Resolution 099-1983 RESOLUTION NO. 99 -1983 RESOLUTION APPROVING CHANGE ORDER NO. 1 AMENDING THE CONTRACT BY AND BETWEEN UPPER KEYS MARINE CONSTRUC- TION, INC. AND MONROE COUNTY, FLORIDA, BY PROVIDING FOR THE FILLING OF VOIDS EXISTING UNDER THE BRIDGE ABUTMENTS OF DUCK KEY BRIDGE NO. 4 IN ORDER TO PRE- SERVE THE INTEGRITY OF THE FOUNDATION. WHEREAS, Monroe County, Florida, previously entered into a contract with Upper Keys Marine Construction, Inc. for the con- struction of Duck Key Bridge No. 4 located in Monroe County, Florida, and WHEREAS, after the contract letting and during construction it was determined that voids existed under the bridge abutments for the subject bridge and that these voids should be filled in order to preserve the integrity of the foundation, and WHEREAS, the County has issued Change Order No. 1 to cover the above described additional work and submitted said Change Order to the Board of County Commissioners of Monroe County, Florida, for its approval, now, therefore, BE IT RESOLVED BY THE BOARD OF COUNTY CO~1ISSIONERS OF MONROE COUNTY, FLORIDA, as follows: 1. That said Board of County Commissioners hereby approves Change Order No. 1 to that certain contract entered into by and between Upper Keys Marine Construction, Inc. and Monroe County, Florida, for the filling of voids with concrete existing under the bridge abutments in order to preserve the integrity of the subject bridge. 2. That said Board also approves and authorizes the adjust- ment to be made in the Contract Price and Time as contained in said Change Order No.1. Passed and adopted by the Board of County Commissioners of Monroe County, Florida, at a regular meeting of said Board held on the 15th day of April, A.D. 1983. (Seal) ?!I'..~"~.~7 n U DU U~ ~' ; '/' 1\1'\1.1 n \'J. '!ili il~. · '"" ~.~ '!"'i"";~l l:,.l.':' ~~..\ BOARD OF COUNTY COl1MISSIONERS OF MONROE OUm'y,-FL?IDA~~ By ~y, Chairman ,f ;f ;"".',' ~ 6:;.~ .".;:' . /7 .... .-JJ'~ Attest: ~. :uJ.w Clerk APPROVED AS TO FORM 8Y ZGAL SUF~CIENCY. Attorney's {fiet? , :. \ '" . 1)\" ) I ," I F.~~"-'-:----~~~ Il'rojcct Tl tie: , Renovation and Upgrading \ Duck Key Bri dge #4 ..;c.u '..'.401-002. 'VOl r Contractor: Upper Keys Marine Construction, Inc. Contract Date: December 15, 1982 ITo:Upper Keys Marine Construction, Inc. ' I Box AAA Key Largo, Florida 33037 You are directed to make the changes noted below in the sub' By: I Attest: I IIDate: 1 i c sand t I Nature of the Change: :Based on ou~ inspection of the holes drilled in the bridge foundations, it has ibe~n determlned that v~ids exist under the bridge abutments for the subject ;~rldge: we have determlned that these voids should be filled to preserve the lntegrlty of the foundation. I I " I IThe changes result in the following adjustment of Contract Price and Time: Contract Price Prior to this Change Order: Net Increase Resulting from this Change Order: Current Contract Price Including this Change Order: Contract Time Prior to this Change Order: Net Increase Resulting from this Change Order: Current Contract Time Including this Change Order: $220,321.00 $ 1,980.00 $222,301.00 240 Days o ,Days 240 Days Prepared by: Richard C. Peper I !Date: 21 March 1983 I Post, Buckley, Schuh &. Jernigan, Inc. ~~onr! ~,ty ~z~ult~~~~ers H.~ee'swans n P~~~ ;~~i::;; MrlniH1Pr ccepted: . * aa?CT7~ Title: {i ~ 1/ f: . Date: