of the water line installation, rather than paving it now, and then cutting and patching it to install the water line when that contract is finally put into operation. The plan would be to tap into the existing water lines at each end of the bridge project, install the PVC portion of • the new water line up to the bridge itself (where it becomes steel pipe) and pave over this installed portion of the water line (see sketch). (B) As an added incentive, the . contractor has agreed. to remove the Temporary Bridge and return to the State prior to January 1, 1984, thus saving the County the cost of an additional month's rent on the Temporary Bridge. . We recommend that these change orders be approved, and that the funds in the amount of $7,627.60 be deleted from Job #401-002.14K, Copa D'Oro Permanent Bridge and added to Job #401-002.14J, Copa D'Oro Temporary (By-Pass) Bridge. It is anticipated that Contract 401-002.14K, Copa D'Oro Permanent Bridge would be completed as far as possible by November 14, 1983 and that Contract 401-002.14J would be completed no later than January 15, 1984. . i RCP/lvc 401-002.14J . 401-002.14K GC #26 • • • • • • • L ,< /6.54 . • x< • ; .max-. R 23 G• G Kew' 'L v r;� CT/ON - :O'URSE RD.' EL. 2.49 SO -# ��- avy cam, ceo `{�. j • r �` i R. G f ARE4 O PR/VA s PROPERTY 1 '` AREA OF PR/V4 TE PROPERTY • �h 5 � // y TO 6E ESTOR TO OR/G/NA -- ; , TO BE RESTORED TO '� W �R� l D COND/4T/ON cot) I \ j %Ye 55 BRIDGE 70 BE lice. EN !4 ��� f \>. 1 ORIGINAL COMO/RON O � G : r�1 N �I • q I� • �, Y W MOVEOD(BPARTEOP7W/S CONT•A• a>1.�4r�B/s�R�ogrRR,` i �FCN[[L/Ni !Sf aI N/M rlt o��/ h EXIST.P4[�EMENT rtl l9 2 Z O �! • - • 4 r-� �57041,gi Ma J ' c' FA✓EN vg-O r/ST) 1h TO BE REMOVED l — - _� -_ Q-- _ n_ (] .1 ��i -J • i 13� Hem :/L01 — — — — — —N c 11 Q 11 i N I • —Z—— — — i—= N :-- EX. 70 6E R �� �- 9 I • • ti II kt. II 1 o. 1 ii 1 can . I� _— 3• -, _ _ — t�C`� ; I �4 .II O orPll ok I Q I OS.yJ / _ 41 _W_� - F�` BYPASS BR/DBE 1f �•��I ' �} N 11 j l7 Ir '� I rEEL'. • / �'S h� \Q II O 1 0 Q 1 it . II_Q- • L.P. ogAILG a �' :: 3• ..,. k _ . - • - - y`�- I z,t j W u lI t I, REt IN �.���f ,■'. Ir. - • eti Hrs. G J 5t .5 0 W\d f _ _ — —=-ttl- ——— • R o cL.-- �. ,.. .• z,..z -r).•-I sue-- - piFS N pd BAR .,, 4�' R/W• LINE. { PP I� "ws/ 67, `� 'F L � YEN ■�ww..- _ PROP-6 iY-M.('BYOTHERS) *��'�• `" �� � L, p . MCI ► + s zt z, W PROP. BR/DGE �i// � � x �zz� .r R t IAA • E1 )-\� �C3 ` �+ OF ) L' �� N -- 7 EooE STRIPE. `'� i PG:L. �= P of :::4:::;:::�u� 0� �� r ..: +•pE /LP ��` ,...s - a`� i@� ,s istM :� •EAC L�NE rN rT , siBLE: a \ - ---- • ���� n - ' `606E-OFPgV'T a a 22 _4, �� �V✓ 2D°/C7 tJO'E <j v} O- mw . ` SURVEY = .¢ . h 7AL r�Xd�T'} F 1: NOD bt ... .. :.:. _ ... .. L..., - r��I EX 3TI T p•OF BANK �`�--� -- - i... {:.4%! i. DOUBLE `^ O � • ,j WHITE -�5- +—I/� _� / . •P.P. , • 0 11�! r+; YELLOIV � , 37Z EXIST. BR/DGE ��' �'` ■��� •+. O EDGE STR/PG � / (APPROX. LOCAT/ON) d L.11II. ii. kg ----- _L IMF Il�f q'. �11� ...4‘111111111111111 _ TO BE REMOVED •�_"' 1�1111 • STi`?/P//VG O T,4 O (T'Y/ ) `-- - a.nn uno 0 �� 1 D , ENO BRIDGE ro�_I{4 Ivy— h , if 1 paLK STA. 22 f 90.00 STOP BAR W VAR/ES CONST. 25 L.F. OF sreEL POsr a ? 1 7• - Sr ME5S,gGEDET,Q/L. (B=o'M,4X.) sH� QQ % GUARDRAIL, SEE SHTS.3{6 O J ` gX ` W �.� ' AlOTES: • (F.D.O.T22S.e) , ' / BEG/N BR/DGE • o h k x • • STA. 2/ f 50.00 o a .a� Q • Q . ' . /)ALL TRAFFIC SIGNS t1 / I O _ - - _ z W/TH/N L/M/TS OF PROJECT N. I_ 1 .__ I. .-.-_1 �.v1____— O TO BE RELOCdTEO. . 2)PORT/AL STRIPING JHCkVN • 4:/ jt ON PLAN FOR[L4R/7 yDOUBLE NATURAL 'GROUND- . I