Change Order No. 01-025-001
C H A N G E 0 R D E R
Project:
Change Order Number: 01-025-001
KJ - NEW DETENTION FACILITY
To Contractor: LYLE PAINTING & COATING, INC.
2635 NW 4TH STREET
FORT LAUDERDALE, FL
33311
Change Order Date: 08/05/93
Architect's Project #:
Contract For:
PAINTING & WALLCOVERING
Contract Date:
07115/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 068 - POMCO DELAY
In accordance wi th the Apri l 9, 1993 updated master schedule and Paragraph 8.3.1 of the -l;ontract \C5
Supplementary General Conditions, the Contract Substantial Completion Date is extended @)No~~r VJ
1, 1993 at no additional cost, due to project delays resulting from the fabrication and~ect1pn of
the precast concrete. :::2 c " ~
-0
N
CO
-'1
nol
,-,
, .--'
''I'
,J
:;::::::
-;
'-D
~
i'-)
~~......
,....1
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 0.00 and 123 days.
The Original Contract Amount was......... ........... ..... ............ ............................... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Value of this Change Order is ..... ................ ...................... ......................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time will change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
~
270,545.00
0.00
270,545.00
0.00
270,545.00
123 days
11/01/93
~h
AV : Danny L. Kolhage, Clerk .
By ~o.bL c.. ~~~~
Deputy Clerk
~9~t:JI-f.3
Agreed to by Contractor:
Authorized by Owner:
INC. /
FORT LAUDERD, 33~;::'" /.
~ -:7~ - 08L!LA3
~ Date .
By
County Commissioners
Approved As
Date
By
Date
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.
,-