Resolution 265-1978 RESOLUTION NO.265 -1978 A RESOLUTION AUTHORIZING THE MAYOR AND CHAIRMAN OF THE BOARD OF COUNTY CO~1ISSIONERS OF MONROE COUNTY, FLORIDA, TO EXECUTE CHANGE ORDER NO.2 FOR PROJECT 78139-109 NORTHSIDE DRIVE BY AND BE- TWEEN THE BOARD OF COUNTY CO~1ISSIONERS OF MONROE COUNTY, FLORIDA, AND CHARLEY TOPPINO & SONS, INC. BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF MONROE COUNTY, FLORIDA, as follows: That the Mayor and Chairman be authorized to execute Change Order No. 2 for Project 78139-109 Northside Drive by and between the Board of County Commissioners of Monroe County, Florida, and Charley Toppino & Sons, Inc., a copy of same being attached hereto. Passed and adopted by the Board of County Commissioners of Monroe County, Florida, at a regular meeting held on the 24th day of October, 1978. BOARD OF COUNTY COMMISSIONERS OF MONROE COUNTY, FLORIDA Be~~' ayor-an alrman Attest:-) ~.) a-- L;;~/2vtl- ) , Clerk (Seal) By I HEREBY CHUfFY that this document has been reviewed for legal suffi- ciency and that the same meets with my approval. a~?LL/~L .'/ ,/ " . -- /~ . / ll..::. _ Attorney's Office . ~ " . RSH 27 (7.811) . CONTRACT CHANGE ORDER NO. 2 'DATE September 2S, 19~ PROJECT NAME Northside Drive - Key West Charley Toppino and Sons, Inc. FILE NO. 7 S139 -1 09 CONTRACTOR WORK UNDER THE ABOVE PROJECT SHALL BE CHANGED AND THE.CONTRACT COST ADJUSTED IN THE FOLLOWING RESPECTS: 1. Omit Structures D14, D15, D16 and D17 and adjust tops of existing inlet to match proposed new grades. ........ ..Deduct $ 2,772.00 Omit Structure B3 . . . . . . . . . . . . . . . . . . . . . . . . Deduct Omit Structure B5 . . . . . . . . . . . . . . . . . . . . . . . . Deduct Omit Structure B4 . . . . . . . . . . . . . . . . . . . . . . . .Deduct 5. Omit Handrail on B4 ............ .... ..... .Deduct 1,200.00 6. Omit 42" pipe from B4 to.B6. 152' of 42" pipe on site to be picked up by owner ..... ........ ..Deduct 5,619.00 7. Omit 165' of IS" pipe from B3 to B5 and add 12S' of IS" pipe from B2 to B6 .... ...... ............... .Deduct 63S.00 Total Deductions $23,19S.00 ORIGINAL CONTRACT AMOUNT719,958.75 SCHEDULE OF ADJUSTED COST' CONTRACT AMOUNT BEFORE THIS CHANGE ADD DEDUCT CONTRACT AMOUNT AFTER THIS CHANGE 620,116.05 4627.00 23,19S.00 $601,545.05 CHANGE APPROVED: ..} ; .~ J I (;' C/ '=-~.~ -~--/) ..~ FOR CONTRACTO~ ,..'L- P-L-i., \. ~ - l~ , ~t..-,""",-..(.,) FOR OWN ER " I' , ! Page 2 Contract Change Order No.2 · Northside Drive-Key West, Florida File No. 78139-109 Charley Toppino and Sons, Inc. September 28, 1978 8. Move structure C9 to 5 feet north of centerline and connect C8 to C9 and C9 to B6 with 112 feet of additional 24 inch pipe ........... ....... ... Add $2,688.00 9. Provide connections to existing structure and de-water at B6 ............................... Add 1,000.00 10. Cost of 4,361 pounds of reinforcing steel and casting on site to be picked up by owner ..... Add 939.00 Total Additions $4,627.00